EE Design SS Introduction
EE Design SS Introduction
WELCOME TO
THE WORLD
OF EE DESIGN
2
featuring:
CUSTOMER
SUBSTATION
3
DESIGN
CONSIDERATION
6
Utility Primary
Distribution Voltage:
34.5kV
13.8kV
13.2kV
7
Utilization Voltage:
400Y/230V,
400V for 3phase loads
230V line-to-ground
for single phase loads
Advantage:
8
Utilization Voltage:
460Y266V for 3phase loads
400Y/230V
for line-to-ground single
phase loads
Disadvantage:
9
DESIGN
APPROACH
10
Statistics method
Inventory of loads method
* Continuous loads
* Non-continuous loads
11
Demand Factor and
Diversity Factor:
Actually, demand factor and
diversity factor can be
determined only after
establishing the expected
maximum demand load.
12
Location :
flood-free
15
Special consideration:
Genset room
Central Aircon Plant room
Grounding
Room Ventilation
Flexibility
21
Positioning
--getting them in
--getting them out
22
Transformer
type
Oil-filled type: in a vault or outdoor 23
Connections
-- delta-wye
--- wye-wye
Technical Specifications: 26
-- Transformer
-- HV Cables
-- HV Terminations kits
-- Primary Protection
Gang-operated LBS/PF
Power Circuit Breaker
-- Protective Relaying
Under-voltage trip (27)
Over-voltage trip (59)
LSIG
27
Low-Voltage Switchgear
-- Emergency Loads
--100% >> Main ATS
--Critical Loads >>Branch
ATS
-- Fault Duty at LVSG Bus
Sample One-Line Diagram 28
29
Design Proper
Conductors Sizes
Equipment Ratings
Layout Plan
Sections
Details
Short Circuit Calculation
One-Line Diagram
30
****E N D****