Project Management: Catch Your FIDIC
Project Management: Catch Your FIDIC
PROJECT MANAGEMENT
Home Blog Project Management Catch Your FIDIC
How much times you hear FIDIC word? , What do you think what is FIDIC? , How can it will be useful for you? , Is it best
practices or documents templates?Sign-up
How to now! get useful contents into your email.
use it?
Your email
In address..
this topic we will take you in a small journey about FIDIC and if you dont know the answer of the above questions, we
will help you to nd all answers here in this topic.
SUBSCRIBE Offline
https://planningengineer.net/catch-your-fidic/ 1/5
11/16/2017 Catch Your FIDIC Planning Engineer Est.
Lets start with the first question, What does FIDIC mean?
The International Federation of Consulting Engineers (commonly known as FIDIC, acronym for its French name Fdration Internationale Des
Ingnieurs-Conseils) is an international standards organization for the consulting engineering & constructionbest known for the FIDIC family
of contract templates. The fact that the organization has a French title bears testimony to its foundation in 1915 by three countries each wholly or
partly francophone. The founding member countries of the FIDIC were Belgium, France and Switzerland. Wikipedia
This Picture just simplify and illustrate all the Contract Form and their use
The Red Book Conditions of Contract for Construction for Building and Engineer-ing
Works Designed by the Employer Offline
https://planningengineer.net/catch-your-fidic/ 2/5
11/16/2017 Catch Your FIDIC Planning Engineer Est.
In 1956 the first edition of the original form of Red Book was published. This was updated and amended over four editions. Then in 1999 FIDIC released a
totally new set of standard forms of contract, including a brand new version of the Red Book, which superseded the original version of the Red Book. The Red
Book is the FIDIC recommended form of contract for building or engineering works where the employer has been re-sponsible for nearly all the design. In fact
FIDIC claim that the Red Book is the most widely used international-al construction contract where most of the works have been designed by the employer.
A key feature of the Red Book is that payment is made according to bills of quantities (ie a document in which materials, plant, and labour (and their costs)
are itemized), although payment can also be made on the basis of agreed lump sums for items of work. The Red Book is administered by the engineer (a
third party) rather than the contractor or the employer. The engineer will also be responsible for monitoring the construction work (but still keeping the
employer fully informed so that he may make variations) and certifying payments.
The Yellow Book Conditions of Contract for Plant and Design-Build for Electrical and
Mechanical Plant and for Building and Engineering Works, Designed by the Contractor
(the plant and design/build contract)
This form of contract is drafted for use on projects where the contractor carries out the majority of the design (ie the contractor carries out the detailed
design of the project so that it meets the outline or performance specification prepared by the employer). The Yellow Book is therefore traditionally
used for the provision of plant and for building or engineering works on a design/build basis.
The Yellow Book is a lump sum price contract with payments made according to achieved milestones on the basis of certification by the engineer (like
the Red Book, the engineer administers the contract). The contractor is also subject to a fitness for purpose obligation in respect of the completed project.
The Silver Book Conditions of Contract for EPC/Turnkey Projects (the EPC turnkey
contract)
The Silver Book is drafted for use on EPC (Engineer, Procure, Construct) projects. These are projects that require the contractor to provide a completed
facility to the employer that is ready to be operated at the turn of a key. These contracts therefore place the overall responsibility for the design and
construction of the pro-ject on the contractor. The Silver Book is used where the certainty of price and completion date is important. The Silver Book
allows the employer to have greater certainty as to a projects cost as the contractor assumes greater time and cost risks than under the Yellow
Book. The Silver Book may also be used for privately financed BOT (Build, Operate, Transfer) projects. These are projects where the employer takes total
responsibility for the design, construction, maintenance and operation of a project and wishes to pass the responsibility in respect of construction to the
contractor. There is no engineer under the Silver Book as his responsibilities are assumed by the employer. Similar to the Yellow Book, the contractor is also
subject to a fitness-for-purpose obligation in respect of the completed project.
The Gold Book Conditions of Contract for Design, Build and Operate Projects (the
design build
operate contract)
FIDIC state that the Gold Book is drafted to minimize the risk of rapid deterioration after the handover of a project due to poor design, workmanship or
materials. The Gold Book is therefore suitable where a long-term operation and maintenance commitment is required along with design and build
obligations. The contractor must operate and maintain the completed project on behalf of the employer for a period of typically 20 years from the date of
the Commissioning Certificate, which is issued at completion of construction of the project. During this 20 year period the contractor must meet certain
targets and at the end of this period the project must be returned to the employer in an agreed condition. Throughout the 20 year period the employer owns
the plant but the contractor operates it at the contractors own risk. However, the contractor has no responsibility for financing the project or ensuring
its long-term success.
Thank You
Tag: Fidic, Fidic types, green dic, red dic, Types of dic Offline
https://planningengineer.net/catch-your-fidic/ 3/5
11/16/2017 Catch Your FIDIC Planning Engineer Est.
Share:
Mahmoud El Refaie
Mahmoud El Refaie Omara ,Civil Engineering Informatics Specialist - Planner Engineer ,worked as site and technical o ce engineer
for 4 years ,In planning Engineering my role is lling the gap between the Planning Engineering and Engineering Informatics by
developing smart Engineering Informatics solutions, which quick your work and make your tasks more easy without any repetitive
or hard work.
Changing PC name will make you unable to Connect to KPI's For construction Industry: Part 1
August 25, 2016
Primavera Database
August 24, 2016
Why you should add the advanced payment to your sched Measuring Construction progress with EVM, is it enough?
22 October, 2017 4 October, 2017
2 COMMENTS
Hello Sir;
Offline plus ,)
What is the difference between FIDIC contracts and other types of contracts(Lump sum contract,Cost
https://planningengineer.net/catch-your-fidic/ 4/5
11/16/2017 Catch Your FIDIC Planning Engineer Est.
Hope you can clarify.
LEAVE A REPLY
SEARCH
Search
PLANNING COURSES
Free
$665.00
$399.00
$149.00
$150.00
$119.00
Offline
https://planningengineer.net/catch-your-fidic/ 5/5