GERC - Distribution Code
GERC - Distribution Code
(GERC)
Distribution Code
In exercise of the powers conferred under Section 86(c), (e) and (i) of the Electricity Act,
2003 (Act 36 of 2003) and under Section 42 (b) of the Gujarat Electricity Industry
(Reorganisation and Regulation) Act, 2003 (Gujarat Act 24 of 2003), and all powers
enabling it in that behalf, the Gujarat Electricity Regulatory Commission hereby makes
this "GUJARAT ELECTRICITY DISTRIBUTION CODE" herein after called
Distribution Code. This Distribution Code is applicable for the state of Gujarat only.
DISTRIBUTION CODE
Distribution Code
GUJARAT ELECTRICITY
REGULATORY COMMISSION
PAGE 1 OF 49
DISTRIBUTION CODE
Table of Contents
1. SECTION-1 6
INTRODUCTION 6
1.1 OVERVIEW: 6
1.5 CONFIDENTIALITY 8
1.7 DIRECTIVES 9
2. SECTION-2 10
DEFINITIONS 10
Interpretation 12
3. SECTION-3 14
3.1 INTRODUCTION: 14
3.2 OBJECTIVE: 14
4. SECTION-4 17
PAGE 2 OF 49
DISTRIBUTION CODE
4.1 INTRODUCTION 17
4.2 OBJECTIVES 17
5. SECTION-5 23
CONNECTIVITY CONDITIONS 23
5.1 INTRODUCTION: 23
5.2 OBJECTIVES 23
6. SECTION-6 26
OPERATION CODE 26
6.1 INTRODUCTION: 26
PAGE 3 OF 49
DISTRIBUTION CODE
6.7 COMMUNICATION: 29
6.12 TRAINING 31
7. SECTION 7 32
7.1 INTRODUCTION: 32
8. SECTION-8 36
8.1 INTRODUCTION: 36
8.2 OBJECTIVE: 36
8.4 PROCEDURE: 36
PAGE 4 OF 49
DISTRIBUTION CODE
9. SECTION- 9 38
INCIDENT/ACCIDENT REPORTING 38
9.1 INTRODUCTION 38
10. ATTACHMENT - 1 40
1.0 INTRODUCTION 40
ANNEXURE 1 48
PAGE 5 OF 49
DISTRIBUTION CODE
ANNEXURE 2 49
PAGE 6 OF 49
DISTRIBUTION CODE
1. SECTION-1
INTRODUCTION
1.1 OVERVIEW:
1 In order to perform the task and the requirements as stipulated in Section 42 (b) of
Gujarat Act No. 24 of 2003 viz. Gujarat Electricity Industry (Reorganisation
and Regulation) Act 2003, and section 86(c), (e) and (i) of the Electricity Act,
2003 (Central Act 36 of 2003), the Gujarat Electricity Regulatory Commission has
formulated this "GUJARAT ELECTRICITY DISTRIBUTION CODE" herein
after called Distribution Code. This Distribution Code is applicable for the state of
Gujarat only.
2 Scope of Distribution Code:
(a) The Distribution Code deals with technical aspects of the supply of electricity,
which have impact on the quality, continuity and reliability of service by
licensees and the use of the Licensees Distribution System for the distribution
of electricity. It specifies the rights and obligations of the Distribution Licensee
and the Users in system planning and operation.
(b) The Distribution Code is not exhaustive as to the requirements to be complied
with by the Distribution Licensee and the Users connected or seeking
connection to the Licensees Distribution System. The Distribution Licensee
and all Users/Consumers must also comply with the requirement as laid down
in various codes, standard and regulations under relevant laws in force.
PAGE 7 OF 49
DISTRIBUTION CODE
concerned shall comply in relation to the part of the Distribution System at the
connection site with Users.
6 Section-6: Operation Code This section specifies the procedures and practices
to be followed for a safe and efficient operation of the Distribution System by the
Distribution Licensee of the Distribution System and by the Users of their electrical
plant and lines which are connected to the Licensees Distribution System. This
shall also apply to any electrical interface between two Distribution Licensees for a
safe and efficient operation of the interface.
7 Section-7: Metering and Protection Code This section specifies the minimum
requirements of metering for measurement of electrical energy (and related
parameters) flowing in Distribution System and Users system especially across the
boundary between the Distribution System and Users System. The section also
specifies the minimum requirement of protection levels.
8 Section-8: Cross Boundary Safety Code This section specifies safety
procedures and precautions for ensuring that work in a Distribution Licensees
system or in a Users system is carried out safely in situations where it is possible
to achieve safety only by operations (isolation and earthing) in others system
across the Connection Point/ Interface Point.
9 Section-9: Incident Reporting Code This section specifies guidelines for
incident reporting.
1 The Distribution Code is applicable to all the Licensees in the state of Gujarat. The
Licensees shall be responsible for its implementation within their respective Area
of Supply. Users shall comply the provision of this code.
2 If any User has any difficulty in complying with any of the provisions of the
Distribution Code, he shall immediately, without delay, inform to the Distribution
Licensee and/ or GERC, as the case may be.
3 Any continued non compliance, without reasonable grounds shall constitute a
deviation under the Act, and may lead to disconnection of the Users plant or
Apparatus in line with the provisions of the Electricity Act, 2003 from the
Licensees Distribution System. The responsibility for the consequences of
disconnection including payment of damages and others rests with the User who
consistently violates the Distribution Code.
4 Non compliance with any provision of the Distribution Code by the Distribution
Licensee shall attract the consequences as provided in the Acts or in the License.
However, in the event of non-compliance with the Distribution Code, the
Distribution Licensee shall prepare and submit to GERC a plan of action for
compliance with the Distribution Code. GERC may exempt the Licensee from
compliance of any provisions for a particular period, if it is found that the
compliance is not feasible for such period, considering the resources available and
the circumstances prevailing.
