Diagram ELEC

This document outlines the submission process for electrical services including: 1) The submission requirements are different for electrical loads less than 100kVA which are submitted to Unit Servis TNB, and loads over 100kVA which are submitted to Bahagian Pembahagian TNB. 2) Additional requirements for street lighting plans submitted to the Public Works Department (JKR) including RSA reports, lighting calculations, and drawings. 3) The approval process involves input from various departments including TNB, the National Fiberization and Connectivity Plan (NFP), and JKR at various stages before final approval.

Uploaded by

Khay Saad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
171 views1 page

Diagram ELEC

This document outlines the submission process for electrical services including: 1) The submission requirements are different for electrical loads less than 100kVA which are submitted to Unit Servis TNB, and loads over 100kVA which are submitted to Bahagian Pembahagian TNB. 2) Additional requirements for street lighting plans submitted to the Public Works Department (JKR) including RSA reports, lighting calculations, and drawings. 3) The approval process involves input from various departments including TNB, the National Fiberization and Connectivity Plan (NFP), and JKR at various stages before final approval.

Uploaded by

Khay Saad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SUBMISSION OF ELECTRICAL SERVICES

(Post-KM)

TNB NFP Street Lighting

Documents for telecommunication plan approval:-


< 100 kVA @ 85 kW > 100 kVA @ 85 kW 1) Standard cover letter PBT JKR Negeri
(Unit Servis TNB) (Bahagian Pembahagian TNB) 2) Surat Perakuan Persetujuan (from Pre-KM) (Jabatan Kejuruteraan) (Bahagian Jalan)
3) 3 sets of all telecommunication drawings
4) 1 CD copy of the above drawings
Documents for electricity supply application:- Documents for electricity supply application:- Acquired by C&S:-
1) Standard cover letter 1) Standard cover letter If R&D approved plans If R&D approved plans 1) RSA report
2) KM approval letter 2) KM approval letter Submit to NFP are required are not required 2) JKR approved R&D plans
3) KM approved drawing 3) KM approved drawing
4) 3 sets of Map A, B & C
DESIGN STAGE

4) 3 sets of Map A, B & C


5) 3 sets of key plan, location plan & site plan 5) 3 sets of Borang Maklumat Awal Perjangkaan Besar (if HT supply intake) Input from NFP:- Acquired by C&S:- Documents for JKR Negeri (Bahagian Jalan):-
drawing showing incoming supply infrastructure 6) 3 sets of key plan, location plan & site plan Invoice for plan processing fee R&D approved plans 1) Standard cover letter
6) 3 sets of main single line diagram drawing showing: 2) RSA report (acquired by C&S)
7) 1 CD copy of the above drawings a) Location of TNB sub-station 3) JKR approved R&D plans (acquired by C&S)
b) Incoming supply infrastructure Pay plan processing fee Documents for Jabatan Kejuruteraan:- Documents for Jabatan Kejuruteraan:- 4) 3 sets of street lighting drawings
7) 3 sets of sub-station detail drawings (if applicable) 1) Standard cover letter 1) Standard cover letter 5) Lux calculation worksheets / catalog
Submit to Unit Servis TNB 8) 3 sets of main single line diagram 2) KM approval letter 2) KM approval letter
9) 1 CD copy of the above drawings Documents for NFP:- 3) R&D approved plans (acquired by C&S) 3) Street lighting drawings:
1) Standard cover letter 4) Street lighting drawings: a) 2 sets paper Submit to JKR
2) Payment receipt of plan processing fee a) 2 sets paper b) 1 set linen
Submit to Bahagian Pembahagian TNB b) 1 set linen 4) Lux calculation worksheets
5) Lux calculation worksheets 5) Payment receipt of plan processing fee
Submit to NFP 6) Payment receipt of plan processing fee

Submit to Jabatan Kejuruteraan

Uploads drawings online


Input from TNB:- Input from TNB:- Input from NFP:-
1) Approved plans 1) Approved plans 1) Approved plans
2) No obstruction/approval letter 2) No obstruction/approval letter 2) Plan approval letter
Input from Jabatan Kejuruteraan:- Input from JKR Negeri (Bahagian Jalan):-
1) Approved plans 1) Approved plans
2) Plan approval letter 2) Plan approval letter
TENDER
STAGE

TO ENSURE THE TENDER DOCUMENTS (DRAWINGS & BQ) HAS BEEN COMPLIED WITH ALL AUTHORITIES REQUIREMENTS/INPUTS

TNB E-application:- TNB E-application:- Documents for handing over of sub-station:- Start of work notice to JKR Negeri:-
Registration Registration 1) Standard cover letter 1) Standard cover letter
2) 3 sets of Borang 'A' 2) Contractor's name
3) 3 sets of Land Title 3) Site photos (before & after)
4) 12 sets of Pre-Computation drawing
5) Bank Guarantee (if applicable)
TNB E-application:-
1) TNB meter application
Submit to Bahagian Pembahagian TNB 2) Form G & H

Pay TNB meter deposit

TNB meter installation


CONSTRUCTION STAGE

Request for sub-station building inspection by TNB:- Request for inspection by NFP:- Request for inspection by Jabatan Kejuruteraan:- Request for inspection by JKR Negeri:-
Standard cover letter Standard cover letter Standard cover letter Standard cover letter

Handing over Pay inspection fee

Input from TNB:-


Cas Sambungan Pengguna (CSP)
Input from TNB:-
Cas Sambungan Pengguna (CSP)
Pay CSP
Pay CSP

TNB installation works:- Documents for relay calibration:- TNB installation works:- If SDF room does not If SDF room If street lighting is not If street lighting is
1) Work permit Standard cover letter 1) Work permit require a TNB meter requires a TNB meter handed over to PBT handed over to PBT
2) Cable laying 2) Cable laying

Submit to Bahagian Pembahagian TNB TNB E-application:- TNB E-application:-


1) TNB meter application 1) TNB meter application
TNB E-application:- TNB E-application:-
2) Form G & H 2) Form G & H
1) TNB meter application 1) TNB meter application
2) Form G & H 2) Form G & H
Pay TNB meter deposit Pay TNB meter deposit
Pay TNB meter deposit Pay TNB meter deposit
TNB meter installation TNB meter installation
TNB meter installation TNB meter installation

Request for TNB supporting letter:- Request for TNB supporting letter:- Request for NFP supporting letter:- Request for Jabatan Kejuruteraan supporting letter:- Request for JKR Negeri supporting letter:-
Standard cover letter Standard cover letter Standard cover letter Standard cover letter 1) Standard cover letter
2) Street lighting & feeder pillar photos
3) Form G & H
T&C

4) Earthing test result


5) Feeder pillar FAT result
6) Supplier assurance letter

TNB supporting letter TNB supporting letter NFP supporting letter Jabatan Kejuruteraan supporting letter JKR Negeri supporting letter
CCC CPC

Submit to Architect