Steam Blowing
Steam Blowing
Commissioning Methods
CONTENT
SL Topic Page No
INTRODUCTION
This is a well established method that has been used extensively for cleaning of all types of steam raising
plant, including large diameter steam lines. The basis of the method is to use steam at the lowest
possible pressure consistent with achieving the required steam flows. This steam has a high specific
volume and therefore the steam velocities are high during steam blowing, making it relatively easy to
achieve the required CFR (Cleaning Force Ratio) with steam mass flows that are much less than the
normal flow rates. Typically, for a high pressure system, the steam flow needed to achieve the CFR is
about 40% of normal flow. This procedure differs from conventional, pressure cycle, steam blowing in that
the steam used for blowing is produced continuously and the exit steam velocity is controlled to below
sonic velocity at the exit of the steam piping which greatly reduces the noise produced during steam
blowing.
Rather than exhausting to atmosphere directly, the exhaust steam exits into temporary pipe work fitted
with a series of quench attemperators. Each attemperator comprises a stepwise expansion in line size
with a facility to spray water into the flowing steam. Quench water is injected into the steam at each
attemperator. After the final attemperator the steam exits to atmosphere via a Muzzler.
The effect of the expansion and attemperation is to reduce the velocity and energy of the steam in the
temporary pipe work thereby minimizing the noise on discharge. For each of the steam systems being
cleaned, the temporary exit piping before the first attemperator is flanged to accept a remotely operated
target plate inserter. This allows target plates to be safely inserted and removed whilst blowing is in
progress. In this way, a series of target plates can be run to monitor the progress of the steam blow.
The steam blowing is designed to produce a disturbance factor (cleaning force ratio) of 1.0, or higher, at
the inlets of the lines being blown.
The main advantage of continuous steam blowing is the very short programme time needed to achieve
acceptable target plates. Typically each system being steam blown will take 12 to 30 blowing hours for
acceptance targets depending on target criteria. The other advantage is that the low pressures used
mean that the exit piping is fabricated from thin wall steel pipe and no special pipe supports are needed.
This greatly reduces the cost for the exit piping.
PROCESS
The silent steam blowing procedure consists basically of four major steps:
Warming up the line
Blowing the line
Thermal cycling the line
Re blowing the line
Target insertion & certification
WARMING UP THE LINE:
The line to be blown is first warmed up by crack opening the valve. The primary purpose of this is to
warm up the line and drain the condensate if any in the header. The secondary purpose is the detection
of leaks in the silent steam blowing assembly. If there are any leaks in the temporary piping, they can
be detected during this phase and can be rectified accordingly so that a safe silent blowing operation is
ensured.
things, there are other major detrimental things present in the steam line such as weld slag, mill scales
etc. During this first blow, these things expand due to the high temperature of the steam.
THERMAL CYCLING
Thermal cycling of steam lines is used to assist with removal of strongly adherent debris such as mill
scale. This reduces the blowing time required to achieve acceptable target plates. During a thermal
cycle the temperature of the line being steam blown is reduced to the minimum safe value then allowed
to rise back to the normal steam temperature. Thermal cycling is achieved by varying the temperature
of the steam flowing in the line. Temperature variation causes the metal line to contract during cooling
then expand as the temperature rises. Provided that the oxide scales on the pipe surface have a
different coefficient of thermal expansion compared to the underlying metal, this movement of the pipe
surface relative to the scale will cause the scale to detach from the metal surface. The loosened scale
is then readily removed during the steam blow.
Thermal cycling can be achieved either by natural cool-down or by forced steam cooling during steam
blowing. If the steam blowing is restricted to blowing for a set period each day, e.g. blowing during
daylight hours only, and is continued over at least 3 days, then normally sufficient thermal cycling will
be achieved by natural cooling. Where steam blowing is on a 24 hour per day basis, forced steam
cooling is used for inducing thermal cycles. In this method a thermal cycle is effected by injecting
suitable quality water, normally boiler feed water, into the steam flow at or before the inlet to the section
of line being steam blown. For thermal cycles,
The steam temperature is varied by about 200 C. During a thermal cycle, the steam temperature
should not be reduced to less than 30 C above the saturation temperature for the steam to avoid the
possibility of condensate slugs forming.
