PGE BMW IChargeForward Final Report
PGE BMW IChargeForward Final Report
A cooperation between
Contents
Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Section 8: Conclusion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
Appendix. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Content Authors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
Table of Figures
Figure 1: Project Timeline. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Figure 2: Overview of Project Partners and Roles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Figure 7: W
eekday and Weekend Charging Demand from the BMW i3 Fleet. . . . . . . . . . . . 16
Figure 8: A
verage kW Contribution and Vehicle Participation per Event Hour. . . . . . . . . . . . 17
Figure 10: B
attery and Range Extender Aggregate Power Draw Comparison . . . . . . . . . . . 19
Figure 13: D
ay Ahead and Real Time Delivered Contribution Comparison. . . . . . . . . . . . . . 24
Figure 18: L
evels of Satisfaction with Elements of the BMW i ChargeForward Program. . . . 34
Figure 24: H
ourly BMW i ChargeForward Aggregated Load (total kWh)
Against 2020 Estimated Duck Curve Grid Needs . . . . . . . . . . . . . . . . . . . . . . . 45
Figure 26: E
xample of Demand Response Event, BMW Group 2nd Life Battery System . . . 48
Figure 27: E
xample of Demand Response Event, Combined System . . . . . . . . . . . . . . . . . 49
Executive Summary
The BMW i ChargeForward Project successfully from the California Independent System Operator.
tested the feasibility of using managed electric These grid services have the potential to result
vehicle (EV) charging as a flexible grid resource. in cost savings associated with operating and
The Project has shown the ability for electric maintaining the grid as well as owning an electric
vehicles to provide viable grid services using vehicle. For each Demand Response event, BMW
the vehicle telematics system as a basis for provided PG&E with 100kW of grid resources by
communicating grid messages to vehicles. The delaying charging for approximately 100 BMW
grid services demonstrated in this pilot included i3 vehicles in the San Francisco Bay Area and
Day Ahead and Real Time Energy, which were drawing from a BMW Group 2nd life stationary
modeled after existing proxy demand resources battery system built from reused EV batteries,
for a duration of one hour.
PAGE 4
Over the course of 18 months, from July to no customer fatigue. Results indicate
2015 to December 2016, the BMW i Charge that the electric vehicle (EV) owners have
Forward Project dispatched 209 Demand a strong interest in supporting renewable
Response events, totaling 19,500 kWh. On energy through managed charging
average 20% of the total contribution was programs. They are willing to participate
attributed to the vehicle pool and 80% from in managed charging or charge during the
the 2nd life stationary battery system. The day as long as they are not inconvenienced
amount from the vehicle share is dependent or limited in their ability to use their car.
on what time of day an event is called. If The largest barrier to day time charging
an event is called from 11 PM to 2 AM, the and managed charging is the lack of
vehicle pool contributes more significantly by workplace charging. Based on the success
increasing the share from 20% to 50% of the of the BMW i ChargeForward pilot, BMW
100 kW required. This increase in vehicle pool received a grant from the California
contribution is the result of PG&Es residential Energy Commission (CEC) to continue
EV and time-of-use rate plans which provide with a second phase of the pilot. Program
lower cost electricity prices during this time participants express an interest in having
period, thus creating an incentive for people the automakers participate and expand
to charge during these hours. their role in providing grid services; this is
seen as an added benefit to drivers who
The BMW i ChargeForward Pilot is deemed a want to optimize the positive impacts of
success both from an energy reduction and driving their electric vehicle. The second
customer satisfaction standpoint. Participants phase looks further into the grid benefits
were very satisfied with the program and were attained from greater flexible charging and
active participants in the research component more advanced charging management
as well. Based off customer research, 98% while continuing to utilize vehicle telematics
of participants indicated that they were to facilitate grid messages to the vehicle
satisfied with the program and 93% stated and driver. Overall, the size and magnitude
that they are likely to participate in a similar of this resource, and the associated cost
program in the future if offered. Since this savings, will ultimately be dependent on
program was designed to run primarily in the EV adoption and the types of grid services
background of customers lives they were that can be cost effectively offered.
able to participate at high rates and felt little
PAGE 5
1 Project Overview
The BMW i ChargeForward Project (known as and maintaining the grid as well as owning and
the Plug-in Electric Vehicle Demand Response operating a vehicle. Added grid services can
Pilot Project as described in D.12-04-045 and potentially reduce the need to increase Californias
Advice Letter 4077-E) aimed to demonstrate the electricity generation capacity and is aligned with
technical feasibility and grid value of managed the States loading order for resources, effectively
charging of electric vehicles, as a flexible and reducing energy procurement costs. The magnitude
controllable grid resource. The main goal of this of these services and their associated cost savings
project was to understand the potential of using will ultimately be dependent on EV adoption
Electric Vehicles (EV) for grid services, which can and the types of grid services that can be cost
result in cost savings associated with operating effectively offered.
