Substructure
Substructure
1 Substructure
Substructure is the lower portion of the building which transmits the dead load, live loads and
other loads to the underneath sub soil. In buildings, the portion of the structure that is above
ground level that receives the live load is referred to as superstructure. Such as the substructure
is start from ground beam, column stump, pad footing and also foundation ( Bakau pile ). In
this project will show the elements of substructure.
Deep Foundations
Deep foundations are those founding too deeply below the finished ground surface for their
base bearing capacity to be affected by surface conditions, this is usually at depths of 3 meter
below finished ground level. Deep foundations can be used to transfer the load to a deeper,
more competent at depth if unsuitable soils are present near the surface.
a) End bearing pile.
b) Friction pile.
1) Timber Pile
In this project the type of foundation is deep foundation and it used the Timber pile. Follow the
specification on the bill of quantity and structural drawing the timber pile used based on the
conditions of soil. The timber pile will absorb the load from foundation and also from the live
load as a motorcycle and vehicle.
On this project it used around 300 unit of Timber. The center to center (cc) of timber is 400mm
between each others. This size was produce by structure engineer as RAF consultant.
Design consideration
Lean concrete is a mix where the amount of cement is lower than the amount of liquid present
in the strata. This makes it ideal as a base layer where other kinds of concrete are placed on top.
It is good for providing a flat bottom in uneven or dirt terrain(M10). The lean concrete thickness
is 50mm laid around the retaining wall areas.
Function of lean concrete is to provide layer or to avoid the bottom layer of ground beam to
touch a soil.
This machine is used because it suitable for this work of installation timber. In this work
process used the backhoe for press the timber till immersed. Backhoe also are familiar used
at site because it friendly used to many types of work progress especially in install the
timber pile.
Backhoe also used for laying the lean concrete before the beam or footing started in
progress.
appendix