Project Report
Project Report
1
ACKNOWLEDGEMENT
2
TABLE OF CONTENTS
Sl. No TOPIC PAGE NO.
Acknowledgement 2
1. Substation 5
Introduction 5
Functions of a Substation 5
Classifications of Substations 7
Boundary Conditions 11
Substation Site Selection 13
Substation Parts and Equipment 13
Substation Protection 15
Earth Resistance 16
Step Potential and Touch Potential 17
Formation of Substation Earthing 18
Equipment and Structure Earthing in Substation 19
Lightning Protection 22
2. Components of Substation 26
Lightning Arrester 26
Capacitor Voltage Transformer 30
Wave Trap 33
Isolator 34
Current Transformer 36
Circuit Breaker 38
Bus 42
Transformer 42
3
3. AN OVERVIEW OF 400/220 kV Ballabgarh Substation 44
Introduction 44
Features Of Ballabgarh Substation 45
Commissioning Chronology 45
Single Line Diagram Of 400/220 kV Ballabgarh Substation 48
4
1. SUBSTATION
INTRODUCTION
Substations are the interconnection points within the power transmission and
distribution system between regions and country. Substation is an assemblage of
electrical components including busbars, switchgear, power transformers,
auxiliaries, etc. Basically, an electrical substation consists of a number of incoming
circuits and outgoing circuits connected to common busbar system. Busbars are
conducting bars to which a number of incoming or outgoing circuits are
connected. Each circuit has certain electrical components such as circuit-breakers,
isolators, earthing switches, current transformers, voltage transformers, lightning
arrester, etc. These components are connected in a definite sequence such that a
circuit can be switched off/on during normal operation by manual/remote
command and also automatically during abnormal conditions such as short-
circuits. A substation receives electrical power from generating station via
incoming transmission lines and delivers electrical power via the outgoing
transmission lines. Substations are integral parts of a power system and form
important links between the generating stations, transmission and distribution
systems and the load points.
Functions of a sub-station:
An electricity supply undertaking generally aims at the following:
5
Maximum possible coverage of the supply network over the given
geographical area.
Maximum security of supply.
Shortest possible fault duration.
Optimum efficiency of plants and the network.
Supply of electrical power within targeted frequency limits.
Supply of electrical power within specified voltage limits.
Supply of electrical energy to the consumers at the lowest cost.
As a result of these objectives, there are various tasks which are closely
associated with the generation, transmission, distribution and utilization of the
electrical energy. These tasks are performed by various, manual, semi-automatic
and fully automatic devices located in generating stations and substations.
The tasks associated with a major substation in the transmission system include
the following:
All these tasks are performed by the team work of load-control centre and control
rooms of substations.
6
CLASSIFICATIONS OF SUB STATIONS
Primary substations are associated with the power generating plants where the
voltage is stepped up from low voltage (3.3, 6.6, 11, 33kV ) to 220kV or 400kV for
transmitting the power so that huge amount of power can be transmitted over a
large distance to load centers.
These substations are located at suitable load centers along with the primary
transmission lines. At primary Grid Power Substations the primary transmission
voltage (220kV or 400kV) is stepped down to secondary transmission voltages
(110kV) . This Secondary transmission lines are carried over to Secondary Power
Substations situated at the load centers where the voltage is further stepped
down to Sub transmission Voltage or Primary Distribution Voltages (11kV or
33kV).
Distribution Electrical Power Substations are located at the load centers. Here,
the Sub transmission Voltages of Distribution Voltages (11kV or 33kV) are stepped
down to Secondary Distribution Voltages (400kV or 230kV). From these
Substations power will be fed to the consumers to their terminals.
7
Basis Of Service Rendered:
1. Transformer Substation:
Transformers are installed on such Substations to transform the power from one
voltage level to other voltage level. At these Substation lines of different voltage
levels are linked with each other through the transformer.
2. Switching Substation:
Switching substations are meant for switching operation of power lines without
transforming the voltages. At these Substations different connections are made
between various transmission lines.
3. Converting Substation:
This type of Substation associated with operating voltages between 11kV and
66kV. Such substations are generally part of a distribution system.
8
2. Extra High Voltage Electrical Power Substation:
Substations where Operating Voltages are above 400kV is called Ultra High
Voltage Substation.
9
Based on Design Configuration:
In Air Insulated Power Substations busbars and connectors are visibe. In this
Power Substations Circuit Breakers and Isolators, Transformers, Current
Transformers, Potential Transformers etc are installed in the outdoor. Busbars are
supported on the post Insulators or Strain Insulators. Substations have galvanized
Steel Structures for Supporting the equipment, insulators and incoming and
outgoing lines. Clearances are the primary criteria for these substations and
occupy a large area for installation.