PAGE 6
1 Project Overview
Whisker
(Meter Data Provider)
PAGE 7
2 System Architecture & Project Development
PAGE 8
2 System Architecture & Project Development
This section includes an overview of the system by pilot participants who are PG&E residential
architecture, summary of the technology customers. Once an event is called, BMW
developed by BMW to deliver the required utilizes proprietary aggregation software to delay
demand response commitment of 100 kW, and charging of participating customers (via telematics
the customer enrollment process. This section embedded in the vehicle) in order to reduce load
also includes a description of challenges faced in on the grid. The algorithm prioritizes the reduction
project development and solutions developed to of electricity consumption from charging without
overcome these project barriers. interfering with customers mobility needs;
however drivers can opt out of event participation
at any time. To address uncontrollable fluctuations
regarding managed charging capacity, BMW
Overview of the developed a stationary battery system made up
System Architecture of eight used BMW Group batteries (100 kW/225
kWh) as backup storage to fill the gap between
The pilot requires BMW to provide 100 kilowatts available load drop from managed charging and
(kW) of capacity at any given time, regardless of the required 100 kW of DR capacity.
how many BMW i3 EVs are charging. BMW is
required to provide this capacity in the form of PG&E leverages the Whisker metering system and
either Day Ahead or Real Time Energy, which were Olivines online monitoring system to produce real
modeled after existing proxy demand resources time baseline calculations in event dispatches,
from the CAISO. An overview of this system is ensuring that the BMW systems can accurately
described in the figure below. meet the dispatch requirement.
To meet the EV managed charging component of See Figures 25-27 in the Appendix for a
the pilot, BMW has enrolled 96 BMW i3 drivers description and example of the systems used
located within the South Bay Area to participate to track the performance of each event.
in this pilot.1 All vehicles are owned and operated
PAGE 9
2 System Architecture & Project Development
PAGE 10
2 System Architecture & Project Development
This graph illustrates the local solar production during three consecutive days. Energy production from
the solar panels as well as battery recharging is displayed as negative values. The energy exported from
the battery to the building or grid is positive. The two distinct orange spikes indicate the DR events called
in the evenings where the battery dispatched power.
100
80
60
40
Battery Power (kW)
POWER (kW)
20
-60
-80
9.15.16 10:00
9.15.16 14:00
9.15.16 18:00
9.15.16 22:00
9.16.16 10:00
9.16.16 14:00
9.16.16 20:00
9.17.16 12:00
9.17.16 16:00
9.17.16 20:00
9.15.16 2:00
9.15.16 6:00
9.16.16 2:00
9.16.16 6:00
9.17.16 2:00
9.17.16 0:00
9.17.16 4:00
9.17.16 8:00
Solar and Battery Profile of the BMW Group Technology Office USA
PAGE 11
2 System Architecture & Project Development
2
MIINUTES
-2
7.30.15
9.6.15
10.7.15
11.9.15
11.28.15
12.28.15
1.25.16
2.16.16
3.4.16
3.23.16
4.12.16
5.10.16
5.28.16
6.16.16
7.9.16
7.31.16
8.23.16
9.14.16
9.29.16
10.25.16
11.17.16
12.15.16
DATE
2 System Architecture & Project Development
PAGE 13
2 System Architecture & Project Development
FIGURE 6 BMW i
ChargeForward
Smart Phone App
Interface of the BMW i ChargeForward
smartphone app
PAGE 14
The press coverage combined with targeted BMW Group Technology Office USA team
emails to all BMW i3 owners living in the South conducted interviews with the participants
Bay Area in January 2015 were successful who submitted the full application with the
tactics in driving traffic to the online application. following goals:
In March the BMW Group Technology Office Verify all information submitted online
USA hosted a meetup of local BMW i3 drivers Review project overview and goals
to improve the connection to the local owner Test vehicle connectivity in
network and provided additional information charging location
regarding the pilot. A second round of targeted Go over contract and sign if possible
BMW i3 owner emails was sent in April 2015 to
include all customers who had bought vehicles
During the enrollment process the BMW team
and live in the project area. Over the course
conducted 107 in-person interviews, of which 96
of the participant enrollment process, BMW
customers were subsequently enrolled in the pilot.
received significant interest in the pilot, with over
By the end of the pilot, 92 customers remained.
500 applications for only 100 available spots.
Since the project started, four customers left the
project due to a variety of reasons: two customers
In parallel the BMW team worked with BMW were unenrolled due to cellular connectivity issues
of North Americas Legal team, PG&E and its at their residence, one customer was in a car
partners to define all participant requirements accident resulting in the loss of the vehicle and the
and draft a contract to be signed by each last customer moved outside the project area.
customer and by BMW of North America. This
contract defines participant responsibilities,
On July 22, 2015, the BMW Group Technology
BMW responsibilities, and outlines criteria for
Office USA hosted a Kickoff Event for program
contract termination.
participants. The goal of the event was to
introduce the program participants to each other,
The online application was designed to quickly as well as the BMW and PG&E team. Over 50
identify interested participants and pre-screen customers attended. Following the Kickoff Event,
them based on the five most important criteria the BMW team distributed a customer handbook
for the pilot, before directing them to the full to all participants that provided extensive program
application. These criteria were: details, best practices, and a contact list in case of
Owning a BMW i3 by July 2015 questions/concerns.
