Solved Exercises ch08
Solved Exercises ch08
Problem 4:
a) The critical path is B E G.
b) 23 work periods.
Problem 7:
Figure 7a is ADM format.
Start D H End
B E
Chapter 8 Project Activity Scheduling
Problem 8:
Please see note about network depiction.
a) The critical path activities are A, C, E, and G.
b) The projects duration is 22 days.
c) Yes, activity B can be delayed one day without delaying the completion of
the project.
Problem 9:
Task a m b Expected Variance Std Dev.
A 6.5 7.5 14.5 8.5 1.78 1.33
B 8.5 10.5 12.5 10.5 0.44 0.67
C 2.5 3.5 4.5 3.5 0.11 0.33
D 6.5 7.5 8.5 7.5 0.11 0.33
E 5.5 5.5 9.5 6.2 0.44 0.67
F 5.5 7.5 9.5 7.5 0.44 0.67
G 4.5 6.5 8.5 6.5 0.44 0.67
H 2.5 3.5 3.5 3.3 0.03 0.17
Chapter 8 Project Activity Scheduling
Sum of
Expected Variances
Desired Project Critical
Duration Duration Path Z Probability
21 24.7 2.78 -2.2 a) 1.4%
22 24.7 2.78 -1.6 b) 5.5%
25 24.7 2.78 0.2 c) 57.9%
Problem 10:
Sum of
Expected Variances
Desired Project Critical
Duration Duration Path Z Probability
14 16.0 4.00 -1 15.9%
e) If CD slips to six days the critical path is unchanged but slack on D is reduced. If
CD slips to seven days then there are two critical paths: A - C - B - E - F and A - C
- D - F. If CD slips to eight days then the critical path shifts to A - C - D - F and
the project duration extends to 17 days.
Problem 11:
10 28 36
B G 8 I
17 28 41
1
3 10
9
4 2
0 7 18 37 43
A 3 C 2 F 11 H 6 J
0 7 18 37 43
1
4 5
6 3
3
3 13
D 8 E
3 13
Figure 8.11 shows duration on the arrow in matching the (i,j) notation used to
define the problems source data.