100% found this document useful (1 vote)
169 views

ASL & Lead Time

ASL & Lead Time
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
169 views

ASL & Lead Time

ASL & Lead Time
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ORACLE FACTS

ORACLE VALUE CHAIN PLANNING

Processing Lead time in ASL



OVERVIEW
How is Supplier Lead time modeled in the ASL ?

Processing lead time in ASL only replaces Processing lead time in Item attributes.
The plan would still consider the Pre and Post lead times from item attributes and add it
to the processing lead time from the ASL.

So in case processing lead time is defined in ASL.

Total Lead time = Preprocessing Lead time (Item attributes)

+ Processing lead time (ASL)

+ Post Processing lead time (Item attributes)

ASL lead time gets precedence over Item attribute lead time.