PG&E customer
W illing to charge BMW i3 primarily at home Coinciding with the program launch, BMW i
during pilot ChargeForward received a second round of news
Level 2 EVSE installed by July 2015 media coverage due in part to two well-timed
Live in PGP2 Sub-LAP (determined interviews by the BMW and PG&E teams with
by ZIP code) the Atlantics CityLab website and Bloomberg
Business. Media coverage included: CityLab,
Approximately 500 people signed up as Bloomberg, Engadget, Chicago Tribune, Fortune,
interested in the program, of those that CNET, Business Insider, Forbes, SlashGear, The
indicated they were interested only 275 passed Verge, Transport Evolved, Green Car Congress,
the primary five criteria. Of those that passed and Ecomento.
the pre-screening almost 200 submitted the
full application.
PAGE 15
3 Analysis of Charging Behavior and
Driver Archetypes
FIGURE 7 Weekday and Weekend Charging Demand from the BMW i3 Fleet
The figure below displays the weekend and weekday charging of the BMW i3 vehicle pool from 8/201512/2016.
The demand curve has a similar shape for both weekday and weekend but the weekday curve is characterized
by a steeper and larger peak demand around midnight.
0
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
HOUR
PAGE 16
3 Analysis of Charging Behavior and Driver Archetypes
This section examines the charging behavior band showing the inter-quartile range (25th75th
of the BMW i ChargeForward participants percentile). The light blue section represents the
from a variety of angels to identify trends in minimum and maximum demand measured.
charging and help influence future managed
charging programs. The weekday charging profile for the BMW i Charge
Forward fleet is relatively low from 6:00 AM to 4:00
First, the demand load curves for weekend PM, and increases beginning at 4:00 PM creating a
and weekday charging are described. Second, small peak or increase at 8:00 PM and a large peak
the section explores three possible charging at 12:00 AM. The weekend demand profile has
archetypes of the participants studied and lower maximum demand and less variability.
variations in the charging behavior of the
battery electric (BEV) and range extender (REX) The vehicle share had a wide range of load
versions of the BMW i3. Lastly, the section contribution based on when the event is called due
examines other locations, aside from home, to the charging patterns of the participants. On
that the pilot participants charged. average, 20% of the total resource was attributed
to the vehicle pool and 80% was provided by the
The demand response capacity from the battery. However, the highest vehicle contribution
vehicle pool varies significantly over the course was during events that were called within PG&Es
of a day and by day of the week. Figure 7 off-peak time-of-use periods, specifically
(on page 16) displays the aggregate weekday 11:00 PM2:00 AM. The higher share at these
and weekend charging demand from the BMW times is the result of about 60% of the BMW i
i3 Fleet between 8/201512/2016. ChargeForward participants that are on a time-
of-use rate plan, either the whole house electric
This is baseline charging data, excluding vehicle rate plan (EV-A) or the tiered, time of use
demand response event days. For these figures, plan (E-6). These rate options incentivize off-peak
a day is defined as starting at 6:00 AM and charging by offering a lower price per kWh between
ending at 5:59 AM the next day. The center the hours 11:00 PM7:00 AM on weekdays and
white line in each figure represents the median 7:00 PM2:00 PM on Weekends and Holidays.
power draw for the EV pool, with the green
kW
The time of hour the day an event is 0 5 10 15 20 25 30 35
called was strongly correlated to the
number of vehicles participating. This 23:00AM
was largely due to the high number of 67:00AM
participants on a time-of-use electric 78:00AM
rate plan that incentivize charging
after 11 PM. 89:00AM
34:00PM
45:00PM
56:00PM
67:00PM
EVENT HOUR
78:00PM
89:00PM
910:00PM
1112:00AM
0 2 4 6 8 10
NUMBER OF VEHICLES
3 Analysis of Charging Behavior and Driver Archetypes
Frequent drivers have the largest power draw of the three driver archetypes.
Household drivers power draw curve is slightly skewed due to the small sample
size of customer that fit this driver archetype.
60
POWER DRAW (kW)
40
20
0
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
Frequent Drivers
Household Drivers
Infrequent Drivers
PAGE 18
3 Analysis of Charging Behavior and Driver Archetypes
Comparison of Battery
Electric and Range Extender
Participants
The BMW i3 is offered in two different
versions, a battery electric vehicle (BEV) or
range extender (REX). For the 2014 BMW
i3, the BEV version is fully electric with an
EPA estimated 80 miles per full charge. The
REX version of the i3 has an EPA estimated
range of 150 miles due to the addition of a
small gas engine that charges the battery
while driving and is designed to enable the
driver to reach the next charging station and
reduce range anxiety.2 Within the BMW i
ChargeForward vehicle pool 44 participants
have a BEV and 48 have a REX BMW i3.