Hybrid Substations are the combination of both Conventional Substation and Gas
Insulated Substation. Some bays in a Power Substation are Gas Insulated Type
and some are Air Insulated Type. The design is based on convenience, Local
Conditions available, area available and Cost.
10
Boundary conditions
The following boundary conditions influence the design concept and measures to
be considered for different parts of substation installations.
Outdoor/ Indoor
AIS/ GIS
Equipment Utilization
Construction
1. Environment, Climate Conditions
Protection class of enclosures
Creepage, arcing distance
Corrosion Protection
Earthquake immunity
11
Busbar Concept
Multiple in-feed
Availability and abundance of Branch Configuration
3.
Power Supply
Standby facilities
Un-interruptable supplies
Fixed/draw out apparatus
Choice of equipment
Network layout
Scope of expansion
4. Power Balance Equipment Utilization
Instrument Transformer Design
Network Layout
Arcing Fault Immunity
Lightning Protectiion
6. Safety Requirements Earthing
Touch Protection
Step Protection
Fire Protection
12
Sub-station site selection
1. Outdoor Switchyard
Busbars
Incoming & outgoing lines
Transformers
Insulators
Substation Equipment such as Circuit breakers, Isolators, Earthing,
Switches, Surge Arresters, CTs, VTs/CVTs
Neutral Grounding Equipment
Station Earthing system comprising ground mat, risers, earthing strips,
earthing spikes.
Overhead earthwire shielding against lightning strokes, or, lightning masts.
Galvanised steel structures for towers, gantries, equipment supports.
13
PLCC Equipment including line trap, tuning unit, coupling capacitor, etc.
Power cables
Control cables for protection and control
Roads, Railway track, cable trenches
Station lighting system
2. 11/ 33 kV Switchgear
11 kV Indoor Switchgear
33 kV Outdoor Switchgear
3. LT Panels
4. Battery room
DC Battery system
Charging equipment distribution system.
5. Mechanical, Electrical
14
6. Protection system
CTs, CVTs
Protective Relays
Circuit breakers
7. SCADA
SUBSTATION PROTECTION
15
the earth surface in and around the substation which will have uniformly zero
potential with respect to ground and low earth resistance.
Earth Resistance:
Earth Resistance is the resistance offered by the earth electrode to the flow of
current in to the ground. To provide a sufficiently low resistance path to the earth
to minimize the rise in earth potential with respect to a remote earth fault.
Persons touching any of the non current carrying grounded parts shall not receive
a dangerous shock during an earth fault. Each structure, transformer tank, body
of equipment, etc, should be connected to earthing mat by their own earth
connection.
16
Step Potential and Touch Potential
Grounding system in a electrical system is designed to achieve low earth
resistance and also to achieve safe Step Potential and Touch Potential.
Step Potential:
Step potential is the potential difference between the feet of a person standing
on the floor of the substation, with 0.5 m spacing between the feet (one step),
through the flow of earth fault current through the grounding system.
Touch Potential:
17
Fig.1.1 Step Potential and Touch Potential
The main earth mat shall be laid horizontally at a regular spacing in both X & Y
direction(9m) based upon soil resistivity value and substation layout arrangement
.The main earth mat shall be laid at a depth of 600 mm from ground. The earth
mat shall be connected to the following in substation:
18
IV. Equipment framework and other non-current carrying parts.
V. Metallic frames not associated with equipments.
VI. Cable racks, cable trays and cable armour.
ii) All steel/RCC columns, metallic stairs etc. are connected to the nearby earthing
grid conductor by two earthing leads. Electrical continuity is ensured by bonding
different sections of rails and metallic stairs.
iii) Metallic pipes, conduits and cable tray sections for cable installation are
bonded to ensure electrical continuity and connected to earthing conductors at
regular interval. Apart from intermediate connections, beginning points are also
connected to earthing system.
iv) A separate earthing conductor should be provided for earthing the lighting
fixtures, receptacles, switches, junction boxes, lighting conduits etc.
v) A continuous ground conductor of 16 SWG GI wire is run all along each conduit
run and bonded at every 600 mm by not less than two turns of the same size of
wires. The Conductor is connected to each panel ground bus, all junction boxes,
receptacles, lighting fixtures etc.
vi) Railway tracks within switchyard are earthed at a spacing of 30 m and also at
both ends.
vii) 50 mm x 6 mm MS (or of specified size) flat runs on the top tier and all along
the cable trenches and the same is welded to each of the racks. Further this flat is
19
earthed at both ends at an interval of 30 mtrs. The M.S. flat is finally painted with
two coats or Red oxide primer and two coats of Post Office red enamel paint or of
specified material.