PAGE 8 OF 49
DISTRIBUTION CODE
1 Nothing contained in this Code should be interpreted as imposing obligations /
duties on Consumers / Distribution Licensees greater or more onerous than those
mentioned in the Electricity Act, 2003 under relevant clauses.
The Distribution Code contains procedures for the management of day to day
technical situations in the Distribution System, taking into account a wide range of
operational conditions likely to be encountered under both normal and abnormal
conditions. The Distribution Code cannot foresee all the possible operating
conditions. Users must therefore understand and accept that the Distribution
Licensee, in such unforeseen circumstances, may be required to act decisively and
with due expedition to discharge his obligations under the Licensee. Users shall
provide such reasonable co-operation and assistance as the Distribution Licensee
may require in such circumstances. The concerned Distribution Licensee shall
however refer all such cases for ratification in the next meeting of the Panel.
1.5 CONFIDENTIALITY
1 Under the terms of Distribution Code, the Distribution Licensee will receive
information from Users relating to their business. The Distribution Licensee shall
not, other than as required by Distribution Code, disclose such information to any
other person without the prior written consent of such informant, unless required
by Central/State government departments or any authority.
1.7 DIRECTIVES
1 Under the provisions of the Acts, the State Government may issue policy directives
in certain matters. The Distribution Licensee shall promptly inform GERC and all
Users of the requirement of such directives. The Users, subject to the relevant
section of the Acts, shall comply with such directive.
***
2.
PAGE 9 OF 49
DISTRIBUTION CODE
SECTION-2
DEFINITIONS
1 In the Distribution Code the following words and expressions shall, unless the
subject matter or context otherwise requires or is inconsistent therewith, bear the
following meanings:
10
PAGE 10 OF 49
DISTRIBUTION CODE
for the time being connected for the purpose of receiving
electricity with the works of a Licensee, the Government or
such other person, as case may be.
Contract Demand Maximum KW or KVA agreed to be supplied by the
Licensee and indicated in the agreement executed between
the parties. Wherever the agreement stipulates supply in
KVA, the quantum in terms of KW may be obtained by
multiplying by the Power Factor of 0.9.
Control Person A person identified as having technical capability and
responsibility for cross boundary safety
Distribution A Licensee authorised to operate and maintain a
Licensee Distribution System for supplying electricity to the
Consumers in his Area of Supply.
Distribution The system of wires and associated facilities between the
System delivery points on the transmission lines or the generating
station connection and the point of connection to the
installation of the Consumers.
Generating Any company or body corporate or association or body of
Company individual, whether incorporated or not, or artificial juridical
person, which owns or operates or maintains a generating
station.
Grid Code Gujarat Electricity Grid Code.
GERC Gujarat Electricity Regulatory Commission
High Tension or Voltage greater than 440 V and lesser than 66 kV.
HT
Indian Standards Those Standards and specifications approved by the Bureau
("IS") of Indian Standards.
Licence Any license granted by GERC under provisions of the
relevant laws in force.
Low Tension or Voltage not exceeding 440 volts.
LT
O p e r a t i o n a l Operational metering indicates monitoring of energy and
Metering power supplied to Distribution Licensee from a
Transmission substation.
Power Factor The ratio of Active Power (kW) to Apparent Power (KVA).
SLDC State Load Despatch Centre.
STU State Transmission Utility
T r a n s m i s s i o n A Licensee authorised to establish and operate transmission
Licensee lines.
T r a n s m i s s i o n The system consisting of high pressure cables and overhead
System lines of Transmission Licensee for transmission of electrical
power from the generating station upto connection point
with the Distribution System. This shall not include any part
of the Distribution System. The system consisting of high
pressure cables and overhead lines of Transmission
11
PAGE 11 OF 49
DISTRIBUTION CODE
Licensee for transmission of electrical power from the
generating station upto connection point with the
Distribution System. This shall not include any part of the
Distribution System.
User Any person having electrical interface with, or using the
Distribution System of the Distribution Licensee to whom
this Code is applicable. Any other Distribution Licensee,
Transmission Licensee and generating units connected to
the Distribution system are also included in this term.
Words and expressions used and not defined in this Code but defined in the Acts shall
have the meanings assigned to them in the said Acts. Expressions used herein but not
specifically defined in this Code or in the said Acts but defined under any law passed by a
competent legislature and applicable to the electricity industry in the state shall have the
meaning assigned to them in such law. Subject to the above, expressions used herein but
not specifically defined in this Code or in the Acts or any law passed by a competent
legislature shall have the meaning as is generally assigned in the electricity industry.
Interpretation
In the interpretation of this Code, unless the context otherwise requires:
words in the singular or plural term, as the case may be, shall also be deemed to
include the plural or the singular term, respectively;
the terms "include" or "including" shall be deemed to be followed by "without
limitation" or "but not limited to" regardless of whether such terms are followed by
such phrases or words of like import;
references herein to the code" shall be construed as a reference to this code as
amended or modified by the GERC from time to time in accordance with the
applicable laws in force.
the headings are inserted for convenience and may not be taken into account for the
purpose of interpretation of this Code.
references to any statutes, regulations or guidelines shall be construed as including
all statutory provisions consolidating, amending or replacing such statutes,
regulations or guidelines, as the case may be, referred to.
***
3.
12
PAGE 12 OF 49
DISTRIBUTION CODE
SECTION-3
3.1 INTRODUCTION:
1 A standing body (Distribution Code Review Panel) shall be constituted by GERC
comprising of the representatives of Distribution Licensee as well as the Users of
the Distribution System in line with the provisions of this Code.
