Flowchart 1 Expropriation
Flowchart 1 Expropriation
Reclamation Projects
Approval Stage
Applicant PRA Other Government Agencies
Government
Agency (GA) / PRA - GA / LGU
Local Enters into
Government MOA
Unit (LGU)
GA/LGU
Complies with
the requirements
under the MOA
(i.e., pre-
construction
requirements)
PRA conducts
review and
evaluation on
the compliance
Pre-Construction Requirements of the LGU
1. Detailed engineering plans and specifications for the reclamation
2. Copies of GSSR, IEE/EIA/EIS and of EGGAR/ECC for
reclamation Phase
3. Copy of Signed contract for the winning bidder, if applicable
4. Soil exploration report, GSQP issued to PRA for the project and
other DENR, e.g., Declaration of Seabed Feasibility, Borrow pit
Utilization and Development Program, and Environmental
Protection and Enhancement Program.
5. Detailed Reclamation Cost Estimates & and Quantity Take-off per
item of work
6. Detailed Work breakdown Structure / Work Program for PRA issues
Reclamation Reclamation Permit
7. Performance Security and All Risk-Insurance / Notice to Proceed
8. Payment of Regulatory Fee & other fees per Reclamation Permit (NTP) (2nd Stage)
/ Contract