20
Fig. 1.3 Pipe Earth Electrode
Water should be poured in the earth pits at regular intervals to maintain the
required earth resistance.
21
LIGHTNING PROTECTION
The protection from the lightning is done with the help of shield wire and
lightning mast (high lattice structure with a spike on top).
1. Shield wire
Shield wire lightning protection system will be generally used in smaller sub
stations of lower voltage class, where number of bays is less, area of the
substation is small, & height of the main structures is of normal height. The major
disadvantage of shield wire type lightning protection is, that it causes short circuit
in the substation or may even damage the costly equipments in case of its failure
(snapping ).
This type of protection will be generally used in large, extra high voltage sub
stations where number of bays is more
It reduces the height of main structures, as peaks for shield wire are not
required.
It removes the possibility of any back flashover with the near by
equipments/structure, etc.during discharge of lightning strokes.
Provides facility for holding the lightning fixtures in the substation for
illumination purposes.
Aesthetic look.
22
Fig. 1.4 Zone Protection for single lightning mask
SELECTION OF LM HEIGHT
The factors to be considered are:
The height of the LM will be decided, depending upon the height of equipment
to be protected
The protection zone or coverage area of LM increases with the increase of its
height. Hence LMs height depends upon the height of equipment to be
protected.
23
The protection zone of same LM would be more if the equipment height to be
protected is less.
The installed LM in the substation covers an area of 44.96m dia circle. It has 2.5m
high spike.
3. Earth wire
Overhead power lines are often equipped with a ground conductor (shield wire or
overhead earth wire). A ground conductor is a conductor that is usually grounded
(earthed) at the top of the supporting structure to minimize the likelihood of
direct lightning strikes to the phase conductors. The ground wire is also a parallel
path with the earth for fault currents in earthed neutral circuits. Very high-voltage
transmission lines may have two ground conductors. These are either at the
outermost ends of the highest cross beam, at two V-shaped mast points, or at a
separate cross arm. By protecting the line from lightning, the design of apparatus
in substations is simplified due to lower stress on insulation. Shield wires on
transmission lines may include optical fibers (OPGW), used for communication
and control of the power system.
7/3.66 mm wire is used for providing earthing in lightning mast and towers.
24
Groundwire must meet the following requirements:
25
2. COMPONENTS OF SUBSTATION
1. LIGTHNING ARRESTER
It is the first equipment in a substation. Substation design involves more than one
installing apparatus, protective devices and equipment. The significant
momentary investment and required reliable continuous operation of the facility
requires detailed attention to preventing surges from entering the substation
facility. The effects of disturbances with limiting in a power system, which if
allowed to persist, may damage plant and interrupt the supply of electrical
energy. Lightning is one of the most serious causes of over voltage. If the power
equipment especially at outdoor substation is not protected, the over-voltage will
cause burning of insulation. Thus it results into complete shutdown of the power
and the loss may run into cores of kyat. Electrical equipment can be damaged due
to over-voltage such as switching surge over-voltage, Lightning surge over-
voltage, transient recovery voltage and power frequency temporary over-voltage
in transmission line and receiving end of substation. It is important to protect
power equipment against them wherever possible. Lightning Arrester can protect
the damages of electrical equipments. So, Lightning Arrester must be installed at
the terminal end of the transmission line, substation, high voltage transformers
and low voltage transformer. The analysis of electromagnetic transient is
depended on operating voltage, lengths of the lines and contactor configuration.
So, it can be chosen correctly the technical specifications of the apparatus of
Lightning Arrester base on the amounts of receiving overvoltage. Generally
arresters are connected in parallel with the equipment to be protected, typically
between phase and earth for three phase installations.
26
Lightning arresters are the most effective means of protecting an electrical
apparatus against traveling voltage waves caused by lightning and switching.
1. Station
2. Intermediate
3. Distribution, and
4. Secondary
27
Functions of a Lightning Arrester
To act like an open circuit during the normal operation of the system i.e., to
hold off the system voltage.
To limit the transient voltage to a safe level with the minimum delay and
fitter.
To bring the system back to its normal operation mode as soon as the
transient voltage is suppressed, i.e., to interrupt the power-follow current and
to reseal itself.
The normal operation or operational mode includes the system under faulted
condition. Under several types of system faults, such as the single line-to-ground
faults, the voltage to ground across the healthy phases will rise above the normal
voltage level. The arrester must not go into conduction during this fault condition.