2 No change in this Distribution Code, however small or big, shall be made without
being deliberated upon and agreed to by the Distribution Code Review Panel and
thereafter approved by GERC. However, in an unusual situation where normal day
to day operation is not possible without revision of some clauses of Distribution
Code, a provisional revision may be implemented before approval of GERC is
received, but only after discussion at a special Review Panel Meeting convened on
emergency basis. GERC should promptly be intimated about the provisional
revision. GERC may issue directions required to revise the Distribution Code
accordingly as may be specified in those directions and the Distribution Licensee
shall promptly comply with any such directions.
3.2 OBJECTIVE:
1 The section defines the method of managing Distribution Code, pursuing of any
changes/ modifications required and the responsibilities of the Distribution
Licensees and the Users/ Consumers in this regard. This section facilitates
revisions taking into account the views of all parties in an equitable manner.
13
PAGE 13 OF 49
DISTRIBUTION CODE
(d) GERC shall develop a list of potential candidates to serve on the Distribution
Code Review Panel, which reflects a balance of the various interest groups in
consultation with the Distribution Licensee.
2 The members of the Review Panel shall normally have a tenure of two years unless
he ceases for any reason to be member of the Review Panel. Chairperson of the
Review Panel and GERC may jointly consider the replacement of such members.
3 The functioning of the panel shall be co-ordinated by the secretary of the Review
Panel.
4 GERC shall publish the names of the members of Review Panel and also inform to
each Distribution Licensee.
5 The model code of functioning of Review Panel shall be finalised at first meeting
of Review Panel in consultation with GERC.
14
PAGE 14 OF 49
DISTRIBUTION CODE
Review Panel meeting in consultation with the chairperson. Based on this
interaction/ discussion, the necessary amendments/ revisions may be incorporated
in Distribution Code after the approval of GERC in accordance with Clause 3.5.2
and 3.5.3.
2 The secretary shall send the following reports to the GERC at the conclusion of
each review meeting of the panel:
(a) Reports on the outcome of such review.
(b) Any proposed revision to the Distribution Code and its rationale.
(c) All written representations and objections submitted by the Users at the time of
review.
3 All revisions to the Distribution Code require the approval of GERC. The secretary
shall publish revisions to the Distribution Code, after the approval of GERC. The
Review Panel may also submit proposals for relaxation in such cases where Users /
Distribution Licensees have difficulties in meeting the requirements of the
Distribution Code.
4 Any change from the previous version shall be clearly marked in the margin. In
addition, a revision sheet shall be placed at the front of the revised version, noting
the number of every changed Sub-section, together with reasons for such change.
5 The secretary shall maintain copies of the Distribution Code incorporating the
latest amendments and shall make it available at a reasonable cost to any person
requiring it.
6 The Commission, may, on the application of the licensee or otherwise, call the
emergency meeting of the review panel as and when the situation so dictates and
make such alterations and amendments in the Distribution Code as it thinks fit.
***
4.
15
PAGE 15 OF 49
DISTRIBUTION CODE
SECTION-4
4.1 INTRODUCTION
1 The Distribution Planning Code specifies the technical & design criteria and
procedures to be followed by the Distribution Licensee for a proper planning and
development of the Distribution System. This Code is also applicable to the Users
of the Distribution System for their planning and development in so far as they
affect the Distribution System.
2 The requirement of the Users may necessitate extension or reinforcement of the
Distribution System. In some cases the same may even require the Distribution
Licensee to seek the extension or reinforcement to the capacity of the Transmission
System at the Connection Point/ Interface Point. This may arise for a number of
reasons mentioned below, but not limited to the same:
(a) A development by any User in his system already connected to the Distribution
System;
(b) Introduction of a new Connection Point/ Interface Point between the User's
System and the Licensee's System;
(c) To increase the capacity of the Distribution System for meeting the security
standards, removal of constraints in operation etc., and accommodate a general
increase in Demand.
3 The development of the Distribution System must be planned sufficiently in
advance allowing adequate time to obtain the required statutory clearances,
consents or way leaves, the detailed engineering, design and construction work to
be carried out and completed. The suitable management techniques shall be
implemented allowing for sufficient time for critical activities and to co-ordinate
all the activities in an efficient manner. These shall be taken care of at the time of
planning itself.
4.2 OBJECTIVES
1 The following are the objectives of the Distribution Planning Code:
(a) To enable the planning, design and construction of the Distribution System for
a safe and economical operation with the specified degree of reliability
conforming to the following standards:
(i) Distribution System Planning and Security Standard as mentioned
under Attachment 1 of this code
(ii) Provisions applicable to Distribution System under Power System
Management and Operating Standard and Power System Safety
Standard.
(iii) Statutory Acts and Rules, which are in force,
(iv) Relevant Indian Standard Specifications, if applicable. The deviations
may be permitted as per specified limit, however, in any case the
security and safety shall not be hampered.
(v) REC (Rural Electrification Corporation) Construction Standards and
manuals.
16
PAGE 16 OF 49
DISTRIBUTION CODE
(b) To facilitate the use of the Distribution System by any User connected to or
seeking connection with it,
(c) To prescribe the technical conditions to be followed by the respective
Distribution Licensees and Users in meeting the standards for an efficient
operation of the common electrical interface,
(d) To prescribe the procedure for the exchange of the system planning data
between the Distribution Licensee and the Users,
(e) To provide the required information to the Users for connection, planning and
development of their own systems and make them compatible with the
Distribution System,
(f) To enable the Distribution Licensee to co-operate with the Transmission
Licensee in furnishing the required data as detailed in the Grid Code.
