1.0 Weather:: Daily Diary: by Supervision Consultant, CECB. (Zone A)

This daily diary summarizes construction progress and inspections for the AVIC Mixed Development Project on March 4, 2016. The weather was sunny throughout the day. Over 100 workers from the main contractor and subcontractor were on site. Inspections were carried out of formwork, reinforcement, concrete work, and curing on slabs, columns, beams and ramps. Drawings and shop drawings were referenced during inspections. No defects or issues were reported. Method statements for aluminum formwork and plumbing drawings were referred to but none were received. Overall progress and quality were found to be satisfactory.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
201 views2 pages

1.0 Weather:: Daily Diary: by Supervision Consultant, CECB. (Zone A)

This daily diary summarizes construction progress and inspections for the AVIC Mixed Development Project on March 4, 2016. The weather was sunny throughout the day. Over 100 workers from the main contractor and subcontractor were on site. Inspections were carried out of formwork, reinforcement, concrete work, and curing on slabs, columns, beams and ramps. Drawings and shop drawings were referenced during inspections. No defects or issues were reported. Method statements for aluminum formwork and plumbing drawings were referred to but none were received. Overall progress and quality were found to be satisfactory.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Project : AVIC Mixed Development Project

Daily Diary : By Supervision Consultant, CECB. (Zone A)

Date : 04/03/2016

1.0 Weather:

Duration 06hrs 08hrs- 10hrs 12hrs 14hrs 16hrs 18hrs 22hrs 24hrs 02hrs 04hrs
_
08hrs 10hrs 12hrs 14hrs 16hrs 18hrs 20hrs 24hrs 02hrs 04hrs 06hrs
Weather S S S S S S LR
* S Sun Shine, HR-Heavy Rain, LR Light Rain, G- Gloomy, W Windy

2.0 Manpower:
A: Main contractor:

Category Nos. Category Nos. Category Nos.


Project manager 01 Masonry workers - Surveyor 01
Site Manager 02 R/f fabricators 33 Carpenters 51
Site Engineer 03 Mech. Workers 01 Welders 03
Tech. assistant 04 Operators 04 General workers 23
Foreman 12 Concreters 09 Survey Helper 01
B: Nominated sub-contractor:

Category Nos. Category Nos. Category Nos.


Kents officers 7 Kents workers 14

3.0 Machineries & Equipment:

Category Nos. Category Nos. Category Nos.


Tower crane 2 Breakers 0 Excavators 0
Mobile crane 0 Vibrators 0 Mixers 0
Bar bending machines 2 Pump car 1 water pumps 1
Bar cutting machines 2 Survey instruments 2 Jack Hammers 2
compressors 1 Welding plants 1

4.0 Inspection Carried out:

Location Element Works inspected By whom Status


TF at 13 - Slab Formwork level Sampath,Dulan Done
16/A-D
TF at 5- Slab Reinforcement Sampath In progress
16/A-D
PL-TF at 24- Arch fin & Concrete Lasitha ,Situge Done
29/D columns
TF at 16- Beam Thermo couple Situge Done
23A/A-D
GR at 23- Ramp Curing Dulan Done
32/A1
TF at 2- Slab Sleeve Situge In progress
16/A-D

1 of 2
5.0 Drawings / Sketches referred for inspection:

Description Construction Shop Sketches/


Issue Drawings Log note
Transfer Level-Civil X X X
Column drawing-Civil X X

6.0 Effects of work (accidents, breakdown, delay etc...):

7.0 Details of Material used for construction:

Material Approved Brand Material Approved Brand


Reinforcement Plumbing
R/f Melwa/Lanwa Upvc puddle National
Concrete collar
C50 SCC Tokyo super
Bara emulsion Finco Electrical
Water proofing

8.0 Defects observed:

Location Element Type of defects Action taken Status

9.0 Site Instruction / Defect Notification issued:

Description Instruction Ref No Remarks

10.0 Approved Method statements referred and received:


A: referred
Aluminum formwork WF-745
Plumbing opening drawing WF-888/868
B: received
Description Ref. No By whom
no

11.0 General Comments:

Prepared By: S.M.J.M.T.Situge Date: 09/03/2016

2 of 2