It should also be able to interrupt the power-follow current and reseal itself under
system fault conditions when the power-frequency voltage across it rises.
The active elements (blocks) of surge arresters are manufactured using a highly
non-linear ceramic resistor material composed for the most part of ZnO mixed
with other metal oxide. The resistor blocks in the surge arrester offers low
resistance to high voltage surge to ground. Surge Arrester discharges current
impulse surge to earth and dissipates energy in the form of heat. After
discharging the impulse wave to earth, the resistor blocks in the surge arrester
offers a very high resistance to the normal power frequency voltage and acts as
open circuit.
28
Fig. 2.2. An Electric Transmission Network
There are 2 types of designs available for EHV Surge-Arrester. These are
Conventional gapped Surge-Arrester (Value Type) and Metal Oxide Surge-
Arrester.
29
2. CAPACITOR VOLTAGE TRANSFORMER
K1 is normally chosen to give E2 = 22/3 kV. Thus for different primary voltages,
only C1 differs and a standard intermediate transformer can be used for all
primary voltages. The intermediate voltage transformer (IVT) also contains
reactors for compensation of the capacitive voltage regulation.
30
CVT quality depends on formula:
31
CVTs as coupling capacitors
It is possible to combine the CVTs as coupling capacitors for line carrier
transmission and as a voltage transformer. The L terminal in the terminal box
gives access to the CVTs capacitor voltage divider. Power line carrier equipment
and accessories including drain coil and spark gap protection are available in the
terminal box. For external connection of the power line equipment the insulation
of wires must withstand 10 kV RMS test voltage. Its further described under PLCC.
32
3. WAVE TRAP
It is also called "LINE trap". It is connected in series with the power line. It blocks
the high frequency carrier waves (24 kHz to 500 kHz) and Wave trap is an
instrument using for trapping of the wave. The function of this wave trap is that it
traps the unwanted waves. Its shape is like a drum. It is connected to the main
incoming feeder so that it can trap the waves which may be dangerous to the
instruments in the substation. Generally it is used to exclude unwanted frequency
components, such as noise or other interference, of a wave. It traps the high
frequency communication signals sent on the line from the remote substation
and diverting them to the telecom/tele protection panel in the substation control
room through coupling capacitor.
33
company network. The signals are primarily tele protection signals and in
addition, voice and data communication signals. The Line trap offers high
impedance to the high frequency communication signals thus obstructs the flow
of these signals in to the substation bus bars. If these are not present in the
substation, then signal loss is more and communication will be
ineffective/probably impossible.
4. ISOLATOR
Isolators are the no load switches and used to isolate the equipment. (Either line
equipment, power transformer equipment or power transformer). With the
isolators, we are able to see the isolation of the equipment with our naked eye.
The line isolators are used to isolate the high voltage from flow through the line
into the bus. This isolator prevents the instruments to get damaged. It also allows
the only needed voltage and rest is earthed by itself. Isolator is a type of switching
device. It has non control devices. Isolator are operated after the circuit breaker is
opened. While closing the circuit, first close the isolator and after the circuit
breaker is closed. Strictly speaking Isolators are operated under no current
condition. In the following cases it is permissible to use isolator for making and
breaking of the circuits.
Air break isolators or disconnecting switches are not intended to break load
though these are meant for transfer of load from one bus to another and also to
isolate equipment for maintenance. These are available mainly in two types
vertical break type and horizontal break type. The later type requires larger width.
However the space requirement can be reduced in the horizontal break isolators
by having double break with a centre rotating pillar.
34
Fig. 2.6. 220 kV Isolators without Earth
35
5. Current Transformers
Components of CT:
36
Fig. 2.7. SF6 Gas Insulated Current Transformer
Loose connections should not be allowed in the electrical circuit. It increases the
contact resistance which in turn the rises the temperature in that area due to load
current. It damages the oil seals in CTs and transformers bushings causing oil leak
and in term entry of moisture in to the equipment causing falling of IR values and
damages O rings in circuit breaker causing SF6 gas leakage. Entry of moisture in
to the VCB insulator chamber cause vacuum interrupter failure and pull rod
failure due to electrical break down. Hence loose connections should not be
allowed.
37
6. CIRCUIT BREAKER
The circuit breakers are used to break the circuit if any fault occurs in any of the
instrument. These circuit breaker breaks for a fault which can damage other
instrument in the station. For any unwanted fault over the station we need to
break the line current. This is only done automatically by the circuit breaker.
These are load switches. It is able to make or break the normal load current as
well as the fault currents. The basic construction of any circuit breaker requires
the separation of contacts in an insulating fluid, which serves two functions. It
extinguishes the arc drawn between contacts when the CB opens and it provides
adequate insulation between the contacts and from each contact to earth.