PAGE 17 OF 49
DISTRIBUTION CODE
arrive at load forecast for succeeding five years after considering all the aspects viz.
government policy/ economic development etc. During this process he shall also
review the status of loads materialising as per the previous load forecast. Further
these forecast shall be in line with the plan to be developed at national level by
CEA. The variation to the forecast shall be incorporated by the Distribution
Licensee, as and when it is known to Distribution Licensee and revise the forecast
annually.
2 Energy sales in each tariff class shall be projected in the forecast period over the
corresponding figures relating to the base year by adopting an appropriate
statistical method.
3 The projections shall take into account the assumed normal growth for non-specific
loads, specific and identified loads of 1 MW and above, and the effects of demand
side management, if any, and energy conservation.
4 The peak load requirements at each Connection Point/ Interface Point shall be
estimated. The peak load requirement at each Connection Point / Interface Point
will essentially ensure that the STU may determine the corrective measures to be
taken to maintain the capacity adequacy in the Transmission System upto the
Connection Point /Interface Point. This will facilitate the Transmission Licensee to
develop the compatible Transmission System. However, if the Distribution
Licensee receive power at a number of Connection Points / Interface Points in a
compact area, which are interconnected in a ring, then such Distribution Licensee
shall forward the overall short term Demand forecast at each Connection Point /
Interface Point with the variation or tolerance as mutually discussed and agreed
upon with the STU.
5 The aggregate energy and peak load requirements for the Area of Supply shall be
estimated. The Distribution Licensee shall forward the short term demand forecast
for each Connection Point/ Interface Point for peak load requirement as well as
aggregate energy and peak load demand for Area of Supply on annual basis to the
STU, Transmission Licensee and GERC along with the following details on the
basis of which the forecast is made:
(a) Data,
(b) Methodology,
(c) Assumptions.
6 It shall be the responsibility of all the Distribution Licensees to fully co-operate
with the STU in preparation of demand forecasts for the entire Gujarat State. The
Distribution Licensee shall furnish the necessary peak load and energy forecasts to
STU/ Transmission Licensee for a period of 10 years in order to enable STU in
formulating the perspective plan, as detailed out in Grid Code.
18
PAGE 18 OF 49
DISTRIBUTION CODE
Circuits shall have adequate capacity to cater to their needs of electricity in a safe,
economical and reliable manner.
2 The Distribution Licensee shall assess and forecast the load demand of each
category of Consumers in his Area of Supply on annual basis or more frequently
as required by the GERC.
3 The Distribution Licensee shall have a thorough knowledge of the nature of
electricity usage by the Consumers and the way they use electrical energy and
other alternative sources of energy in his area. The load forecasting shall take into
account all these along with other conservation programs and the demand side
management or off-peak usage programs which the Licensee may sponsor,
resulting in reduction of energy used and peak demand of the Consumers over the
years.
4 The Distribution Licensee shall implement an appropriate load research program
for the systematic collection of data describing Consumers' energy usage patterns
and analysis of these data for energy and demand forecast. For this purpose, the
Consumers shall be divided into all the tariff classes and may be broadly in the
following classes:
(a)Domestic sector,
(b) Commercial sector,
(c) Agricultural sector,
(d) Industrial sector
The pattern of energy consumed by each sector and the load demand, the period of peak
demand etc., shall be determined on the basis of sample surveys taking
representative samples from each sector for its different seasonal requirements. A
suitable questionnaire shall be prepared for these sample surveys and the data
obtained shall be analysed using suitable statistical models. Based on this, load
profiles shall be drawn implementing demand side management techniques to
match the availability from time to time.
5 The load research program shall assess the following:
(a) Demand at the time of system peak, daily, monthly, seasonal or annual,
(b) Hourly demand for the day of the system peak, monthly, seasonal or annual,
(c) Total energy consumption for each category by month, season or year.
6 Based on the results of the above analysis the load forecast shall be made using
the appropriate modern forecasting tools wherever applicable.
7 The optimum Circuit loading and the maximum number of Circuits at any
electrical interface between the Distribution and Transmission Systems shall
conform to the Distribution System Planning and Security Standard as mentioned
under Attachment 1 of this code, Distribution System under Power System
Management and Operating Standard and Distribution System under Power
System Safety Standard.
8 As far as practicable, separate Circuits shall be provided for the following:
(a) Urban non-industrial power supply,
(b) Urban industrial power supply,
(c) Rural supply (as far as possible further segregation between rural agricultural and
rural non agricultural supply)
19
PAGE 19 OF 49
DISTRIBUTION CODE
9 The loads shall be arranged as far as possible in discrete load blocks to facilitate
load management during emergency operations.
10 Load flow and other system studies shall be conducted to locate the position of
outlets from substations, capacitor installations, distribution transformers, and to
contain voltage variation and energy losses within reasonable limits.
11 The following parameters of equipments and system designs shall be standardised
to facilitate easy replacement and reduction of inventories of spares in stores:
(a) Capacities of power transformers,
(b) Capacities and designs of distribution transformers,
(c) 22 kV/11kV substation layouts,
(d) Pole mounted substations,
(e) Sizes of bus bars,
(f) Capacities and ratings of circuit breakers and instrument transformers,
(g) Earthing,
(h) Lightning arresters,
(i) Control panels,
(j) Station batteries,
(k) Fire extinguishers.
(l) Maintenance tools
(m) Safety equipments
(n) Energy meters
(o) Wires and cables
(p) Clamps and connectors
12 The planning of the Distribution System shall always keep in view the cost
effectiveness and reduction in energy losses without sacrificing the requirements
of Security Standards and Safety Standards for the Distribution System.
13 The Distribution Licensee shall plan the Distribution System expansion and
reinforcement keeping the following in view along with all other measures to
accommodate the advancement in technology prevailing at the time:
(a) Economic ratio of HT and LT line lengths,
(b) Use of aerial bunched conductors,
(c) Underground cables,
(d) Optimising the number of distribution transformers and their location at the
electrical load centres.
