0% found this document useful (0 votes)
60 views4 pages

Methods and Details of All Tests and Inspections (Stringing Work)

This document provides inspection and testing details for stringing work on the Rajamandala Hydroelectric Power Plant 1x47MW project transmission lines. It outlines the checklists, reports, and testing plans for tower erection, including torque bolt testing and earthing system testing. The document applies to inspections by the project owner and contractors to ensure quality control on transmission line construction works.

Uploaded by

Idris Affandi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views4 pages

Methods and Details of All Tests and Inspections (Stringing Work)

This document provides inspection and testing details for stringing work on the Rajamandala Hydroelectric Power Plant 1x47MW project transmission lines. It outlines the checklists, reports, and testing plans for tower erection, including torque bolt testing and earthing system testing. The document applies to inspections by the project owner and contractors to ensure quality control on transmission line construction works.

Uploaded by

Idris Affandi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT RAJAMANDALA HYDROELECTRIC POWER PLANT 147MW

METHODS AND DETAILS OF ALL TESTS AND


INSPECTIONS (STRINGING WORK)

DOCUMENT No. :
PLN APPROVAL NO. : 2013/REP/TL/S/B-III/01/010
CONTRACTORS NO. : HI-E-TL-TL-R2-00050-A

EMPLOYER : RAJAMANDALA ELECTRIC POWER (REP)


EPC CONTRACTOR : HYUNDAI ENGINEERING CO., LTD. (HEC) (SUPPLY CONTRACTOR)
PT. TEKNIKO INDONESIA (TI) (CONSTRUCTION CONTRACTOR)

ISSUE STATUS

A ISSUED FOR APPROVAL IDRIS A A RAHMAN AGUS S

REV. No. DATE DESCRIPTION PREPARED CHECKED APPROVED


RAJAMANDALA
HYDROELECTRIC POWER PLANT 147MW

METHODS AND DETAILS OF ALL TESTS AND


INSPECTIONS (STRINGING WORK)

-OCTOBER-2017
DOC.No. : HI-E-TL-TL-
RAJAMANDALAHYDROELECTRICPOWERPLANT147MW R2-00050-A
METHODS AND DETAILS OF ALL TESTS AND Issue Date :
INSPECTIONS (STRINGING WORK) Rev.No. :
Page :

CONTENTS

1. Purpose

2. Scope
2.1. Check List for Tower Erection
2.2. Tower Inspection Report
2.3. Torque Bolt for Erection of Tower
2.4. Test Earthing System / Grounding

3. Inspection and Test Plan for Erection

4. Check List for Tower Erection

5. Tower Inspection Report

6. Torque Bolt for Erection of Tower

7. Test Earthing System / Grounding


DOC.No. : HI-E-TL-TL-
RAJAMANDALAHYDROELECTRICPOWERPLANT147MW R2-00050-A
METHODS AND DETAILS OF ALL TESTS AND Issue Date :
INSPECTIONS (STRINGING WORK) Rev.No. :
Page :

1. Purpose

This purpose of this inspection and test plan is to describe the process of
Inspection and Test which will perform at site to accomplish the Rajamandala
Transmission Line 150kV works.

2. Scope

This Inspection and Test Plan (ITP) is applicable to inspection by REP-HEC,


Quality Control, and Test Inspection personnel on all works within the scope of
works of REP-HEC for Rajamandala Project, as following :
-