Application of Value Engineering in Commercial Building Projects
Application of Value Engineering in Commercial Building Projects
Abstract- The current construction industry conditions have entailed the use of rational method and techniques and
research and application of new techniques by utilizing advancements in technology in the field of production as well as in
every field. Value Engineering is a proven management technique that can make valuable contributions to value
enhancement and cost reduction in construction industry. Value Engineering is one of the most effective techniques
known to identify and eliminate unnecessary costs in product design, testing, manufacturing, construction, operations,
maintenance, data, procedures and practices. The methodology is composed of three main stages. The first stage is the
Pre-Study of the Value Engineering. The purpose of this stage is to plan and organize the value study. Value Engineering
is the systematic application of recognized techniques that identify the functions of the product or service, creatively
establish the worth of those functions, and provide only the necessary functions to meet the required performance at the
lowest overall cost. Value Engineering focuses on accomplishing the required functions at the lowest overall cost. It helps
in eliminating or minimizing wastage of material, time, and unnecessary cost, which improves value to the customer. The
second stage is the Value Study which is the core of Value Engineering study and it is composed of five phases, the
Information phase, Function Analysis Phase, Creative Phase, Evaluation Phase and the Presentation phase. All phases
and steps perform sequentially. Such sequence of the methodology is expected to assist in logical and systematic flow of
the process to achieve the targets of the VE study. The third stage is the Post Study. The objective during post-study
activities is to assure the implementation of the approved value study change recommendations. In this study, how the
principles of Value Engineering are applied in construction projects is explained, and by taking case study on commercial
building as the sample project, practices of Value Engineering in this project are described.
Keywords – Value Engineering, Functions Analysis, Cost, Quality aspects of a project, Value Analysis.
I. INTRODUCTION
Value Engineering is a systematic study to seek out the best functional balance between the cost, reliability and
performance of a project. It can be defined as a systematic interdisciplinary examination of various factors those
affect the cost of a project or service in order to device means of achieving the specified purpose most economically
at the reduced standards of quality and reliability. Value engineering is basically a team effort. It aims at
promotion of value awareness and raising the level of professional competence and technological excellence in the
organization. Value engineering not only aims at cost reduction but also cost effectiveness which in turn enhances
the value and provides competitive advantage. Value engineering techniques can be applied wherever cost is
proposed or likely to be incurred in terms of money, skills/expertise, energy or other resources. In other words, this
will cover practically every area of human activity and value engineering can be considered applicable to all of
them. value engineering is applicable to hardware, building or other construction projects and to soft areas, such as
manufacturing processes, administrative and management systems, office procedures, books and forms and
computer software costs. In case of once through projects such as civil engineering works for example, buildings,
highways, water/air/effluent treatment plants, etc and engineering projects such as product design, greater benefits
from the application of Value Engineering can be obtained by application of these techniques at the early design
stages. Adequate data collection in such studies is essential together with in depth involvement of the agencies
dealing with the finance, design, construction and use of the project. A project may require several teams to work
simultaneously on different aspects such as, structural design, layout, subsystem services, etc
Value engineering studies in soft areas are those which concern manufacturing processes and
administrative procedures. A sequence flow chart of activities and times using standard industrial engineering
techniques is essential. Details of material loss, low yield, wastages, rejection, rework, loss of man/machine hours,
etc, together with their costs, are equally essential as part of the data to be collected during the information phase of
the value engineering study. [1]
Value engineering results in the increased use of alternative less expensive material, cheaper design, weight
reduction, new methods of manufacturing, indigenization, etc, to give the same or better performance, quality and
efficiency at a lower overall cost. In order to produce a product or service to be competitive in the open market, the
best value is determined by two considerations, namely, function and cost of product. Value of a product or service
can be enhanced either by increasing the function or decreasing the cost or both while maintaining the performance
quality and reliability. [2]
Tae Hyung Kim Hyun Woo Lee, and Seok Woo Hong (2015)[5], concluded that applying a systematic value
engineering process can be beneficial to develop cost effective design alternatives. Value Engineering studies
specifically targeting for this problem are absent from the field. Thus, the goal of this study is to supplement this
knowledge gap by applying a systematic value engineering process to an expansion project on soft ground to
demonstrate the benefits of performing value engineering.The value engineering process and design alternatives as
applied in this study are expected to serve as a guideline for engineers and decision makers in roadway expansion
projects on soft ground.
Sungwoo Moon, A.M. Chideok Ha, and Jinkook Yang (2012)[6], said that value engineering is an effort to increase
the value of a system through a creative and organized approach. Idea generation is the most important part in a VE
job plan. Although the experts in a value engineering team can evaluate multiple alternatives that can replace the
original idea, idea generation is usually on the basis of their knowledge and experience.
used to further enhance the product and respond to changing customer and economic conditions. A value
methodology can be used to either develop new ways to manufacture a product or change an existing process.
x Business systems and processes may also be the subject of Value Studies. Many elements of a business or an
organization may be improved through the application of a value methodology. This may be from the
development of business plans and organizational studies to improving existing business processes.
Value methodologies may be applied more than once during the life of the project. Early application of a
value methodology helps to get the project started in the right direction, and repeated applications help to refine the
project’s direction based on new or changing information. The later a Value Study is conducted in project
development, more likely implementation costs will increase. A value methodology may be applied as a quick
response study to address a problem or as an integral part of an overall organizational effort to stimulate innovation
and improve performance characteristics. Value methodologies may be used to enhance an organization’s quality
programs, new product development activities, manufacturing processes, and architectural and engineering design.