REX drivers have an earlier peak and a slightly larger power draw throughout the day for both weekday
and weekend. The power draw difference between REX and BEV pool at the peaks is about 10 kW with the
exception of the second weekday peak at midnight when the power draw is the same. This slight difference
in power draw may suggest that REX drivers drive slightly further between charging event. However, overall
the charging behavior is very similar between the REX and BEV.
60
POWER DRAW (kW)
40
20
0
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
BEV
REX
Since i ChargeForward launched, BMW has increased the range for both the BEV and REX.
2
Participants for this pilot had the 2014 version of the BMW i3.
PAGE 19
3 Analysis of Charging Behavior and Driver Archetypes
The figure below indicates where participants have charged outside their homes.
Areas of purple and orange have a higher frequency of charging events.
Berkeley Berkeley
Oakland Oakland
Pacifica Pacifica
Union City Union City
San Mateo
Fremont San Mateo Fremont
Sunnyvale Sunnyvale
San Jose San Jose
Campbell Campbell
PAGE 20
3 Analysis of Charging Behavior and Driver Archetypes
PAGE 21
4 Participation in Demand Response
(DR) Events
3
Prior to October 2015, BMW was required to provide 80 kW.
4
These percentages are derived from the total delivered amount, 19,500 kW.
5
Graph does not total 100% since BMW did not meet the full 100 kW in every event.
PAGE 22
4 Participation in Demand Response (DR) Events
100%
90%
80%
70%
60%
50%
40%
0%
0 20 40 60 80 100 120 140 160 180 200
EVENTS
Average of Vehicle Share Target
Average of Battery Share Target
PAGE 23
4 Participation in Demand Response (DR) Events
Real Time and per event. On average, the per vehicle capacity
during an event was 4.43 kW.8 The lower
Day Ahead Events capacity observed (compared to the maximum
capacity) is a result of a portion of vehicles that
Between July 2015 and the end of December either end or start a charging event during an
2016, the BMW resource reliably provided grid hour-long DR event.
services for both Day Ahead and Real Time
events. The results indicated that there was no During the summer when demand response
significant difference in the vehicle and battery programs are utilized frequently, customers
contribution percentage between Real Time and often feel the burden of repeated events in a row.
Day Ahead. This can place a burden on customers to perform
and often result in less successful events (lower
Across all DR events (Both Real Time and Day curtailment), poor customer satisfaction, and
Ahead), the vehicle pool of customer owned increase dropout rates. Unlike typical demand
BMW i3 vehicles has contributed, on average, response programs, the BMW i ChargeForward
approximately 18% while the BMW Group 2nd Pilot had significantly more events at a much
life battery system has contributed 77% of the higher frequency. For context, PG&Es SmartRate
targeted DR resource.6 While the vehicle share residential demand response program caps the
has varied throughout the pilot, the majority of number of events at 15 per year whereas the
events have been between 15 and 35% of the BMW i ChargeForward pilot had over 200 events
total DR resource. Each vehicle has a maximum across an 18 month period.
capacity of 6.6 kW per charge7; results from the
pilot indicate a lower average vehicle capacity
20.2%
79.7%
Real Time
6
Percentages come from the targeted amount (100 kW per event) and is slightly less than the percent from the total delivered kW.
7
Based on the maximum capacity of the BMW i3 on-board charger.
8
Average vehicle capacity was calculated by averaging the kW reduction attributed to each vehicle that participated throughout the
programs duration.
PAGE 24
4 Participation in Demand Response (DR) Events
Throughout the pilot, PG&E called an average The low opt out rate suggests that
of three to four events per week. BMW was customers were not negatively impacted
able to reliably and successfully respond by the program and didnt feel customer
to these events over 90% of the time. This fatigue from consecutive events.
indicated that both the vehicles and the Further, only two participants opted
battery had a consistent response time and out for more than two events over the
were able to meet the contribution multiple 18 months. Based on surveys of BMW
days in a row. Since this program was i ChargeForward participants, most
designed to run primarily in the background participants never felt the need to opt out.
of participants lives they were able to Of the participants surveyed, 95% noted
participate at higher rates and felt little to no that they never, or very seldom, had to
customer fatigue. change their driving or charging behavior
as a result of participating in the BMW
This is further evidenced by reviewing the i ChargeForward program.
customer opt-out rate. Each customer had
the ability to opt out of each event at any
time. However, the overall rate was low
throughout the pilot. The most opt outs for
one event was on the October 14, 2015
11 PM event with three customers opting
out. The majority of events had no opt-outs.
1
OPT-OUTS
0
7.30.15
9.6.15
10.7.15
11.9.15
11.28.15
12.28.15
1.25.16
2.16.16
3.4.16
3.23.16
4.12.16
5.10.16
5.28.16
6.16.16
7.9.16
7.31.16
8.23.16
9.14.16
9.29.16
10.25.16
11.17.16
12.15.16
DATE
PAGE 25
4 Participation in Demand Response (DR) Events
Demand Response Events per Vehicle. The figure below displays the distribution of vehicles participating in events
throughout the pilot. The bars represent the number of vehicles participating in events. For example, in 27 events
five vehicles participated. The average number of vehicles participating in an event was seven. However, five events
had over 20 vehicles participating.