If permanent attemperation equipment is not available, temporary facilities can be provided. Normally
this will require injecting dematerialized water at a controlled rate into the steam line either upstream of
the inlet or as close as possible after the inlet. The water can be injected via a spray nozzle if a suitable
flanged connection exists or more commonly, directly into a steam line mud boot (drip leg) drain. The
water supply needs to be at a higher pressure than the line pressure during blowing, typically about 5
bar above the line pressure.
Where,
CFR = Cleaning Force Ratio
Mb = Mass Flow rate required for blowing
CHECKED BY: PAGE : 5 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
In the above equation, the values of Mo, Vo, Vs & CFR are known. From these values the value of Mb
can be determined using the above equation. The values of Mo and Vo can be obtained with the help
of LDT [Line Designation Table]. A sample calculation is given below.
In order to calculate the mass flow of steam required for steam blowing to achieve a specified value of
CFR it is necessary to estimate the steam pressure during steam blowing. During continuous steam
blowing the steam pressure at the inlet to the line is determined only by the pressure drop due to the
flow of steam during blowing. This is because the exit piping is open to atmosphere at its termination
and the steam velocities during blowing are always sub-sonic, hence choked flow does not occur.
Various methods are used to estimate pressure drops for flow of superheated steam. For complex
systems normally software used are Flow master, a commercial one dimensional CFD software
package or Crane Software.
Sample calculation for blowing steam requirement
Taking CFR= 1.8, Mo and Vo values from the LDT & Vs value from the steam table at 6
Hence
Mb = 55 tph
The same procedure was followed to establish the flow rates of all the lines.
Raw Water Supplies
Raw water supplies are required for operation of the quench attemperation system, used to reduce the
CHECKED BY: PAGE : 6 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
discharge noise of the steam during steam blowing. Fire water shall be used for the purpose.
Discharge Noise
The quench attemperation system is very effective at reducing the steam discharge noise. Discharge
noise levels are typically around 85 dBA at one metre from the discharge point .
Target Insertion Equipment
The target insertion equipment comprises a pneumatically operated isolation valve, a pneumatically
operated insertion ram and a control panel.
Engineering Design
In order to perform the detailed engineering design, the following information is required.
Accurate piping & instrumentation diagrams (P&ID) for all lines to be cleaned. These
will be used to produce flow diagrams for steam blows.
Accurate isometric construction drawings (ISO) and/or piping plans drawings for all
lines to be cleaned including boiler details. These drawings will be used during the detailed design
calculations.
Stress and movement design information on the lines to be blown to carry out a
stress analysis on the temporary piping.
Accurate information on the type, dimensions and Cv values for all valves in the lines
to be cleaned.
Maximum pressure and temperature limitations for all lines to be blown.
Maximum continuous rating (MCR) values for steam mass flows, pressures and
temperatures for all lines to be blown.
Execution Plan
This would include the following:
Detailed Engineering Design for steam blowing
Detailed Method Statement for steam blowing
Site Risk assessment.
Preliminary Checks.
Line Warming Procedure.
Targeted Steam Blow Procedure.
Preliminary Checks
Verification
Action
Step Action
by Initial Date & time
1.3 Safe access to all drip legs & isolation valves available.
Verification
Action
Step Action Initial Date &
by
time
Note On commencing steam blowing it is important to control the steam flow and temperature
of the exit line, to prevent water hammer and excessive line stresses.
The requirement is to slowly heat the steam line using a controlled flow of steam,
gradually increasing the flow rate if necessary. It is essential to drain water condensed
during the heating process.
This controlled operation also provides time to check the exit line for leaks or other
problems due to thermal expansion.
All drip leg drains between steam source and the main
2.1
steam stop valves to be opened.
2.2 Open Bypass valve on steam header isolation valve
If no bypass is present then crack open the main stop
2.3
to warm up steam lines.
