Road Concreting - Sample Estimate
Road Concreting - Sample Estimate
Total 1,661,962.35
BRGY. POBLACION ILAWOD
ITEM 105 - SUB-GRADE PREPARATION
Area = 1,210.00 sq.m 50.00 60,500.00
Materials 60,500.00
Labor 2,722.50
contingencies 1,391.50
Overhead and Supervision 1,996.50
Contractor's Profit 2,601.50
VAT 2,722.50
TOTAL 71,934.50
Unit Cost 59.45
ITEM 200 - AGGREGATE SUB-BASE COURSE
volume = 121.00 cu.m 800.00 96,800.00
Materials 96,800.00
Labor 4,356.00
contingencies 2,226.40
Overhead and Supervision 3,194.40
Contractor's Profit 4,162.40
VAT 4,356.00
TOTAL 115,095.20
Unit Cost 951.20
ITEM 201 - AGGREGATE BASE COURSE
volume = 254.10 cu.m 700.00 177,870.00
Materials 177,870.00
Labor 8,004.15
contingencies 4,091.01
Overhead and Supervision 5,869.71
Contractor's Profit 7,648.41
VAT 8,004.15
TOTAL 211,487.43
Unit Cost 832.30
ITEM 311 - PORTLAND CEMENT CONCRETE PAVEMENT
Area = 726.00 m2 145.20
Portland Cement 1,306.80 bags 205.00 267,894.00
Washed Sand 72.60 cu.m 850.00 61,710.00
Washed Gravel 145.20 cu.m 650.00 94,380.00
Deformed RSB 16mm x 6.0m 36.30 pcs 230.00 8,349.00
GI Tie Wire #16 7.26 kg 65.00 471.90
432,804.90
Materials 432,804.90
Labor 19,476.22
contingencies 9,954.51
Overhead and Supervision 14,282.56
Contractor's Profit 18,610.61
VAT 19,476.22
TOTAL 514,605.03
Unit Cost 708.82
SPL.1 - ROAD MONUMENT /PROJECT MARKER
= 1.00 lot 0.90
Portland Cement 8.10 bags 205.00 1,660.50
Washed Sand 0.45 cu.m 850.00 382.50
Washed Gravel 0.90 cu.m 650.00 585.00
Rebars 25 pcs 230.00 5,750.00
GI Tie Wire #16 25 kg 65.00 1,625.00
10,003.00
Materials 10,003.00
Labor 450.14
contingencies 230.07
Overhead and Supervision 330.10
Contractor's Profit 18,610.61
VAT 450.14
TOTAL 30,074.05
Unit Cost 30,074.05
SPL. 1 - Technical Supervisor
= 1.00 lot 7,500.00 7,500.00
Materials 7,500.00
Labor 337.50
contingencies 172.50
Overhead and Supervision 247.50
Contractor's Profit 322.50
VAT 337.50
TOTAL 8,917.50
Unit Cost 8,917.50
Total 952,113.70