30
25
NUMBER OF DR EVENTS
20
15
10
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 24 25 29
NUMBER OF VEHICLES PARTICIPATING
PAGE 26
4 Participation in Demand Response (DR) Events
The figure below displays the distribution of event participation per vehicle. The bars represent the number of
events in which each vehicle participated. For example, four vehicles participated in 24 events. On average vehicles
participated in eight events across the pilot. However, three vehicles participated in over 50 events.
5
NUMBER OF VEHICLES
0
0 4 8 12 16 20 24 28 32 36 40 44 48 52 56 60 64 68 72
NUMBER OF EVENTS PER VEHICLE
PAGE 27
4 Participation in Demand Response (DR) Events
9
The server that transmits OpenADR signals to end devices or other intermediate servers, in this case the intermediate server is BMWs
backend automated aggregation server.
10
The server that accepts the OpenADR signal, in this case the server is BMWs backend automated aggregation server.
11
The communication between the OpenADR Server and OpenADR Client noting that the OpenADR client has received the OpenADR signal.
12
Database and system that verifies the amount of load reduction from BMW, confirms that event requirements have been met and calculates
payments for modeled grid services.
PAGE 28
4 Participation in Demand Response (DR) Events
OpenADR server9 taken down during a maintenance Once back online, the OpenADR
cyclea DR event was not communicated to the server again was able to communicate
OpenADR client.10 DR events.
OpenADR client did not pick up the DR event creating a Increased the timeout values at
timeout issue in the OpenADR handshake.11 The server the OpenADR client to allow the
took longer to respond to a request than the OpenADR OpenADR server to provide longer
client was waiting. processing times.
EV Pool Control failed as a result of a server The server was restarted and
maintenance cycle. automated restart-mechanism was
implemented.
Stationary 2nd Life Battery Storage System was not Restarted the battery control
operational during a DR eventcontrol program was program and implemented automated
not working correctly. Battery did not power to the grid restart mechanism.
during an event.
Battery cell replacement took longer than expected. The issue was resolved by revising,
Battery did not power to the grid during an event. repairing and adapting the configuration
While attempting to loop-in a repaired battery pack in in the battery system components
the second live battery the battery control loop was (site controller).
non-functional.
The overall technical architecture has proven to be viable with minimal issues. With each new issue,
the project team was able to identify and correct the problem so it did not become a reoccurring issue.
All challenges encountered have been of local nature or have been related to a specific communication
link. It is important to emphasize that no overarching problem occurred that would fundamentally
question the integrity and design of the overall program architecture.
PAGE 29
5 Overview of Customer Behavior Research
PAGE 30
5 Overview of Customer Behavior Research
PG&E and BMW executed a series of surveys The objective of the first phase was
and focus groups from February 2016 to to explore the primary motivators for
December 2016 in order to gain a deeper participating in the BMW i ChargeForward
understanding of pilot participant charging Program, and participants perceptions
behavior and charging flexibilities. This research and experience with the program and the
specifically sought to better understand launch process. A total of four focus groups
participants motivation for participating in the (two in-person and two-online utilizing
pilot, perceptions and experiences with the webcams) were conducted among BMW i
program, understanding participant profiles, ChargeForward participants.13 In addition,
preferences for future managed charging an online survey distributed to the BMW i
programs (both reducing and increasing ChargeForward participants.14
charging), and the general comfort and trust
associated with allowing their charging to The objective of the second phase was
be managed by a third party. This section to understand an EV drivers general
describes the research methods, objectives comfort and trust in a managed charging
and results. program concept, that includes a third party
controlling charging by either reducing or
increasing charging based on grid conditions.
In addition, this research also explored what
Objectives and tactics would drive confidence and potential
Methodologies engagement in this program, the thresholds
for allowing a third party to manage
The BMW i ChargeForward team partnered customers battery charge, and how other
with Ipsos RDA to conduct an approximately factors impact customer confidence. Two
year-long research study looking into the needs online focus groups were conducted among
and motivators of EV drivers. The research BMW i ChargeForward participants.15 In
component was broken into two phases, addition an online survey was sent to BMW
BMW i ChargeForward program research and i ChargeForward pilot participants as well
managed charging program research. as EV owners from PG&Es Customer Voice
Panel Members.16
13
The two Customer Research In-person focus groups had 7 participants and 8 participants. The two Customer Research
online focus groups had 4 participants and 5 participants.
14
The survey was completed by 63 participants. At the time of the survey, 94 participants were enrolled resulting in a
67% response rate.
15
The first Managed Charging focus group had 7 participants, all of whom used their BMW i3 to commute to work. The second
Managed Charging focus group had 6 participants, 4 of whom were retired and 2 commuted to work by other means of
transportation.
16
PG&Es Customer Voice Panel is comprised of PG&E customers that have agreed to participate in online surveys. No incentive
was offered to these customers for taking the survey described in this report. Of the 1,054 plug-in EV Owners in the panel,
a total of 332 surveys were completedresulting in a 32% response rate. Of the 94 BMW i ChargeForward participants, a total
of 67 surveys were completedresulting in a 71% response rate.
