Examination Question 510
Examination Question 510
1. Who is responsible for transferring the plate marking to the balance plate for a vessel repair
work
A. Authorized inspector who is overseeing the repair activities
B. Repair organization who does the repair work
C. The fabricator who is involved in the repair process
D. The pressure vessel Engineer who approved the repair work
2. A repair work on a pressure vessel is to be carried out. Who is responsible to have WPS/PQR
made for the repair work.
A. Owner user
B. Repair organization
C. Authorized inspector
D. Third party company who does the inspection work
3. A vessel in service has different zones of corrosion. The next inspection frequency will be
decided by
A. Zone with highest rate of corrosion
B. Zone with lowest remaining life
C. Average rate of corrosion shall be taken into consideration
D. Average remaining life of the vessel shall be considered
4. When the vessel is opened for inspection. Entry of the vessel is allowed only after the evaluation
of the condition in accordance to
A. OSHA
B. API
C. ASME/API
D. ANSI
5. PSV cold set pressure is 400psi. What is the acceptable tolerance in the set pressure
A. 402 psi
B. 412 psi
C. 420 psi
D. 418 psi
6. A pressure vessel of 60 has three pits within a circle of 7 diameter. The nominal thickness of
the shell is 0.75 and the CA is 0.125. The details & dimensions of the pits are listed below. Your
assessment is
0.475 X 0.385 depth 0.21
1 dia depth 0.35
0.375 X 0.385 depth 0.23
A. The area of pit is more than the acceptable
B. The pits are more than the acceptable length
C. The pit depth is more than the acceptable
D. The pits are acceptable as they are meeting the requirement
7. The vessel has serviced for 10 years and the original thickness was 1.25. The observed thickness
after 8 years is 0.92 and the thickness at the end of 10th year is 0.886. The minimum required
thickness is 0.8. What corrosion rate will be taken for calculation
A. 0.017
B. 0.033
C. 0.33
D. 0.17
8. A pressure vessel of 80 has its part MAWP at various parts are detailed in the sketch. What is
the vessel MAWP Ref: Sketch The static head is 0.433 psi per foot of water
A. 419 psi
B. 420 psi
C. 430 psi
D. None of the above
9. A pressure vessel fabricated in 1960 was in service. It has been decided to remove the top head
and extend the height to 2mtrs and replace the dish head with a new one. The proposal is
A. The proposal can be accepted for review
B. No modification is allowed on this vessel
C. A pressure vessel engineer should be consulted for approval
D. None of the above
10. While calculating the MAWP of a vessel in service which one of the basic thing to be taken into
consideration
A. The original design code should be taken in to consideration
B. Relevant ASME Sec. Should be taken into consideration
C. It should be done as per the latest edition of ASME Sec. VIII Division-1
D. As per API 510
11. The following are the thickness readings taken on a 20 dia on a 60 dia vessel. The original
thickness of the vessel is 1.125 and its corrosion allowance is 0.125. For MAWP calculations
what potential average thickness would be considered
Location 1- 0.885
Location 2- 0.745
Location 3- 0.725
Location 4- 0.750
Location 5- 0.690
A. 0.759
B. 0.885
C. 0.690
D. 0.725
12. An insulated pressure vessel operating above 450F the external visual inspection should
basically concentrate on
A. The lowest point where condensation accumulate on the vessel
B. All nozzle, skirt & attachments
C. Like any normal external inspection it should be done
D. If the vessel has intermittent service check for CUI
13. On an Ultrasonic survey of a vessel has how many minimum points should be covered
A. Representative gauge point readings with respect to corrosion
B. Minimum two points on dished, shell nozzle
C. Minimum one points on dished, shell nozzle
D. Authorized inspector will decide the number of points
14. SS Clad repair has been carried out on a vessel which NDT method will best used to check the
repair weld.
A. Magnetic particle testing
B. Dye penetrant testing
C. Eddy current testing
D. Ultrasonic testing
15. A claded vessel repair work is carried out up to parent metal. What heat treatment shall be
done on the vessel before clad repair is attempted
A. Post weld heat treatment of entire vessel
B. Local post weld heat treatment
C. Base metal out gassing shall be done
D. No heat treatment shall be attended
16. For external inspection on a insulated vessel with no history of corrosion has to be done on the
A. Remove 10% of insulation to check the condition
B. Remove insulation on all suspected areas
C. Remove the entire insulation
D. Carry out normal inspection as there is no need to suspect any area
17. As per API 510 the organization who carryout PSV repair, testing has to be
A. Registered with repair organization for similar activities
B. Have proper quality control procedure
C. Needs to have qualified and certified personnel to carry out the job
D. Needs to be a qualified and certified company to perform all repair work in accordance
to ASME
18. Which one of the dished end will have higher thickness and write the order to lowest thickness
A. Flat ,Hemispherical, 2:1 ellipsoidal, Torispherical
B. Flat, Torispherical, 2:1 ellipsoidal, Hemispherical
C. Torispherical, 2:1 Ellipsoidal, Hemispherical, Flat
D. 2:1 Ellipsoidal, Torispherical, Hemispherical, Flat
19. As per WPS the material used is SA516 Gr.70 and the electrode used is E-7018. What is the A#
and F#
A. 1, 4
B. 4,1
C. 2,4
D. 4,2
20. Which type of welding does not require a WPS
A. SMAW
B. GMAW with globular transformation
C. GMAW with flux core electrode
D. GMAW
21. In a pressure vessel the 2:1 ellipsoidal Dished head is removed and a new Dished head is
installed with a single V joint with packing strip. RT-1 was carried out considering the same was
carried out originally. What is the joint type and efficiency of the joint now
A. Category-B, Type-2 & E-0.9
B. Category-A, Type-2 & E-0.9
C. Category-A, Type-2 & E-1.0
D. Category-B, Type-2 & E-1.0
22. Ovality tolerance of a vessel is
A. 1% of shell OD
B. 2% of shell OD
C. 1% of radius
D. 2% of radius
23. Reinforcement pad required for a opening of dia of 8 nozzle with shell nominal wall thickness
1.125, minimum required wall thickness is 1.0 & the nozzle thickness of 0.75 with no
corrosion allowance
A. 9.0 sq. inches.
B. 8.0 sq. inches.
C. 1 inch thickness
D. 20 sq. inch
24. The notch test is better described as
A. Plastic formation and fracture
B. Brittle failure
C. Energy observed at the notch
D. toughness
25. The material normally not required PWHT has been heat-treated. The PWHT carried out on this
material is
A. Due to process requirement
B. Because of the material
C. As per authorized inspector requirement
D. Owner user asked for it
26. A vessel has been constructed by using SA516 Gr.70 normalised material of thickness 1.125.
The vessel can be designed up to what would be the minimum MDMT with out any impact
testing requirement
A. -25F
B. -30F
C. -20F
D. -15F