Walk line closing all drip leg drains and checking all
flanges for leaks and for any problems due to thermal
expansion. Rectify as required.
2.4
When the exit pipe temperature, as shown on
Temperature Gauge, has reached 100C, line warming
is complete.
Action Verification
Step Action
by Initial Date & time
Note The following procedure is generic for all Target Steam
Blows. For individual blow processes see Step by Step
Procedure.
3.1 Establish flow required as mentioned in blow work sheet
provided in engineering package.
3.2 Continue blowing for 2 hrs.
3.3 Reduce flow to half of the total blowing flow.
3.4 Perform thermal cycling (TC) by spraying DM water or
cold condensate at nearest point of source. Allow
temperature to drop by 150 deg C.
3.5 Continue TC for around 1.5 hrs.
3.6 Stop TC and establish normal blowing flow.
3.7 Continue blowing for 1 hr.
3.8 Starting from the drains nearest to the steam source,
sequentially blow down all steam line drains. Fully open
CHECKED BY: PAGE : 9 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
each drain valve and allow the drain to blow until clean,
then close drain valve.
3.9 Insert a reference target. Keep target exposure for 20
minutes.
3.10 Remove the target safely by operating the Ram.
3.11 Note the following in the target plate log:
(a) Line number
(b) Plate number
(c) Time of insertion
3.12 Examine for impression when plate is cool.
3.13 Store the plate for future reference.
3.14 Repeat step from 3.1 to 3.13 till target meets the criteria.
Apart from silent steam blowing there are various other Non conventional cleaning methods
CHECKED BY: PAGE : 10 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
as listed below.
Chemical Cleaning.
Hydro Milling
Hybrid Chem steam cleaning
Chemical Cleaning:-
Chemical cleaning uses the most cost effective and environmentally sound means to reach
the desired objective whether it is simply degreasing or removal of mill scale. The chemical
mixture is formulated to remove hard deposits or soft films from virtually any type of
metallurgy. Chemicals used are environmental friendly. The process injects proven
chemistries into saturated steam. By not filling with liquids the chemistry is able to act directly
on the surface of the pipe. Continuous monitoring of the condensate product controls pH and
iron content. The vapour is condensed at the outlet point and neutralized for disposal to plant
waste system. After mill scale removal a final blow for 4 hours is given at calculated flow to
remove the construction debris. Total time required is around 18 hrs in place of 36 hrs for
conventional silent steam blow. The process reduces considerable steam consumption.
working pressure of 12,000 psi for mill scale removal and an average water flow of 40 GPM.
All resulting debris and mill scale may be contained and/or collected for proper disposal. This
proprietary pipe cleaning system is capable of handling changes of direction including multiple
90 degree turns and pipe offsets to distances of 100 mtrs vertically or 30 mtrs horizontally from
the point of entry with precise tracking capabilities. The hydro milling process is capable to all
pipe sizes from 2 dia meter and up. This process is best suited for De aerator lines, PRDS
lines.
Hydro Milling
Vapor Phase Chemical Cleaning
Steam blow
With the advent of much larger piping systems the previous methods of chemical cleaning, line
flushing, and steam blowing have become cumbersome, expensive, time consuming, and in
some cases impossible to perform utilizing the previous methods. In addition traditional
methods often create large quantities of waste effluent creating disposal problems.
The above stated cleaning methods are combined with the following objectives:
Hybrid Chem Steam blow time is 10-20% of normal silent steam blow duration and 2-5% of
conventional steam blow duration.
INTRODUCTION
The object of chemical cleaning of carbon steel piping is to remove the loose rust, dislodging the burs,
welding slag & mill scales adhering to the internal surface of the pipelines. The procedure specifies the
method of cleaning & passivation with sodium nitrite prior to taking in service for the first time after
installation of pipeline.
