Repair & Rehabilitation of Distressed Structures (Repair & Retrofitting)
Repair & Rehabilitation of Distressed Structures (Repair & Retrofitting)
DrChitrarekha Kabre
Repair&RehabilitationofDistressed
Structures(Repair&Retrofitting)
Definition
A distressed building is considered to be any
residential commercial,
residential, commercial industrial,
industrial or mixeduse
building (excluding sheds and garages on
residential property) that is not occupied and has
visible signs of physical distress (boarded, burned,
open to the elements, or otherwise
deteriorated).
Buildings used for storage may be surveyed as
distressed if they are boarded or appear
otherwise unoccupied.
1
8/30/2017
2
8/30/2017
Condition Assessment of
Buildings
1. The building has not shown any signs of distress
and it satisfies all the safety and serviceability
requirements
i t according
di t relevant
to l t Codes
C d off
practice, hence no action is needed towards
retrofitting.
2. The building is seen to be deficient (or
distressed) but it can be repaired and
strengthened to satisfy the Codal safety
requirements or performance criteria set by the
user.
user
3. The building is badly damaged. It is to be
demolished and a new building may be built,
build back better
3
8/30/2017
http://www.civil.mrt.ac.lk/ICSBE_2010/vol_01/31.pdf
STRUCTURAL REMEDIATION & RETROFIT OF
DISTRESSES PRECAST-PRESTRESSED T BEAMS
OF A PUBLIC UTILITY BUILDING, IN COLOMBO, SRI
LANKA A SITE CASE STUDY
4
8/30/2017
Summary
1. A public utility building of a
government department
situated in the central
business district (CBD) of
Colombo, Sri Lanka
comprises of the front tower
portion of basement +
ground + 14 upper floors
and a rear portion rising 4
floors high.
high The roof slab of
a portion comprises of
precast prestressed T
beams.
Summary
1. There was a huge fire in this building on 20th February 2009
and during the subsequent refurbishment of the building it
was noted that the majority of the 4th floor (roof floor) T
beams of the rear portion of the building were exhibiting
structural distress in the form of cracks.
2. The structural distress was due to event overloading onto the
roof slab during the fire fighting operations.
3. Certain remediation and retrofit measures to the distressed
elements were necessary to bring the T beams back to their
intended service performance level.
4. Repairs to cracks were carried out using multi-port, low
pressure resin injection, the retrofit was carried out using the
Carbon Fibre Reinforced Polymer (CFRP) system.
5
8/30/2017
OBJECTIVES:STRUCTURALREPAIR&
RETROFIT
Restoring the structural integrity of the cracked
beam elements i.e. repair
p
Recommended repair technique was surface
mounted, multi-port low viscosity epoxy resin
injection into the cracks
Enhancement in the flexural capacity of the
repaired beams i.e. retrofit
Conventional techniques such as concrete
j k ti or steel
jacketing t l plate
l t bonding:
b di i
invasive,
i ti
time
consuming process and additional dead loads
Recommended retrofit technique was carbon
fibre reinforced polymer (CFRP) wrapping
6
8/30/2017
7
8/30/2017
Crackinjectionresinproperties
An appropriate crack injection resin was
selected based on the following physical and
mechanical criteria:
1. Viscosity low enough to have good
penetrability into hair line cracks.
2. Pot life long enough to facilitate the
proposed low pressure, surface mounted,
multi p
port injection
j technique.
q
3. Good mechanical properties such as bond
strength, tensile strength, slant shear
strength.
8
8/30/2017
9
8/30/2017
10
8/30/2017
11
8/30/2017
Retrofit CFRPWrapInstallation
The two components of the saturant resin matrix were mixed
together in the ratio as per manufacturers specifications.
Sized fabric was then manually saturated from both sides with
the mixed resin matrix.
Saturation was carried out manually using fabric rollers.
The saturated fabric was then rolled onto spools and taken to
site for installation.
Prior to installation of the CFRP wraps, the prepared surface
was first wet primed with a coat of saturant resin.
The saturated fabric was then installed onto the primed surface
by evenly rolling out the spool along the primed surface.
The CFRP strips were adhered onto the surface using uniform
hand pressure along the main fibres, thus ensuring removal of
any entrapped air voids behind the CFRP wrap.
Additional layers were installed on wet strips to build up to the
required number of layers as specified
12
8/30/2017
STRUCTURALRETROFITTING:CASE
STUDY
13
8/30/2017
Summary
The subject building is ground + 12 upper floors RC
framed residential building structure with masonry
infills and is more than 30 years old.
The building belongs to Syndicate Bank namely
Panchratna CHS Ltd., 4-E, Damodar Park, Ghatkopar
(W), Mumbai 400086.
The building was identified as dilapidated structure
by Municipal Corporation (MCGM) for immediate
demolition within 30 days
14
8/30/2017
Distress
The major type of distress observed in RC elements
were of moderate damage level.
Age related distress and fatigue were identified in all
RC members.
Distress were in the form of cover failure to
reinforcing bars, spalling of concrete due to
corrosion born internal stresses, Open cracks etc.
Foundation was inspected up to pile cap then further
digging was stopped as concrete found was sound.
15
8/30/2017
16
8/30/2017
HeightandUnprotectedSurface
Diagnosis
Step 1: Categorisation into one of the three manifestation
of concrete damage g cracking,
g, spalling
p g or disintegration.
g
Step 2 : Error in design (not available)
Step 3: Relate basic symptoms to potential causes.
Step 4: Eliminate the possibilities which are readily
identified like corrosion of Reinforcement, Reinforcing bars
rust and cover spall, Parallel cracks along reinforcing bars
and Rust stain
Step 5: Analysis of available clues like Disintegration of
surface, Unsound material, Weathering conditions,
Abrasion action, Swelling of Concrete, Chemical reactions,
Moisture absorption, Crack penetration / depth of crack and
Cold or construction joints
17
8/30/2017
18
8/30/2017
19
8/30/2017
20
8/30/2017
21
8/30/2017
22
8/30/2017
1.LatexModifiedCementitious
Mortar
The most suitable material for RC repair is Latex
Modified Cementitious Mortar.
The advantages of such mortar are underlying in its
properties of control strength gain, set time and
reduce shrinkage.
These contain Polymers to improve low permeability
and to enhance the adhesion.
2. Micro-concrete
23
8/30/2017
3. Replacing Concrete
Areas of concrete which have been cut away
were made good depending on situation,
situation scope
of work and type / importance of member under
repair.
Recasting of broken chajjas (sun sheds), coping,
etc. were done using ordinary concrete.
4. Grouting
There were certain
locations where
h
honeycomb b or rockk
pockets existed.
Such locations required
the packing by non
shrink low viscosity
material.
The existing cracks in
RC were sealed by low
viscosity and very low
viscosity.
24
8/30/2017
25
8/30/2017
26