Project Execution Plan
Project Execution Plan
ALONE
for
April 2015
Client: Alone
1
Project Execution Plan Jamestown Court
2
Project Execution Plan Jamestown Court
CONTENTS
1. Project Definition 4
3. Programme Management 6
5. Communication Plan 8
3
Project Execution Plan Jamestown Court
1. Project Definition
The development will be designed to comply with the requirements of the Building Control
(Amendment) Regulations 2014. The Architect will be appointed as the Assigned Certifier.
Due account to be taken by all design team members of the Code of Practice for Inspecting
and Certifying Buildings and Works.
The development has already been submitted for planning permission, Planning Application
Reference: 2402/15.
4
Project Execution Plan Jamestown Court
5
Project Execution Plan Jamestown Court
The Project Responsibility Matrix, outlining the key tasks associated with project deliverables
and the key parties associated with each task is given in the table below:
3. Programme Management
It is planned that the building works are to be out to tender in mid- September 2015, on site
by mid-November 2015 and complete by mid-July 2016. A detailed project programme is set
out in section 4 of the PEP.
A detailed programme capturing the requirements of the baseline Schedule above will be
developed by the appointed consultants to ensure delivery at the various stages.
6
Project Execution Plan Jamestown Court
Cost management procedures for the recording and reporting of cost management are
outlined below:-
The budget and cost plan is to be developed in elemental format in line with CWMF
guidance notes and developed in detail through design development and tender.
Analysis shall be provided at each stage as Section 5 below.
Cost reporting shall be carried out through the construction stage in accordance with
the CWMF guidance notes.
In terms of cost change and contingency management, detail cost change controls, approval
mechanism and contingency management are to be carried out in accordance with the
CWMF guidance notes.
Risk Management Plan, Value Management Plan & Whole Life Costing:-
Value Management shall be carried out through all stages in accordance with the
CWMF guidance notes.
The required procedures under the CWMF vary in accordance with the value and
complexity of the project. This project is judged as Category 1 (low value, low
complexity) with the commensurate level of procedure and service required as defined
in Section 1.4 of Guidance Note 2.2 of the CWMF.
Value Management Level 1: In addition to the cost/m2, cost/km, unit cost, etc.,
benchmarks as a basis for estimation the benchmark should also be used as a tool for
reviewing value for money compared to other updated similar projects.
Whole Life Cost Analysis Level 1: As a matter of best practice, ensure that affordable,
sustainable design solutions are included.
7
Project Execution Plan Jamestown Court
5. Communication Plan
The project reporting requirements are summarised in the table below and will be updated
as the project progresses:
As the project has already been submitted for planning permission and planning approval is
anticipated, the design team are not required to go through Stage 1, 2a and 2b as detailed
below. However, the team are required to revisit and review the activities required through
each of these stages so as to verify continued feasibility of the scheme as specified. This is to
be formalised with the submission of a detailed review and report on the proposed scheme
which is scheduled for delivery four weeks after appointment. This report should address the
issues as outlined below in respect of Stage 1, 2a and 2b.
Stage 2b Developed Scheme Design for Stat. Approvals and Cost Plan
Develop developed Sketch Scheme and prepare submissions for Statutory Approvals.
Develop & Review Costing as per previous stage. Risk and value management to include
assessing buildability of designs; suitability assessment of contractors; and general review of
risks, allocation and mitigation strategy.
8
Project Execution Plan Jamestown Court
Stage 4 Construction
Design Activity (Architecture/ Structural & civil / Services)
Manage Contract
Manage Change control
Prepare interim progress reports every two months
Commission, certify and handover
9
Project Execution Plan Jamestown Court
Meeting Schedule
The following table outlines the general schedule for project meetings,
Meeting Chair Purpose Intervals Output
Client Meeting Arch. Set high level Fortnightly at Agenda and
direction. design minutes, 3
Forum for development days prior and
solving major and Monthly post meeting
issues thereafter respectively
Public Alone/ Liaise with Assume two Scheme
Consultation PC Community and (PC and layouts and
Meetings stakeholders Architect only) reports
Design Team Arch. Manage project Fortnightly Alone/ Project
implementation Co-ordinator
monitor,
control and
coordinate
project team
Construction Arch. Coordinate Fortnightly Agenda and
Site Meeting construction. minutes, 1 day
Resolve any prior and post
construction meeting
issues respectively
Post-project Arch. Review end Project Agenda and
Review project report closure minutes, 1 day
prior and post
meeting
respectively
10