PAGE 31
5 Overview of Customer Behavior Research
PAGE 32
5 Overview of Customer Behavior Research
17
As part of the pilot, participants received a quarterly newsletter detailing program performance and activity.
PAGE 33
5 Overview of Customer Behavior Research
%
put in next gen elecric vehicle +
67%
Level of satisfaction with elements of
the BMW i ChargeForward program:
Percent of pilot participants who
rated somewhatHelp(4) or extremely
manage load
94%
Up-front incentive +
88%
Enrolling in the
ncentive (5) satisfied to
onthe
thefollowing
electricquestion
grid Process of how you were invited to participate program
Using a five point scale, please
indicate your level of satisfaction with
mote reuse of EV batteries
each of the following items related to
the BMW i ChargeForward program.
83% Ongoing participation incentive
(n=69)
oy participating in research/pilots 80% Frequency of delayed charging events
going participation incentive
78% Participation in delayed charging events
Ws program involvement
77% Explanation of delayed charging events
save money on charging costs
75% Explanation of user agreement/App to obtain info/opt-out of delays
&Es program involvement
74% Coordinating the setup/Using the app on smartphone
PAGE 34
5 Overview of Customer Behavior Research
PAGE 35
5 Overview of Customer Behavior Research
Charging Away from Home and The participants would be more likely to charge
Barriers to Daytime Charging during the day if charging stations were reliable
and readily available, but also feel there will be
While workplace charging stations may be less of a need to charge during the day as the
provided, participants indicated that charging range of EV batteries increases.
at work is increasingly becoming more difficult.
The most frequent barrier to daytime charging,
and charging away from home, is the availability Comfort and Trust in
of charging stations, cost of charging stations, Managed Charging
and vehicles parked at a charging station but no
longer charging. As mentioned above in Section Participants are very interested in managed
3: Analysis of Charging Behavior and Driver Archetypes, charging and have a high degree of confidence
81% of BMW i ChargeForward participants work in both PG&E and BMW to effectively manage
full time but only 37% charge at both home and the charging of their electric vehicles. Despite
work. On average 85% of charging is done at high interest in the program and confidence in
home with occasional charging away from home PG&E and BMW, participants still want to retain
when it is convenient or necessary. some control of their EV charging. Specifically,
participants want to have the ability to opt-out
Those who regularly drive the BMW i3 to work of events and knowledge of the exact times and
feel charging during the day is quite tedious length for events. Overall, participants rated the
mostly due to the lack of charging stations and ability to set an exact time their EV needs to
charging ethics, such as moving your car once be at a desired charge level as one of the most
it has finished charging. Participants prefer to important program feature.
charge at night, regardless of the amount of
charge left in their battery. Participants indicated
that charging at home during the night is more
convenient and their preferred option.
The figure displays how renewable energy impacts participation in a potential managed charging
program. Participants indicate a strong interest in charging with renewable energy, but require an
incentive to charge during the middle of the day.
63%
70% BMW i ChargeForward
PG&E's Customer Voice Panel
42% 83%
41% 83%
Likelihood to participate at home Likelihood to participate at home and work
and work (between 9 AM4 PM) in order if offered additional monetary incentive
to charge EV with solar energy
PAGE 36
5 Overview of Customer Behavior Research
Thresholds and Flexibility for number of opt-outs. They feel about 20 opt-outs
Managed Charging are reasonable. These participants are familiar
and confident with the program design due to
Among four potential program features tested, their participation in the BMW i ChargeForward
participants rank the ability to set a time their car program. If the number of opt-outs is limited
would need to be at the desired charge level as to 5 times in a 12-month period at home and
most important, as participants want assurance work, about half (52%) of the PG&E Customer
their EVs will be sufficiently charged for their Voice panelists would be less likely to participate
commute. An additional important feature is while far fewer (17%) BMW i ChargeForward
the ability to set a minimum level of battery participants would be deterred by this number
charge before managed charging would begin, of acceptable opt-outs.
as participants want assurance they will not be
stranded away from their homes. Participants When presented with the option of charging EVs
are more likely to participate in a program if with renewable energy (solar or wind), roughly
they know the exact times and length of the two-thirds (68%) are more likely to participate
upcoming delayed charging events. in a managed charging program. This number
drops significantly to less than half (41%) when
Participants want to retain flexibility and control participants are told they will need to adjust their
through the ability to opt-out of managed charging to the core daytime hours (9:00 AM
charging events as they see fit. For PG&Es to 4:00 PM) to take advantage of solar energy.
Customer Voice panelists, they felt that However, the presence of an additional monetary
approximately 40 opt-outs are reasonable incentive significantly increases the likelihood of
before having an incentive negatively impacted.18 participating from 41% to 83%. Thus, there is
This relatively high number could be attributed clearly a high interest in charging with renewable
to a lack of familiarity and confidence in the energy provided the participants receive an
program since they have not participated in a additional monetary incentive for changing their
similar program before. BMW i ChargeForward charging behavior.
participants are much more lenient with the
18
Important to note that PG&Es Customer Voice panelists were not participants of the BMW i ChargeForward pilot thus do not have
previous experience with a managed charging program.