[7]
A. Pre-Study
Pre-study tasks involve six areas: Collect User/Customer Attitudes, Complete Data File, Determine
Evaluation Factors, Scope the Study, Build Models, Determine Team Composition. [3]
1) Information Phase: The objective of the information phase is to complete the value study data package started in
the pre study work. If not done during the pre study activities, the project sponsor or designer brief the value study
team, providing an opportunity for the team to ask questions based on their data research. If a site visit wherever
applicable was not possible during pre-study, it should be completed during this phase. [7]
In order to keep this process easy, however, the function of each task must be defined as simply as possible,
such as using two verb-noun words. [4]
2) Function Analysis Phase: Functional analysis outlines the basic function of a product using a verb and a noun
such as ‘boil water’ as in the case of our kettle. [8].
In function Analysis Phase the team performs: Determine the functions, classify the functions, build a
function model, estimate the cost of performing each function, determine the best opportunities for improvement,
refine study scope. [3]
3) Creative Phase: The Creative Phase develops ideas for alternative ways to perform each function selected for
further study. The objective of the creativity phase is to develop a large quantity of ideas for performing each
function selected for study. [9]
This is a creative type of effort, totally unconstrained by habit, tradition, negative attitudes, assumed
restrictions, and specific criteria. No judgement or discussion occurs during this activity. [3]
4) Evaluation Phase: In Evaluation phase alternative ideas are ranked and rated and ideas for development are
selected.[8]
The objectives of the evaluation phase are to synthesize ideas and concepts generated in the creativity
phase and to select feasible ideas for development into specific value improvement. Using the evaluation criteria
established during the pre-study effort, ideas are sorted and rated as to how well they meet those criteria. [3]
5) Development Phase: The Development Phase takes the most feasible alternatives and prepares information such
as sketches, narratives and specifications to improve the value of the project.[10]
The data package prepared by the champion of each of the alternatives provide as much technical, cost, and
schedule information as practical so the designer and project sponsor may make an initial assessment concerning
their feasibility for implementation. [7]
6) Presentation Phase: The presentation phase is actually presenting the best alternatives to those who have the
authority to implement the proposed solutions that are acceptable. [8]
Through the presentation and its interactive discussions, the team obtains either approval to proceed with
implementation, or direction for additional information needed. [9]
C. Post-Study
The objective during post-study activities is to assure the implementation of the approved value study change
recommendations. Assignments are made either to individuals within the VE study team, or by management to other
individuals, to complete the tasks associated with the approved implementation plan. [3]
VIII. CONCLUSION
Value engineering can be applied to a project in a few stages: The first stage is during planning of the plans,
specifications and design i.e. prior to release to the contractor. The purpose here is to study various alternatives
in planning, designing, specifications, use of local available materials to economise the construction cost
wherever possible of course without affecting the quality. The new saving if any shall be the total reduction
in cost. The second stage of value engineering study is after the award of the contract of construction works.
Here the study is generally made either by the contractor or his value engineer. Here value engineer after
studying all details; informs there is any scope for reduction in the cost of the project by adopting certain
methods of construction or by changing or modifying design method or by any other legal method
maintaining the quality if possible. The application of Pareto Law 20/80 states that around 20 % of the functions
constitute around 80% of the cost. These functions are the subject of value engineering. As a conclusion, the area of
value engineering analysis and study will be controlled by that functions. Further, we can do analysis of these
functions and suggest alternatives and calculate cost model after application of value engineering technique.
ACKNOWLEDGMENT
It is stern guidance and grandeur of him which has brought this work in a proper channel. This guidance not only
helps me to collect the knowledge but also to gain the confidence which would help me in future. My association
with him as a student has been extreme pleasing. I would like to express my gratitude towards my respected guide
Prof. P.M. Attarde. I pay my sincere thanks to Prof. P.P. Bhangale, HOD of Civil Engineering Department. I would
also like to thank Principal Dr. R.P. Singh sir for his encouragement and valuable suggestions. Finally heartfelt
appreciation to the all those who directly and indirectly helped me in completion of this experiment.
REFERENCES
[1] Dr. S.V. Deodhar,(2010) "Construction Equipment and Planning," Khanna Publishers Delhi. Fourth Edition .
[2] K.K. Chitkara,(2011) "Construction Project Management Planning, Scheduling, and Controlling," Second Edition, Tata McGraw
Hill Education Private Limited New Delhi 2011.
[3] Value Engineering: A Guidebook of Best Practices and Tools, Department of defence United State of America, June 13,2011
[4] Boo Young Chung, Syadaruddin Syachrani, Hyung Seok Jeong, and Young Hoon Kwak, (2009) "Applying Process Simulation
Technique to Value Engineering Model: A Case Study of Hospital Building Project" IEEE transactions on engineering management,
vol. 56.No.3.
[5] Tae Hyung Kim, Hyun Woo Lee, M.ASCE, and Seok Woo Hong,(2015) "Value Engineering for Roadway Expansion Project over
Deep Thick Soft Soils" ASCE.
[6] Sungwoo Moon, Chideok Ha, and Jinkook Yang (2012) "Structured Idea Creation for Improving the Value of Construction
Design"ASCE.
[7] Value Standard and Body of Knowledge SAVE International, The Value Society,USA, June 2007.
[8] Amit Sharma, R.M. Belokar, (2012) " Achieving Success through Value Engineering:A Case Study" Proceedings of the World
Congress on Engineering and Computer Science 2012 Vol II, ISSN: 2078-0966
[9] Om Ji Shukla , Anil Kumar Misra, (2013) "Easily & Economically Feasible Value Analysis &Value Engineering Concepts for
Manufacturing industry" Engineering Management Reviews (EMR) Volume 2 Issue 3.
[10] Abeer Khalid Mansour, and Mohammed Abueusef, (2015) " Value Engineering in Developing Countries" International Conference
Data Mining, Civil and Mechanical Engineering, Bali Indonesia.