This cleaning enables to remove
a) Grease or oil
b) Mill scales
c) Loose rust
d) Welding slag
e) Paint or varnish if used for protective purposes
f) Any loose foreign particle during flushing of system
The sequence of operations includes flushing by cold & hot water, degreasing, acid pickling, citric rinse,
passivation, drying & preservation. In between this processes different parameters like pH, Alkalinity,
temperature, acid concentration, total iron & clarity of water to be monitored. Various chemicals used in
chemical cleaning process includes Soda ash, Caustic soda, Sodium nitrite, Wetting agent, CORONIL
92B, citric acid & ammonia.
CONTENTS
1 Temporary Arrangements
2 Leak Test
5 Degreasing
6 Water flushing
7 Acid Pickling
8 Water flushing
11 Testing Procedure
For starting & smooth operation of chemical cleaning following arrangements has to made before
CHECKED BY: PAGE : 14 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
starting of job
(a) Scaffolding for all the valves operations. (For vents, Hot tap connections & water supply valves
etc.)
(b) Motor connection to be made either from DG set or through Reliance system depending upon the
conditions. For this permit, isolation tag etc to be provided in consultation with electrical personnel.
(c) Return Hose connection from all valves to pump suction.
(d) Hose connection for DM Water, utility water, LP condensate etc from header valve to chemical
circulation tank.
(e) Chemicals storage at predefined place.
(f) Tie in between chemical circulation tank & effluent tank.
(g) Hose connection from effluent tank to tanker, to discharge effluent after conditioning in Effluent
tank.
(h) Tanker arrangement to dispose effluent at proper place.
(i) All control valves, flow meters & other instruments removal.
(j) Spool fixing in place of Control valve & NRV if required.
(k) Suction strainer removal.
(l) Danger Tags & Barrication in whole area.
2. Leak Test
This is to be done to avoid any leakage in between the process & to avoid any hazard because of
that.
a) After circuit completion, the system will be filled with utility water.
b) Water circulation for 30 min. to check the leakages in system & leakages to be rectified if found
any.
c) Water drain in storm water channel.
To remove loose slag, dirt, foreign particles etc from the system
a) Continuous system flushing with utility water for approx 1 hour.
b) Water filling & circulation in system and drainage in storm water channel till drain water will be
clear.
To remove loose slag, dirt, foreign particles etc from the system while giving a thermal shock
System flushing with hot water.
a) Water filling, circulation in system and raise the temperature up to min. 50 c
c) Drainage in storm water channel till drain water will be clear.
CHECKED BY: PAGE : 15 OF 19
JLB RELIANCE, JAMNAGAR REV : 00
CAPTIVE POWER PLANT ISSUE : 01
APPROVED BY: DATE : 15.02.2007
NKM AUTHOR : JKP
CPP Steam & BFW System Position : SFE (SG & D)
Commissioning Methods
Parameter to be monitored
pH & Total Alkalinity
End of degreasing-
pH and Total alkalinity of system at inlet and outlet of cleaning loop is equal and stabilized.
6. Water Flushing
7. Acid Pickling
a) Refill the system with condensate or DM water, circulate & raise temperature to 70 c
b) Add 0.2% of corrosion inhibitor Coronil 92 B & circulate for one hour.
c) After 1 hour add 3% of Citric Acid into the solution.
d) Maintain pH of solution between 3.5 to 4 using Ammonia.
e) Monitor concentration of acid, pH & total iron in every hour.
f) Circulate till the acid concentration & total iron remains constant.
g) After stabilizing drain the solution to effluent tank. (If possible under nitrogen)
h) Neutralize the solution with water & burnt lime before discharge in tanker.
Process -
NH3
Fe2O3 + C6H8O7 FAC (Ferrous ammonium citrate)
pH 9 - 9.5
C6H8O7 + NH3 + NaNO2 Fe3O4
60 c Magnetite Layer
11. Check passivation layer, remove temporary arrangement, normalize the system & restore the
area after housekeeping.
TESTING PROCEDURE
1. Total Alkalinity: -
Total Alkalinity as CaCO3 (%) = Total Volume * 0.1 * 50 * 100 / (10 * 1000)
= Total Volume * 0.5
Citric Acid Strength (%) = Total Volume * 0.1 * 70 * 100 / (10 * 1000)
= Total Volume * 0.07