PAGE 37
6 EV Adoption and its Potential for
Further Grid Support
400
200
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
PAGE 38
Over the next 15 years electric vehicle the potential if this pilot were to scale to a
adoption is projected to rise dramatically larger vehicle population. Aggregating EVs
as vehicle price drops, range increases, en masse creates the potential for a large
and a wider range of models becomes demand response resource.
available. By 2020 almost every major
vehicle manufacturer is expected to have a The BMW i ChargeForward pilot provides
long-range electric vehicle on the market. some insight into the magnitude of the future
However, consumers do not have to wait load reduction of this population. The table
until 2020 as manufacturers are beginning below outlines this potential by assuming
to release these vehicles now. At the end and enrollment of 20% of customers with
of 2016 the first long-range battery electric similar behavior of BMW i ChargeForward
vehicle with a competitive, mass market price participants (8% participation rate and a
point and 238 mile range was released. contribution of 4.4 kW per vehicle). Based on
these assumptions, the potential load drop
As EV adoption grows, the potential for EVs of a single event in 2030 is about 77.6 MW,
as a grid resource becomes more significant. which is enough to power approximately
Throughout the course of this pilot, an 58,000 homes in California.23 Thus, on
average of 7 out of 92 customers participated a larger scale, a similar program has the
in each event representing approximately potential to provide a significant resource.
8% of the total vehicle pool. On average, the
vehicle contribution per event is 4.43 kW. The
average contribution is attributed to vehicles
that join the event after the start, unplug
during the event or are near the end of their
charge cycle. While this may seem like a
small contribution, it is important to recognize
19
Forecasted Total number of Electric Vehicles in PG&Es service territory
20
Predicted Enrollment: 20% of the forecasted EVs in PG&Es service territory for the specified year. An average was taken since the actual
enrollment in a program is unknown.
21
Customers Participating: The average number of participants in a given event assuming that 8% of customers participate in each event.
22
Load Drop (kW): The approximate load drop per event based on the number of customers participating in the event and the average
contributed load drop (4.43 kW) per vehicle per event.
23
Glossary of Energy Terms. California Commissionwww.energy.ca.gov/glossary/ISO_GLOSSARY.PDF
PAGE 39
6 EV Adoption and its Potential for Further Grid Support
22,000
2012
20,000
2013
18,000
Increased
2014 ramp
16,000 Potential 2015
overgeneration 2016
14,000 2017
201819
MEGAWATT
12,000 2020
10,000
0
0:00
3:00
6:00
9:00
12:00
15:00
18:00
21:00
HOUR
24
California ISO, Flexible Resource Fast Facts. www.caiso.com/Documents/FlexibleResourcesHelpRenewables_FastFacts.pdf
25
St. John, Jeff. (2016, November) The California Duck Curve Is Real, and Bigger Than Expected. GreenTechMedia
PAGE 40
6 EV Adoption and its Potential for Further Grid Support
The two graphs display the comparison between the percentage of vehicles charging and the
percentage of vehicles plugged in but not charging.
Percent of Vehicles Connected at Home: Weekends Percent of Vehicles Charging at Home: Weekends
100%
90%
80%
70%
60%
50%
40%
Vehicles
30%
20%
10%
0
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
PAGE 41
7 BMW ChargeForward Phase 2
PAGE 42
7 BMW ChargeForward Phase 2
BMW and PG&E will collaborate to build Near-term and long-term advances in electric
on the learnings described in this study vehicle technology necessitate taking a new,
through the implementation of a second broader view when managing vehicle charging.
phase of the BMW ChargeForward project. Vehicle battery size is increasing, which will
The second phase of the pilot will explore reduce the need for vehicles to charge every
two primary themestesting advanced night for most vehicles. The average commuter,
smart charging use cases that promise driving 3040 miles per day, may no longer find
additional value to the grid; and evaluating it necessary to charge every day or even every
customer engagement strategies that other day. With this range, drivers may be able
incentivize drivers to provide additional to charge only two or three times per week to
flexibility in their charging behavior. With the fully meet their mobility needs. While current
support of a California Energy Commission policies have tried to address range anxiety,
grant, BMW will work with PG&E to explore new policies will need to be in place to capture
how charging can be moved throughout the grid opportunity of range freedom. The
the day and across the geographic areas higher range vehicles increase the flexibility in
that a vehicle travels within. In 2017 and charging vehicles, which can be better adapted
2018, BMW will work with a vehicle pool to meet the grids needs. The average vehicle
of over 250 vehicles, now including BMW is parked for most of the day and night, which
iPerformance PHEVs as well as BMW i3 provides numerous opportunities to move
and BMW i8 vehicles, to explore the grid charging so to avoid charging during hours
benefits of increasing charging flexibility as when the grid is strained or power is expensive,
well as customer engagement in advanced and increase charging when it is advantageous
charge management. to do so. At the same time, this greater range
could also reduce the predictability of electric
vehicle load.
