0% found this document useful (0 votes)
1K views2 pages

Do - 066 - s2017 As Built Plan As Variation Order

The document outlines conditions for when an "As-Built" plan can be used as the basis for a final variation order from the Department of Public Works and Highways in the Philippines. It states that works completed without an approved variation order cannot simply use the "As-Built" plan as justification. It provides exceptions for emergency or time-sensitive works when the variation does not exceed 5% of the original contract price, and that the variation order must still be submitted for approval. All implementing offices are directed to only accept "As-Built" plans as the reason for final variation orders under the stated conditions.

Uploaded by

rubydelacruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views2 pages

Do - 066 - s2017 As Built Plan As Variation Order

The document outlines conditions for when an "As-Built" plan can be used as the basis for a final variation order from the Department of Public Works and Highways in the Philippines. It states that works completed without an approved variation order cannot simply use the "As-Built" plan as justification. It provides exceptions for emergency or time-sensitive works when the variation does not exceed 5% of the original contract price, and that the variation order must still be submitted for approval. All implementing offices are directed to only accept "As-Built" plans as the reason for final variation orders under the stated conditions.

Uploaded by

rubydelacruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

t)91;, /J~P.

J#
Republic of the Philippines !fir ~r~~~/7

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


OFFICE OF THE SECRETARY
Manila
1 5 MAy 2011

DEPARTMENTORDER ) SUBJECT: Conditions as to When "As-Built" Plan


) can be Used as Reason for Final

NO. 66_
)
)
Variation Order

Series of 20~J,.f7

It has been observed that there are Implementing Offices in the Department that are
processing Final Variation Orders only after the "As-Built" Plan is approved by the concerned
DPWH Officials since the said approved "As-Built" Plan is one of the requirements in the
processing of Final Variation Order as per D.O. No. 156, Series of 2015. As a consequence,
all works under the Final Variation Order are those that were already accomplished and
actually incorporated for the completion of the project even without an approved variation
order. Implementing Offices simply use the approved "As-Built" Plan as the reason for the
approval of Final Variation Order.

Pursuant to Section 3 Annex "E" of the Revised IRR of RA 9184, all works under a variation
order of a project should be undertaken only in accordance with the following:

3. CONDITIONS UNDER WHICH CONTRACTORS IS TO START WORK


UNDER VARIATION ORDERS AND RECEIVE PAYMENTS

3.1. Under no circumstances shall a contractor proceed to commence work


under any Change Order or Extra Work Order unless it has been
approved by the Head of the Procuring Entity or his duly authorized
representative.

3.2. However, under any of the following conditions, the procuring entity's
representative/Project Engineer may, subject to the availability of
funds and within the limits of his delegated authority, allow the
immediate start of work under any Change Order or Extra Work
Order:

i) In the event of an emergency where the prosecution of the work


is urgent to avoid detriment to public service, or damage to life
and/or property; and/or

ii) When time is of the essence;

Provided, however, That such approval is valid on work done up to


the point where the cumulative increase in value of work on the
project which has not yet been duly fully approved does not exceed
five percent (5%) of the adjusted original contract price;
D.O. No. 66 s.2017
Conditions as to When "As Built" Plan can be Used as Reason for Final Variation Order
Page 2 of 2

Provided, further, That immediately after the start of work, the


corresponding Change Order or Extra Work Order shall be prepared
and submitted for approval in accordancewith the above rules herein
set. Payments for works satisfactorily accomplished on any Change
Order or Extra Work Order may be made only after approval of the
same by the Head of the Procuring Entity or his duly authorized
representative.

Provided, finally, That for a Change Order or Extra Work Order


involving a cumulative amount exceeding five percent (5%) of the
original contract price, no work thereon may be commenced unless
said Change Order or Extra Work Order has been approved by the
Head of the Procuring Entity or his duly authorized representative.

In view of the foregoing, all Implementing Offices are hereby directed to observe the
conditions as to when the "As-Built" Plan can be made as reason for items of work to be
covered by a proposed Final Variation Order, as shown in the table below.

Not Acceptable
Conditions for
Acceptable (Requires Prior Approval
Undertaking Works
of Variation Order)
1. In the event of emergency
when prosecution of work
is urgent
Works which are Urgent,
The cumulative amount
completed without prior
2. Time is of the essence exceeding 5% of the
approval of Variation Order
adjusted original contract
and incorporated in the "As-
The cumulative increase in price
Built" Plan
value of work does not
exceed 5% of the adjusted
original contract price

This order shall take effect immediately.

6.1 TCA/AMD/WRO

Department of Public Works and Highways


Office of the Secretary

1111111111111111111111111111111111111
WIN7W02004

You might also like