20
PAGE 20 OF 49
DISTRIBUTION CODE
meters such that the energy supplied to the each feeder is accurately available. It
shall be compared with the corresponding figures of monthly energy sales and the
distribution loss for each feeder shall be worked out. In case the Distribution
Licensee has adopted ring main system at 11kV and there is difficulty in
determining the distribution losses for each feeder, then the Distribution Licensee
shall work out distribution losses for the overall Area of Supply.
***
5.
21
PAGE 21 OF 49
DISTRIBUTION CODE
SECTION-5
CONNECTIVITY CONDITIONS
5.1 INTRODUCTION:
1 The Connectivity Conditions specify the minimum technical and design criteria,
which shall be complied by any agency connected to, or seeking connection to the
Distribution System. The Distribution Licensee shall ensure compliance of the
above criteria by any agency as a pre-requisite for the establishment of an agreed
connection. The connectivity conditions should fulfill the requirement stipulated in
section 50 and 53 of the Electricity Act, 2003.
5.2 OBJECTIVES
1 The Connectivity Conditions are provided to ensure that:
(a) The basic rules for connections are complied by all agencies. This will help to
treat all agencies in a non-discriminatory manner.
(b) Any new or modified connection, when established, shall not suffer
unacceptable effects due to its connection to the Distribution System nor
produce unacceptable effects on the system or any other connected agency.
(c) The ownership and responsibility for all the equipments, shall be clearly
specified in a schedule (site responsibility schedule) for every site, where a
connection is made.
22
PAGE 22 OF 49
DISTRIBUTION CODE
4 The operation of the Distribution System shall be in accordance with the
"Distribution System Operating Standard" under Power System Management &
Operation Standard. The User shall however be subject to the distribution
discipline prescribed by the SLDC/Distribution Licensee.
5 The insulation co-ordination of the Users' equipment shall conform to the
applicable Indian Standards/Code of practices. The rupturing capacity of the
switchgear shall not be less than that notified by the Distribution Licensee.
23
PAGE 23 OF 49
DISTRIBUTION CODE
5.7 ACCEPTANCE OR REJECTION OF APPLICATION FOR
CONNECTION:
1 The acceptance or rejection of Consumers application for supply connection shall
be as per the Supply Code.
***
6.
24
PAGE 24 OF 49
DISTRIBUTION CODE
SECTION-6
OPERATION CODE
6.1 INTRODUCTION:
1 This section contains the procedures and practices to be followed for a safe and
efficient operation of the Distribution System by the Distribution Licensee and by
the Users of the Distribution System of their electrical plant and lines which are
connected to the Distribution Licensees system. This shall also apply to any
electrical interface between two Distribution Licensees for a safe and efficient
operation of interface.
2 The following aspects of operation are covered in this section:
(a) Demand Estimation
(b) Outage Planning
(c) Contingency Planning
(d) Demand Side Management and Load Shedding
(e) Interface with Small Generating Plant including CPPs
(f) Communication
(g) Monitoring and Control of voltage, frequency and power factor.
(h) Safety Co-ordination.
(i) Maintenance and testing
(j) Tools and spares
(k) Training
3 OUTAGE PLANNING:
1 The Distribution Licensee shall furnish his proposed outage programs to the
Transmission Licensee on a month ahead basis.
2 The outage program shall contain identification of lines and equipment of the
Distribution System proposed by Licensee.
3 The outage plan proposed by the Licensee shall come into effect only after the
Transmission Licensee releases the finally agreed transmission outage plan.
4 However at the time the line or equipment is taken out of service, the Distribution
Licensee shall intimate the Transmission Licensee to facilitate in accommodating
their maintenance work, if possible, even though the same is already included in
the approved plan.
5 In case of lines and equipment of 66 kV and above the specific concurrence of
SLDC shall be obtained in addition to the above.
25
PAGE 25 OF 49
DISTRIBUTION CODE
6 The above procedure shall not apply under the following circumstances:
(a) Emergency situations to save plant and machinery;
(b) In such of the unforeseen emergency situations requiring isolation of lines or
equipment to save human life,
(c) Where disconnection is to be effected on any User installation due to breach of
Agreement. In this case the SLDC shall be informed wherever the load to the
extent of 5 MW or more is affected.
7 Planned outages of Power System for the duration as specified in Standard of
Performance for Licensee for maintenance purposes shall be intimated to the public
through media including publishing in at least two largely circulated Newspapers
(one in English and one in Gujarati) of that area, two days in advance.
26
PAGE 26 OF 49
DISTRIBUTION CODE
restoration and the probable restriction of load drawl from the affected
substation.
(b) The Distribution Licensee shall effect the demand management plan
accordingly.
27
PAGE 27 OF 49
DISTRIBUTION CODE
6.7 COMMUNICATION:
1 Reliable communication links viz telephone, fax, teleprinter, etc. shall be
established for exchange of data, information and operating instructions between
the Licensee, Consumer with a demand of 5 MW and above and the SLDC. Each
constituent shall ensure installation and maintenance of proper communication
infrastructure at his end.
28
PAGE 28 OF 49
DISTRIBUTION CODE
apparatus, switchgear or circuits in any part of the Distribution System or in any
part of the User System. The safety manuals thus prepared shall be issued to all the
control persons and such Users for compliance.
3 There shall be co-ordination between persons of the Distribution Licensee and the
Users, between persons of two Distribution Licensees having electrical interfaces,
for carrying out the work on any apparatus or lines etc., belonging to either party at
the point of interconnection.