The present trend is up to 33KV, VCBs are preferred and beyond 33KV, SF6 gas
circuit breakers are preferred.
38
VCB is to be meggered periodically to know the healthiness of the vacuum
interrupter and the insulating pull rod. Vacuum integrity test is the correct
test to know the healthiness of the vacuum interrupter.
SF6 gas pressure is to be noted in log sheets at least twice in a day. If it is
reaching to SF6 gas pressure low alarm stage, it is to be brought to the notice
of the maintenance personnel.SF6 gas circuit breaker goes to lockout
conditions after falling to lockout pressure close and trip circuits will be
blocked and circuit breaker operation cant be performed N<0 contacts of
63GLX were used in close and trip circuits of the CB and 63GLX contactor is in
picked up conditions when the gas pressure is sufficient. Some of the SF6 gas
circuit breaker automatically trips while going to lockout stage N<C contacts
of 63GLX contactor were used in close and trip circuits and 63GLX is in drop
off condition when the gas pressure is sufficient.
There are mainly two types of circuit breakers used for any substations. They are
(a) SF6 circuit breakers
(b) Vacuum circuit breakers.
39
force i.e. under high pressure. When if the gas gets decreases there is a motor
connected to the circuit breaker. The motor starts operating if the gas went lower
than 20.8 bar. There is a meter connected to the breaker so that it can be
manually seen if the gas goes low. The circuit breaker uses the SF6 gas to reduce
the torque produce in it due to any fault in the line. The circuit breaker has a
direct link with the instruments in the station, when any fault occur alarm bell
rings.
The bus is a line in which the incoming feeders come into and get into the
instruments for further step up or step down. The first bus is used for putting the
incoming feeders in a single line.
There may be double line in the bus so that if any fault occurs in the one the other
can still have the current and the supply will not stop. The two lines in the bus are
separated by a little distance by a conductor having a connector between them.
This is so that one can work at a time and the other works only if the first is having
any fault.
TRANSFORMERS:
A transformer is a static machine used for transforming power from one circuit to
another without changing frequency. This is a very basic definition of transformer.
Since there is no rotating or moving part so transformer is a static device.
Transformer operates on ac supply. Transformer works on the principle of mutual
induction. Transformers come in a range of sizes from a thumbnail-sized coupling
transformer hidden inside a stage microphone to huge units weighing hundreds
of tons used to interconnect portions of national power grids. All operate with the
same basic principles, although the range of designs is wide. While new
technologies have eliminated the need for transformers in some electronic
circuits, transformers are still found in nearly all electronic devices designed for
household ("mains") voltage. Transformers are essential for high voltage power
transmission, which makes long distance transmission economically practical.
42
Fig. 2.8. 315 MVA, 400/220 kV Power Transformer
Basic Principle:
Changing the current in the primary coil changes the magnetic flux that is
developed. The changing magnetic flux induces a voltage in the secondary coil.
43
3. AN OVERVIEW OF 400/220 kV Ballabgarh Substation
INTRODUCTION
BALLABGARH is a vital node for disbursement of power to Northern States of
India. It is located at a distance of 47 KM from DELHI, near Samaypur village of
BALLABGARH (Distt. FARIDABAD) of Haryana State. Normally it imports power
from generating stations of SINGRAULI/RIHAND, AURAIYA, DADRI reroute the
substations of KANPUR, AGRA, DADRI & MAINPURI respectively and the same is
exported to RAJASTHAN, HARYANA/DELHI via Gurgaon substation, Bamunali
substation & 220 kV BBMB SAMAYPUR. Further BALLABGARH being one of the
five nodes of 400 kV RING MAIN double circuit line around national capital of
DELHI, assumes the additional onus of responsibility for ensuring uninterrupted
power supply to the CAPITAL. Indias first indigenous FACTS has been test charged
at Ballabgarh on 400 kV S/C Ballabgarh-Kanpur line. However Fixed Series
Compensation (35%) on 400 kV BLB-KNP line executed by M/S BHEL is in service
since July2002. This Fixed Series Compensation was first project on any 400 kV
line in India.
Ballabgarh substation is nearly 29 years old. It spans over 135 acres of land, and
consists of huge outdoor switchyard equipment with transmission lines carrying
average power flow of 2000 MW at 400 kV voltages level.
