Pump Questions PDF
Pump Questions PDF
Q1 Problem:
A seepage water sump has been installed next to a clean water reservoir. All the seepage water that
gathers in this sump must be returned back into the clean reservoir. You are asked to install a pump
station that is able to perform two duties, namely:
Transfer at least 45l/s of seepage water from the sump into the reservoir under normal
conditions
Transfer 80l/s of seepage water from the sump to the reservoir during rainy conditions.
As your client already has HDPE Pipe available (200mm OD, with 6mm wall thickness), this pipe must
be used in your installation. The pipe must be installed such that it takes suction from the bottom of
the sump and discharges into the top of the reservoir. You can assume that the exit velocity head at
the discharge point is negligible. You can also assume that 100m of pipe will be installed with 6 90
bends.
Your client has four identical pumps in his stores. Each pump requires a 22kW supply.
Your client has two available switchgear buckets. If possible, the client would prefer that the
maximum power drawn from each bucket is 15kW.
Assume a constant pump efficiency of 85%.
The NPSH available is sufficient for the installation.
The maximum static head between the sump water level and the top of the reservoir is 19m.
The pump characteristic curve can be plotted using the following table:
Flow (l/s) (1 Pump) Head (m)
0 38
5 37.5
10 36
15 35.5
20 35
25 34
30 33
35 30
40 28
45 25
50 22
55 19
60 15
Pump configuration and valve installation is at your discretion. All losses associated to the
pump installation can be neglected.
The following properties should be used in your calculations.
Density 998 kg/m3
Viscosity 1.00E-03 kg/ms
Gravity 9.81 m/s2
Pipe roughness
factor 0.0015 mm
Q1 Solution:
Service water is used for cooling water at a power station. A pressurised manifold is used to supply
service water to various points at the power station. This is an expensive operation as the price of
river water (used as the normal service water supply) is slowly rising. Power stations have other
sources of water that is also suitable for service water supply such as rain water or recovered run off
water. This water is captured at a power station in a recovery reservoir.
You are asked to install a pump station that is able to recover water from the recovery reservoir into
the pressurized service water manifold. Your pump station must be able to perform two duties,
namely:
Transfer at least 75l/s of recovered water from the reservoir into the service water
manifold under normal conditions
Transfer at least 140l/s of recovered water from the reservoir into the service water
manifold during rainy conditions.
Your client already has commercial steel pipe available (250mm NB, with 6mm wall thickness, SANS
719). This pipe must be used in your installation. The pipe must be installed such that it takes suction
from the bottom of the reservoir and discharges into the service water manifold at a pressure of
200kPa. The gauge pressure in the manifold is 190kPa so you can assume that the exit velocity head
at the discharge point is negligible. You can also assume that 100m of pipe will be installed with 4
90 bends.
Your client has four identical pumps in his stores. Each pump requires a 45kW supply.
Your client has two available points of supply in the nearest switchgear room. If possible, the
client would prefer that the maximum power drawn from supply point is 30kW during
running conditions.
Assume a constant pump efficiency of 85%.
The NPSH available is sufficient for the installation.
The maximum static head between the reservoir water level and the service water manifold
is 10m.
The pump characteristic curve can be plotted using the following table:
Flow (l/s) (1 Pump) Head (m)
0 72
10 68
20 65
30 62
40 59
50 53
60 50
70 42
80 35
90 30
100 22
110 18
120 10
K (250 NB Pipe)
Sharp Entrances 0.5
Non-Return Valves 2.5
Gate Valves 0.15
T-Pieces 0.1
90deg Elbows 0.31
45deg Elbows 0.16
Sharp Exits 1
Pump configuration and valve installation is at your discretion. Remember that you will
need to protect your pumps/service water manifold using NRVs and Isolation Valves. Minor
losses due to the pipeline installation around the pumps can be ignored.
The following properties should be used in your calculations.
Q2 Solution:
You are asked to complete a pump installation design. The following information is available:
a) For a flow rate of 80l/s and 120l/s, calculate hloss and hp. Tabulate your answers in the
given table on pg 5. (4)
c) If a flow rate of 0.045m3/s is required, how many identical pumps would you use? In what
configuration? What is your expected duty point? (3)
d) Discuss any other pertinent information necessary for your pump installation. (2)
Pump Curve vs System Resistance Curve
50
45
40
35
30
Head (m)
25
20
15
10
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
Flow (l/s)
Q3 Solution
Two pumps
In series
Your manager has asked you to complete the design of a pump station between the open
dam at the Vaal Water Purification Plant and a private reservoir on a neighbouring farm.
The Moody Chart is available to you. You may also use Haalands Approximation where:
[ ( ) ]
(a) Complete the design of the pumping system by determining the best pump
configuration to meet the flow requirements.
i. You only need to plot 4 points to generate the system resistance curve
namely 0l/s, 40l/s, 80l/s and 120l/s.
ii. Also please show your expected pump configuration on the given graph.
iii. State the expected operating point as well as any other necessary information
to complete the design.
K FACTORS K (200 NB Pipe)
Sharp Entrances 0.5
Non-Return Valves 2.5
Gate Valves 0.15
T-Pieces 0.1
90deg Elbows 0.31
45deg Elbows 0.16
Sharp Exits 1
Flow Rate (l/s) Velocity Reynolds Num hlosses hpump
Vlooi Tempo
40
80
120
140
120
100
Head (m)
80
60
40
20
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Flow (l/s)
Q4 - Solutuion
Vlooi Tempo
0 0 0 0 25.21 m
Q = 92 l/s, h =42.5m
Power consumption:
Inform farmer to install switchgear for two pumps sufficient sized for a minimum rating 30kW
as well as control system (pressure switches, flow switches etc) for pump protection.