4 The provisions of the Grid Code shall be followed at Connection Points/ Interface
Points in co-ordination with the Transmission Licensee.
5 The disconnecting device(s) at each electrical interface, which shall be capable of
effectively disconnecting the system of the Distribution Licensee and the other
Users, and the grounding devices of the respective systems at the control boundary
shall be identified and marked by the Licensee and the respective Users. These
shall be maintained in good condition at all times. To prevent inadvertent
switching operations by unauthorised persons, such disconnecting devices shall be
provided with interlocks.
6 Wherever any Consumer has installed an emergency power supply system, either
an electronic system with storage batteries or with generators, the arrangement
shall be such that the same cannot be operated without clearly isolating the system
from the supply mains. The responsibility of making the required arrangement for
isolation from supply mains shall be of the User and this shall be part of the
electrical layout submitted to Electrical Inspector for his approval. The possibility
of a feed back from these devices to the Distribution System from any of the
conductors, including the neutral conductor shall be clearly ruled out.
7 The appropriate Control Person at the electrical interface shall issue written
permission to his counterpart for carrying out the work on any apparatus,
switchgear or lines beyond the electrical interface. Such permissions shall be
termed as "Line Clear Permits" (LCP). The format for LCP shall be standardised by
the Distribution Licensee and shall be used by all concerned.
8 The Distribution Licensee in consultation with the concerned User shall frame
checklist of operations to be carried out and the procedures for safety coordination
for each electrical interface, before issue and return of LCPs. Such procedures and
checklists shall be issued to all the concerned by the Licensee for implementation.
29
PAGE 29 OF 49
DISTRIBUTION CODE
equipment, preventive maintenance shall be carried out to ensure serviceability,
safety and efficiency.
3 The Distribution Licensee shall maintain well trained hot-line personnel, and all
the required tools in good condition, and conduct the maintenance work by using
hot-line technique, wherever possible, to reduce the period of interruption.
4 The Users shall maintain their Apparatus and Power Lines at all times
conforming to I.E. Rules 1956 which are in force for time being and will be
replaced by new rules made under Electricity Act, 2003 and shall be suitable for
being connected to the Distribution System in a safe and reliable manner.
6.12 TRAINING
1 The Distribution Licensee shall make appropriate arrangements for imparting
training to his workmen and supervisory staff, incorporating up-to-date
techniques of Distribution System design, construction and maintenance, safety,
consumer services etc. He shall frame a suitable syllabus for this purpose.
***
7.
30
PAGE 30 OF 49
DISTRIBUTION CODE
SECTION 7
7.1 INTRODUCTION:
1 This section specifies the procedure for metering in Distribution System with
respect to operational metering as well as tariff and commercial metering. This
section also specifies the general guidelines for protection of Distribution system.
31
PAGE 31 OF 49
DISTRIBUTION CODE
accuracy (as available in their inventory). It is desirable that the Distribution
Licensee shall purchase new CT/PT of 0.2 class accuracy.
5
6 The open access consumer, Generating company, Distribution licensee and traders
shall provide Meters, as may be specified by the Commission for such consumer
based on voltage, point and period of supply and tariff category (as also
incorporated in Grid Code) as per the Gujarat Electricity Regulatory Commission
(Open Access in Intra-state Transmission & Distribution) Regulations, 2004.
32
PAGE 32 OF 49
DISTRIBUTION CODE
the relevant IEC/IS specifications at least once a year and also whenever the
difference in readings between the main and check meters exceed 0.5%.
7 Records of these calibrations and tests shall be maintained for reference.
8 The Generating Companies, Transmission Licensees and Distribution Licensees
shall formulate and agree upon a procedure covering summation, collection and
processing of tariff meter readings at various interconnection sites of their area.
Whenever necessary, these procedures can be revised.
9
10 The ownership, responsibility of maintenance and testing of these meters shall be
as mutually agreed to between the Users and the concerned Licensees.
11 The term Meter shall include Current transformers, voltage/potential
transformers, wiring between them and meter box/panel.
33
PAGE 33 OF 49
DISTRIBUTION CODE
protection, as per CBIP manual vide publication 274, so that the system does not
suffer due to any disturbances originating at the generating unit.
6 Distribution System:- For Power Transformers of HV class in the Distribution
System, differential protection shall be provided for 10 MVA and above along with
backup time lag over current and earth fault protection with directional feature for
parallel operation. Transformers of 1.6 MVA and above but less than 5 MVA shall
be protected by time lag over current and earth fault. . In addition, all power
transformers shall be provided with gas operated relays, winding and oil
temperature alarm and protection.
7 Distribution lines: - All the 22 kV and 11 kV lines at Connection Points / Interface
Points shall be provided with a minimum of over current and earth fault relays as
follows:
(a) Plain radial feeders: Non-directional time lag over current and earth fault relays
with suitable settings to obtain discrimination between adjacent relay settings.
(b) Parallel/ring feeders: Directional time lag over current and earth fault relay.
8.
34
PAGE 34 OF 49
DISTRIBUTION CODE
SECTION-8
8.1 INTRODUCTION:
1 This section specifies the requirements for safe working practices for maintenance
of equipment associated with cross boundary operations and lays down the
procedure to be followed when the work is carried out on electrical equipment
connected to another User's System. User may mean another Licensee so that this
Code applies for safety across the boundary between two Licensees also, by
substituting another Licensee for User.
8.2 OBJECTIVE:
1 The objective of this section is to achieve an agreement on the principles of safety
when working across a control boundary between the Distribution Licensee and the
Users.
8.4 PROCEDURE:
1 The Distribution Licensee shall issue a list of Control Persons with their names,
designations, addresses and telephone numbers, to all the Users having direct
control boundary with him. This list shall be updated promptly whenever there is
any change of name, designation or telephone number of any Control Person
named in the list.