PAGE 43
7 BMW ChargeForward Phase 2
To explore the value of this increased flexibility, BMW and Olivinewith support from PG&Ewill test
new ways to shift charging across both time and locations that respond to functionalities that will be
needed to address new challenges that the grid will face in the future. For example, the growth of
renewable generation is expected to create more dynamic conditions on the grid, that require more
options for grid operators to match load to unpredictable renewable generation. Figure 24 (on page 45)
shows the hourly aggregated load curve for the entire vehicle pool and three load requirements that
will be required to enable grid management under duck curve conditions:
Nighttime charging can Adding load in the Price signals can help to
be more beneficial if the afternoon can help address defer early-evening charging.
timer peak is eliminated the growth of solar.
and charging is allowed While not all EV drivers may be
to follow nighttime wind While the afternoon hours are sensitive to TOU price signals,
production. currently peak hours, the many are, and these signals and
steady increase in solar panels additional mechanisms such as
10,000 vehicles all following will soon require new afternoon power alerts could enhance the
timers at midnight would loads to maintain grid balance. ability of grid operators to defer
mean that 77 MW of power This need is likely to be EV charging from the early
would be instantly added to localized on specific circuits. evening when drivers arrive home
the grid. If this load is Circuits during these hours to their homes or apartments.
concentrated in urban areas, are likely to exhibit strongly Charging could be deferred to
it could increase the risk of different needs depending on late night or even to the following
grid instability. Nighttime their climate and solar day(s) depending on their battery
charging has a high degree adoptionthose circuits with charge level and travel patterns.
of flexibility, as the charging significant solar penetration These programs could be
dramatically drops around will need additional load, localized to address distribution
4 AM, hours before vehicles while those circuits without issues unique to specific
generally begin their morning solar will continue to need to neighborhoods and grid areas.
commute. reduce load.
PAGE 44
7 BMW ChargeForward Phase 2
The second phase of BMW ChargeForward In addition to testing the functional capabilities
will test functionality needed to address needed to provide advanced grid services,
these challenges. For example, BMW will BMW will also test different ways to engage
test the ability to move load from nighttime customers in ways that encourage drivers
charging to daytime charging. Doing so has to provide more charging flexibility to the
the potential to address excess solar supply grid. BMW will explore how different types of
that may occur in the future on PG&Es customer engagementincluding customer
grid. BMW will also test the ability of its incentives and customer performance data
charging control system to control charging can be used to encourage customers to
in response to price signals that reflect allow BMW greater flexibility in managing
dynamic generation prices or impacts on vehicle charging. BMW will also test how a
the distribution system. renewable energy signal, showing customers
how much renewable energy their vehicles
absorbed, can serve as an incentive to
encourage smart charging.
The hourly aggregated load curve for Duck Curve Solar Trough Peak Nighttime
the entire vehicle pool and three load Grid Conditions Increase flexible Eliminate Charging
requirements that will be required to Desired charging charging to all Optimize to follow
enable grid management under duck outcome accommodate charging wind and avoid
more solar timer spike
curve conditions.
90
80
70
60
50
40
30
20
10
0
6:00
8:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
Non-modified load of i ChargeForward participants
PAGE 45
8 Conclusion
PAGE 46
8 Conclusion
PAGE 47
Appendix
FIGURE 25 Examples of Demand Response Event, Vehicle Pool
120
The figure displays the
performance of the
vehicle pool (Residential 100
BMW i3) customers
during a demand ~40 kW load reduction
response event on 80
(paused charging)
10/21/2015 from 8:00
9:00 PM. The colored
60
bands indicate individual
vehicles charging. The
orange column indicates 40
the demand response
event duration when
charging was delayed for 20
each customer charging
at that time.
kW
0
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
FIGURE 26 Example of Demand Response Event, BMW Group 2nd Life Battery System
20
kW
-20
~60 kW power reduction
(2nd life battery export)
-40
-60
-80
-100
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
PAGE 48
FIGURE 27 Example of Demand Response Event, Combined System
The figure below displays the performance of the combined system including the microgrid at the
BMW Group Technology Office USA (top right) as well as the vehicle pool (top left) during a demand
response event on 10/21/2015 from 8:009:00 PM. The chart at the bottom of the figure represents
the aggregated resource along with the baseline (blue line) computed using the 10-in-10 baseline
methodology. The orange band indicates the demand response event duration.
125 kW
100 kW
75 kW
50 kW
25 kW
+
0 kW
-25 kW
Vehicles + 2nd life
battery together provide
-50 kW 100kW DR Capacity Baseline
Targetload
kW
-75 kW Load
14:00
16:00
18:00
20:00
22:00
0:00
2:00
4:00
HOUR
PAGE 49
Content authors:
BMW Project Manager:
Sebastian Kaluza
[email protected]
Reporting Period:
01/201512/2016
PAGE 50