44
Features Of Ballabgarh Substation
Commissioning Chronology
45
400 KV BLB-AGR S/C 26 December 1991
400 KV 315 MVA ICT IV 30 June 2002
400 KV BLB MAINPURI I 11 May 2005
400 KV BLB MAINPURI-II 08 May 2005
400 KV BLB-BAMNAULI-I 18 Aug 2004
400 KV BLB-BAMNAULI-II 21 Aug 2003
FACTS STAGE-I 01 July 2002
FACTS STAGE-II TEST CHARGE 29 November 2004
REMOTE OPERATION OF BWD S/S 01 December 2003
46
THE RELAYS SCHEMES PROVODEED FOR PROTECTION PURPOSES ARE AS UNDER:
1. DIFFERENTIAL PROTECTION
2. REF PROTECTION
3. BACK UP O/C AND EARTH FAULT PROTECTION
4. CORE PROTECTION
5. OTI/WTI
6. PRD
47
Single Line Diagram Of 400/220 kV Ballabgarh Substation
48
4. OPERATION OF 400 kV SUB-STATION
GENERAL
In general if everything is normal then the staff has to fill the operation
records as listed in enclosure.
All readings must be taken at proper time as per OS norms.
There should not be any over writing or cutting on Log Books.
Readings of switch yard equipments, A/C plant, DG set, F/F system, Auxiliary
system must be taken locally.
Normally there should not be any alarm on control panel windows in C/R, A /C
plant control panel, DG control panel and F/F system Control panel. In case any
alarm appears then try to reset the same and inform to maintenance In-charge.
About 90% of the faults on line are transient in nature because line passes
through forests, other areas also. In this case fault is not of permanent nature,
so an attempt is to be taken to reclose the line.
As soon as there is any fault in the line, Main-I and Main-II protections will
operate and particular pole of CBs (main & tie) will open at both ends. After
dead time (1 second), which starts since the operation of Main-I and Main-II,
A/R attempt is taken by A/R relay and if fault is cleared with-in dead time, CB
at both ends will close but If fault is persisting 3 phase tripping will takes
place. If fault is again repeated with in reclaim time after successful A/R of
49
line, which is 25 seconds for A/R relay, then also 3 phase tripping takes place.
After 25 seconds of auto - reclosing A/R relay become normal for next
operation.
50
OPERATIONAL STRATEGY IN CASE LINE TRIPS OR A/R UNSUCESSFUL:-
The reason for unsuccessful auto-reclosure at one end or at both ends will be
following:-
51
OPERATIONAL STRATEGY IN CASE LINE TRIPS:
The reasons other than earth fault for tripping of line are given below.
1) Over voltage protection operates [voltage goes > (440-460) KV for 5 Seconds
or 600 KV for instantaneous tripping).
In case of above there will not be any flag on Main-1 / Main-2 panel & fault
locator will not give any reading. Follow steps 1 to 5 as in the section Line auto
recloses successfully.
i) In case of over voltage take permission from CPCC if voltage has come
down. Consult other end and Charge/Synchronize the line.
In case over voltage stage-2 operates then inform S/S In-charge for further
restoration of the feeder.
ii) Bus reactor has hand reset type of trip relay, so when ever Bus
reactor trips, clearance is to be taken from S/S In-charge and then reset the
relay by pressing push button.
iii) In case direct trip signal receives, consult other end if they find out the
reason for tripping after that code may be taken for charging and
synchronization of line.
52
OPERATIONAL STRATEGY IN CASE BUS BAR PROTECTION AND LOCAL BREAKER
BACK UP (LBB) PROTECTION OR BREAKER FAILURE RELAY (BFR) OPERATES.
The operation of Bus Bar protection is very rare. It can operate in case some
earthing is left during the shut down or bus post insulator has failed.
Bus bar is having differential protection. It is divided into Zone-I covering B/B 1
and Zone -2 covering B/B- 2 and check zone covers both buses. Core-I of all CTs
which are used in Bus Bar protection is connected with Check zone and core-2
connected to zone-1 or zone-2 as per Bay connection to Bus-1 or Bus-2. CT cores
1&2 used for bus bar protection has 2000/1 ratio. For any tripping check zone &
zone-1 or zone-2 has to pick up. This is for giving more security in tripping. The
relay setting is 100V and relays are located in BB panel.
LBB (local breaker back up) or BFR will operate when main protection has
operated and tripping has been extended to trip relay and CB fails to trip due to
mechanical problem etc. It is delayed protection if the current to the LBB or BFR
persists for 200 ms then only relay will operate. Setting of ABB relay RAICA)
is 200mA and that of ALSTOM relay CTIG 1.2 amps for phase element & 0.4
amp for neutral element with 1000/1 A CT. The tripping relays for both these
protection are common and are located in bus bar Panel. In case of operation of
these protection either B/B-I or B/B-II connected all CBs will trip and B/B will
become dead.