2 All the Users such as mentioned in 8.3.1 having a direct control boundary with the
Distribution Licensee shall issue a similar list of their Control Persons to the
Licensee. This list shall be updated promptly whenever there is any change of
name, designation or telephone number of any Control Person named in the list.
3 Whenever any work across a cross boundary is to be carried out by the User or the
Distribution Licensee, the Control Person of the User or the Licensee as the case
may be, who has to carryout the work, shall directly contact his counter part. Code
words shall be agreed to at the time of work to ensure correct identification of both
the parties. Contact between Control Persons shall normally be made by direct
telephone.
4 If the work extends beyond one shift, the Control Person shall hand over charge to
the relief Control Person and fully brief him on the nature of work and the code
words in the operation.
5 The Control Persons shall co-operate to establish and maintain the precautions
necessary to be taken for carrying out the required work in a safe manner. Both the
35
PAGE 35 OF 49
DISTRIBUTION CODE
established isolation and the established earth shall be kept in the locked positions
wherever such facilities exist, and these shall be clearly identified.
6 The Control Person in charge of the work shall satisfy himself that all the safety
precautions to be taken are established before commencing the work. He should
issue the safety documentation to the working party to allow the work to
commence.
7 After the completion of the work, the Control Person in charge of the work being
carried out should satisfy himself that the safety precautions taken are no longer
required, and shall make a direct contact with his counterpart Control Person and
request removal of the safety precautions. The equipment shall be declared as
suitable for return to service only after confirmation of removal of all the safety
precautions, by direct communication, using the code word contact between the
two Control Persons, and the return of agreed safety documentation from the
working party.
8 The Distribution Licensee shall develop an agreed written procedure for Cross
Boundary Safety and continuously update the same.
9 Any dispute concerning Cross Boundary Safety shall be resolved at the level of
STU, if STU is not a party. In case where STU is a party, the dispute shall be
referred to the GERC for resolution of the dispute.
36
PAGE 36 OF 49
DISTRIBUTION CODE
SECTION- 9
INCIDENT/ACCIDENT REPORTING
9.1 INTRODUCTION
1 This Section covers procedure of major incident / accident reporting (which occur
in Distribution System) by User to Licensee and Licensee to User and GERC.
37
PAGE 37 OF 49
DISTRIBUTION CODE
(h) Relay indications and performance of protection,
(i) Brief description of the incident,
(j) Estimated time of return to service,
(k) Any other relevant information,
(l) Recommendations for future improvement,
(m)Name and designation of the reporting person.
3 The report shall contain sufficient detail to describe the event to enable the
recipient to assess the implications and risks arising out of the same. The recipient
may ask for clarifications and additional information wherever necessary and it is
obligatory that the reporting User shall put his best efforts and provide all the
necessary and reasonable information.
4 In case of a request by either party, the oral report shall be written down by the
sender and dictated by way of a telephone message or sent by Fax/e-mail to the
recipient. In case of an emergency the report can be given only orally and followed
by written confirmation.
5 Reporting of accidents shall be in accordance with the rules framed under relevant
provision made under Electricity Act, 2003 or other applicable rules. Till such
rules are made, the Distribution Licensee shall follow reporting of accidents as
mentioned in Power System Safety Standard.
***
10.
38
PAGE 38 OF 49
DISTRIBUTION CODE
ATTACHMENT - 1
1.0 INTRODUCTION
1 The Distribution System Planning and Security Standard specifies the guidelines
for planning methodology of the Distribution System. The scope of this standard
covers
(a) Quality of power supply
(b) Load forecast
(c) Planning procedure.
(d) Service area of a distribution network.
(e) Planning standards.
(f) Reliability analysis.
(g) Standardisation of design of distribution transformer
(h) Standardisation of substation layouts
(i) Reactive Compensation
(j) Service Mains
(k) Metering Cubicles
(l) Security Standards
39
PAGE 39 OF 49
DISTRIBUTION CODE
appropriate demand making due allowance in the growth rate to account for
increased tempo of household electrification envisaged in the future. The higher
level of electrification planned in the area should be kept in view. Energy
consumption per Consumer shall be estimated after studying the past trends and
taking into account the anticipated improvements in the standard of living.
2 Public Lighting and Water Works: The estimates of electricity consumption in
public lighting and water works shall be based on the average consumption per
kilowatt of connected load, projected on the basis of trends, keeping in mind the
likely increase in public lighting and water supply facilities. The number of hours
of operation shall be estimated taking into account the past trends and the power
cuts if any effected in the area.
3 Agricultural Loads: The power requirement for irrigation pump sets shall be based
on the program of energisation of pump sets in the plan period, available resources
and the ultimate ground water potential. The average capacity of pump sets shall be
worked out considering the mid-year figures for connected load and the number of
pump sets. The consumption per IP set per year shall be estimated by means of
representative sample studies till all the IP sets are metered.
4 Industrial Loads: The power requirements for industrial sector shall be estimated
under following three categories, viz.
(a) L.T. Industries;
(b) H.T. Industries with a demand of less than 5 MW;
(c) H.T. Industries with a demand of 5 MW & above.
The consumption in category (a) & (b) shall be on the basis of historical data duly
considering the developments in future. In case of category (c), projection shall be
made separately for each industrial unit on the basis of the information furnished
by the industrialists and the Department of Industries.
5 Non-industrial Bulk Supply: The available data regarding the consumption of bulk
supply to non-industrial Consumers such as research establishments, port trusts,
military engineering services, supply to power projects etc., and the probable future
developments in these areas, shall be considered for the forecast.
6 Other Loads: For other loads, the projections shall be based on the best judgement.
40
PAGE 40 OF 49
DISTRIBUTION CODE
Point / Interface Point with the variation or tolerance as mutually discussed and
agreed upon with the STU.
3 The diversity factor of each category of Consumers fed in the Area of Supply shall
be worked out by installation of load survey meters at selected typical locations. A
record of such data shall be maintained and continuously updated. The short-term
load forecast for a period of five years, based on these data shall be prepared.
41
PAGE 41 OF 49
DISTRIBUTION CODE
shall be standardised with the objective of reducing inventory and standard
specifications shall be prepared.
2 Design Criteria for Distribution Lines
1 Radial system of distribution can be adopted in rural areas and as far as possible
loop system with provision for feeding from at least one alternate source shall be
adopted in urban areas.
2 The HT and LT distribution lines shall be any of the following types according to
the necessity at the required area.
(a) Over-head line with bare conductors;
(b) Over-head line with Aerial Bunched Cables;
(c) Under-ground Cables.
3 In thickly populated cities, in areas having heavy traffic densities, under ground
cable installation shall be considered to the extent possible. Wherever a number of
trees are encountered, either in residential locations or in gardens and forests,
over-head lines with aerial bunched cables shall be adopted. In other places
over-head lines with bare conductors shall be adopted. The following standards
shall be adopted for planning and design purposes:
(a) The design and construction of over-head lines with bare conductors shall be
generally in accordance with IS 5613 Part I, sections 1 and 2.
(b) Vertical configuration of conductors for LT distribution lines, to prevent
accidental short circuit due to galloping of conductors, shall preferably be
adopted in rural areas since the spans are large in such areas.
(c) The maximum length of LT and HT lines shall be maintained within the
prescribed limit so as a safe and quality power may be delivered.
(d) The design and construction of over-head lines with aerial bunched cables shall
be generally in accordance with REC Specifications 32 and IS 14255.
(e) The design and construction of under-ground cables shall be generally in
accordance with IS 1255.
4 The line supports can be of steel, wood, RCC or PCC. The RCC and PCC poles are
preferred over the other two considering their cost and longer life. The choice of
the size of conductor for a line shall be made based on the following criteria:
(a) Power to be transmitted and the techno-economic studies conducted for
selecting the size of conductor according to the cost of loss of power and the
interest and depreciation charges on the cost of the conductor thus selected;
(b) Length of Line;
(c) Line Voltage;
(d) Permissible voltage regulation;
(e) Mechanical strength;
(f) In coastal areas and other areas where severe corrosion is expected due to
heavy rainfall and/or salinity in atmosphere and theft prone areas, appropriate
conductors only shall be used.
42
PAGE 42 OF 49
DISTRIBUTION CODE
the Distribution System before and after the implementation of the extension and
improvement program shall be estimated. The planning of the distribution system
shall also take into consideration the improvement in reliability and efforts should
be made to collect the data in this regard.
2 The following factors, which affect reliability indices, shall be considered subject
to availability of data:
(a) Momentary incoming supply failures
(b) Momentary interruptions on 22 and 11 kV feeders
(c) Breakdown on LT feeders
(d) Prearranged shutdowns on lines and feeders
(e) Blowing out of distribution transformer fuses
(f) Individual fuse off calls
43
PAGE 43 OF 49
DISTRIBUTION CODE
measures, such as automatic switching etc., shall be adopted to avoid over voltages
at light load periods.
2 Optimisation studies of shunt compensation shall be conducted by the Distribution
Licensee to determine the most appropriate sizes and locations for shunt capacitor
installations.
44
PAGE 44 OF 49
DISTRIBUTION CODE
2 The feeders, either HT or LT, feeding important loads such as hospitals,
crematoria, airports, railway stations, and the like shall be planned to have a
selective switching system, so that selective switching can be operated to transfer
the load on to an alternate healthy feeder. Appropriate safety precautions shall
invariably be taken in this regard. In case of failure of the feeder, these switches
shall be operated immediately either manually or automatically depending on the
importance of the load.
3 The feeders connected to important industries which are very sensitive to
interruption of even short duration shall be planned to have automatic switchover
to an alternate healthy feeder in case of failure of supply.
4 Loading in any current carrying component of the Distribution System (e.g.
Conductors, joints, transformers, switchgear, cables and other apparatus) shall not
exceed 75% of their respective thermal limit.
5 The rupturing capacity of the switchgear employed in the system shall have at least
25% more capacity than the short circuit level computed even considering the
anticipated future development of the system.
6 Provision shall be made for every HT feeder, either primary or secondary, to
manually switch over to the immediately available HT feeder of the same voltage
class available in the vicinity. Provision shall be made in the design itself for any
HT feeder to share at least 50% of the loads in the adjacent feeder during
emergencies.
7 In case of single contingency; failure of any substation equipment controlling any
outgoing 11 kV feeder, the load interrupted shall not generally exceed 50% of the
total demand on the substation. The Distribution Licensee has to bring it down to
20% within a period of three years.
8 There shall be adequate stand by capacity in the system.
9 The design of the Distribution System shall accommodate the arrangements in such
a way that the electricity supply need not be interrupted for more than the specified
duration in Standard of Performance of Licensee in case of breakdown of any
distribution transformer. Similarly in case of failure of 11 kV feeders including
terminal equipment, the design shall accommodate an arrangement for the power
supply not to be interrupted to the extent possible.
***
45
PAGE 45 OF 49
DISTRIBUTION CODE
ANNEXURE 1
46
PAGE 46 OF 49
DISTRIBUTION CODE
ANNEXURE 2
SYSTEM DATA (CLAUSE 4.3.3)
The Distribution Licensee shall provide only relevant details out of the following details as
required by Consumer for designing and selecting electrical equipment:
47
PAGE 47 OF 49