STEPS TO BE TAKEN
53
In case of LBB or BFR note down the flags on respective panels.
Inform S/S In-charge and CPCC immediately.
Do not charge the Bus or line till clearance is given by S/S In-charge and CPCC.
After inspection and clearance is accorded by S/S In-charge and ask for code
from CPCC.
Reset the B/B trip relays by pressing the push button in B/B panel.
Without resetting the B/B trip relays, CBs cannot be closed because closing
command for CB goes through the contact of this relay.
If code is given by CPCC charge the B/B by closing CBs and record time and
other parameters
SHUTDOWN PROCEDURES
A. Avail permission code from CPCC for shut down of the line. Pass on the
same code to remote end.
(If the remote end opens the line from their end, Main CB & Tie CB will open
automatically)
E. Put the Auto Reclose switch (A/R) of the line in NON AUTO position.
54
F. Open the line Isolator *89L.
G. Open the Main Bay Isolator *89A & Tie Bay Isolator *89A & *89B.
L. Close the earth switch of the line Isolator *89LE and inform other end.
N. Attach DO NOT OPERATE board at the control panel of the line bay.
A. Avail permission code from CPCC for shut down of the ICT. Pass on the same
code to BBMB.
55
F. Open the 400 KV line Isolator *89L of the ICT.
G. Open the Main Bay Isolator *89A & Tie Bay Isolator *89A & *89B.
H. Open Bus side Isolator *89 & 220 KV side isolator L*89.
L. Close the earth switch of the ICT from 220 KV side Isolator L*89E.
M. Close the earth switch of the ICT from 400 KV side Isolator *89LE.
N. Attach DO NOT OPERATE board at the control panel of the 400 KV & 220
KV ICT bay.
A. Avail permission code from CPCC for shut down of the BUS 1/ BUS 2.
B. Open all the CBS connected to BUS-I/ BUS 2.
C. Put the Auto Reclose switches (A/R) of all the above CBs in NON AUTO
position.
D. Open all the Isolators of the bays connected to BUS 1/ BUS 2.
E. Check physically for proper opening of all Isolators done in D.
F. Ensure that the BUS-I/ BUS-2 voltage is around 10KV (due to induction).
56
G. Close Bus-I/ Bus-2 earth switch 1389E / 1589E Bus side respectively.
H. Ensure that the Bus selection switch of voltage / frequency is on Bus-II/ Bus-I
respectively.
I. Ensure that the bus selection latch relay is correctly operated and MW,
MVAR and Current of all feeders are matching.
J. Ensure that all the energy meters of feeders & ICTs are running
K. Issue the PTW (PERMIT TO WORK) on individual equipment.
A. Ensure all permits issued are returned and cancelled. (i.e. Line, Switchyard,
CP/RP Maintenance)
B. Check for removal of all men and material from S/Y physically.
C. Physically check for removal of earthing done at working site, both permanent
and temporary.
D. Ensure that all S/Y equipments of the line on which PTWS were cleared, are
in operating condition.
E. Check for SF6/ OIL pressure of Main & Tie CB.
F. Ensure local/remote switch of CBs are in Remote position.
G. Ensure that all relay flags are reset.
H. Check for no annunciation pending on window and do lamp test OK.
I. Ensure that D/R,E/L, F/L are in service.
57
J. During charging of the line from BALLABGARH end the A/R selection switch of
both Breaker must be kept in NON AUTO mode to avoid auto re-closure of
switch on to fault. After successful synchronizing same may be kept in 1 PH
mode.
58
M. After synchronising the line note down the readings and check the current in
all the three phases and inform to CPCC.
N. Check all the relay & control panels and note down the PLCC readings. If any
abnormalities observed then inform to S/S in-charge.
A. Ensure all permits issued are returned and cancelled. (i.e. ICT, Switchyard,
CP/RP Maintenance)
B. Check for removal of all men and material from S/Y physically.
C. Physically check for removal of earthing done at working site, both permanent
and temporary.
D. Ensure that all S/Y equipments of the ICT & Bay on which PTWS were cleared,
are in operating condition.
E. Check for SF6/ OIL pressure of Main & Tie CB.
F. Ensure local/remote switch of CBs are in Remote position.
G. Ensure that all relay flags are reset.
H. Check for no annunciation pending on window and do lamp test OK.
I. Ensure that Event Logger is in service.
ICT shall be charged preferably from 220 KV side and synchronized from 400
KV side in normal condition.
59
In case of Auto transformer has undergone major overhaul or oil has been
exposed to the atmosphere, values of BDV, PPM shall be taken before
charging the transformer.
SEQUENCE OF OPERATIONS
A. Confirm the removal of earthing at BBMB end, if any, and give clearance for
closing the 220 KV line isolators at their end.
B. Close 220 KV side Autotransformer isolator L*489.
C. Close all the 400 KV side isolators of Main & Tie Bay.
D. Check physically the closing of all isolators done B & C.
E. Inform the readiness to CPCC.
F. Take permission from CPCC for charging the ICT-I from 220 KV side.
G. Note down all parameters of ICTs and lines.
H. Check physically the healthiness of transformer.
I. Close 220 KV Breaker of ICT. As such the Auto- transformer is charged from
220 KV side.
J. In case the Auto transformer trips on fault, second attempt MUST NOT be
made until ICT is properly tested and reason for tripping is ascertained.
K. Close 400KV Main and Tie CBs of ICT as per requirement. In no case check
synchronizing relay should be bypassed.
L. After synchronizing the ICT note down the readings and check the current in
all the three phases and inform to CPCC.
M. Check all relay and control panels and equipments in the switch yard for any
abnormalities and inform S/S In-charge.
60
SEQUENCE OF OPERATION FOR CHARGING BUS-1/ BUS-2
A. Ensure all permits issued are returned and cancelled. (i.e. Bus-1/ Bus-2,
Switchyard, CP/RP Maintenance).
B. Check for removal of all men and material from S/Y physically.
C. Physically check for removal of earthing done at working site, both permanent
and temporary.
D. Ensure that all S/Y equipments on which PTWS were cleared, are in operating
condition.
E. Check for SF6/ OIL pressure of all the CBs.
F. Ensure local/remote switch of CBs are in Remote position.
G. Ensure that all relay flags are reset.
H. Ensure that Event Logger is in service.
SEQUENCE OF OPERATION:
61
5. MAINTENANCE OF 400 kV SUB-STATION
CIRCUIT BREAKER:
iii) Checking of hydraulic oil level & replenishment/ topping up of oil (if
necessary).
62
CURRENT TRANSFORMER:
PROTECTION SYSTEM:
CIRCUIT BREAKERS:
63
YEARLY MAINTENANCE OF EQUIPMENTS (S/D ACTIVITY):
vi) Checking of all remote indications (WTI & Tap position indicator)
CIRCUIT BREAKER:
i) Checking of Hydraulic oil pressure drop/ air pressure drop during duty cycle
operation check.
iii) Dew point measurement of operating air at the outlet of Air Dryer for ABCB
breaker.
64
vi) Functional checks, duty cycle operation including rapid re-closing (O-0.3s-CO).
CURRENT TRANSFORMER:
i) Visual checking of earthing HF point (in case it is not being used for PLCC).
65
ISOLATORS AND EARTH SWITCHES:
SURGE ARRESTOR:
i) Cleaning of LA insulator.
WAVE TRAP;
PROTECTION SYSTEMS:
67
xiii) Checking of fault locator initiation.
xix) Checking of PLCC system for return loss, transmitter/ receiver check,
power supply measurement and alarms.
CIRCUIT BREAKER:
68
CURRENT TRANSFORMER:
CIRCUIT BREAKER:
69
SOS ACTIVITIES FOR EQUIPMENTS:
CIRCUIT BREAKER:
CURRENT TRANSFORMER:
i) IR measurement.
70
CAPACITOR VOLTAGE TRANSFORMER:
i) Testing of EMU tank oil for BDV (if oil found discoloured).
MAINTENANCE OF FACTS:
FACTS installed on 400 KV BLB-KNP line is first project on any 400 KV lines in India.
For the maintenance of FACTS some precautions has to be taken as capacitor
bank and all other equipments are installed on a platform, charged at 400 KV.
1. Bypass the capacitor bank permanently (both earth switches will be closed
under this condition, both capacitor isolators are open, bypass isolator and
BPCB is closed).
2. Open the fence door observing all capacitor isolator interlock protocol.
71
3. Using an earth rod, manually earth all incoming tube connections from line
for all the phases. Also, earth all the platforms manually by earthing rod. Keep
the earth rod permanently connected on that platform on which work will be
undertaken.
4. Do not work on the platform when it is drizzling or raining or under conditions
of thunder and fog.
1. Visual Inspection
2. Check for any bulging of Pressure Relief Diaphragm
3. Check for cleanliness of insulator surface and clean if required
72
PREVENTIVE MAINTENANCE SCHEDULE FOR CAPACITOR BANK
YEARLY MANITENANCE:
73