Risk Management Process
Risk Management Process
Page 1 of 8
Step 2 Identify the risks
The purpose of this step is to identify what could go wrong (likelihood) and what is
the consequence (loss or damage) of it occurring.
Key questions to ask include:
What can happen? List risks, incidents or accidents that might happen by
systematically working through each competition, activity or stage of your
event to identify what might happen at each stage.
How and why it can happen? List the possible causes and scenarios or
description of the risk, incident or accident.
What is the likelihood of them happening?
What will be the consequences if they do happen?
Page 2 of 8
The criteria for evaluating the risks at your club are shown below:
LIKELIHOOD
Rating
The potential for problems to occur in a year
5 ALMOST CERTAIN: will probably occur, could occur several times
per year
4 LIKELY: high probability, likely to arise once per year
3 POSSIBLE: reasonable likelihood that it may arise over a five-year
period
2 UNLIKELY: plausible, could occur over a five to ten year period
1 RARE: very unlikely but not impossible, unlikely over a ten year
period
Question: what is the loss or damage impact if the risk event occurred
(severity?)
POTENTIAL IMPACT
Rating
In terms of the objectives of the club
5 CATASTROPHIC: most objectives may not be achieved, or
several severely affected
4 MAJOR: most objectives threatened, or one severely affected
3 MODERATE: some objectives affected, considerable effort to
rectify i.e. sport injury requires medical attention and has some
impact on participation in sport and/or other activity
2 MINOR: easily remedied, with some effort the objectives can be
achieved i.e. sport injury requires first aid treatment and
prevents immediate participation in sport and/or other activity
1 NEGLIGIBLE: very small impact, rectified by normal processes
i.e. sport injury but does not prevent participation
Risk priority
The risk priority scale determines the nature of the risk and the action required.
They are indicators to assist in the decision making of what action is warranted for
the risks.
Page 3 of 8
Table 3 Risk priority scale
IMPACT
5 4 3 2 1
Catastroph Major Moderate Minor Negligible
ic
O
D 1 Medium Medium Minor Minor Minor
Rare (3) (3) (4) (4) (4)
Key:
Extreme Extreme risks that are likely to arise and have potentially
serious consequences requiring urgent attention
Major Major risks that are likely to arise and have potentially serious
consequences requiring urgent attention or investigation
Medium Medium risks that are likely to arise or have serious consequences
requiring attention
Minor Minor risks and low consequences that may be managed by routine
procedures
Page 5 of 8
Attachment A
How the risk rating works.
Step 1 & 2: Establish Context & Identify risk
A risk identified under physical sporting environment - Does our cricket
club take all reasonable steps to check field for foreign objects which may
result in injury to players would be considered as follows:
Question: Step 3 Analyse the risk
Is it likely that some of our club home field games may not be checked
properly or at all using the CricketNSW field check requirements
[likelihood]?
Answer:
Maybe (probability Yes)
Question:
If yes, how likely?
Answer: Table 1
Likelihood rating would be a 3 (reasonable likelihood) over a season.
Question: Table 2
If yes, what would be the consequences and/or the loss or damage impact
of those consequences [severity]?
Answer:
Impact rating would be a 3 (moderate, some objectives threatened i.e.
player injury may occur but can be easily remedied (prevented), with
some effort, objectives can be achieved).
Question:
What is the nature of the risk and the action required?
Answer: Table 3 rate the risk
Given the likelihood rating is a 3 (possible) and the impact rating is a 2
(minor), the risk rates as a medium (level 3) risk on the risk rating scale.
So it is a medium risk that is possible to arise over a five year period but
can be easily remedied.
Question: Step 4 Treat the risk
How should it be treated?
Answer: Step 4 and 5.
Ensure all volunteer cricket team coaches/managers are aware of their
game day obligations as required by Cricket NSW and Cricket Australia
under their risk management program. Club office bearers should ensure
that volunteer cricket team coaches/managers receive the appropriate
training, information and compliance checklists and provide feedback.
They should have first aid kits and medical plan.
Page 6 of 8
Effective risk management is increasingly seen as an essential element of
delivering successful projects. With a project risk management process and
system, risks to the project can be identified early and minimized, and
teams will be able to seize opportunities as they occur.
Use the five tips below to help deliver projects on time, on budget, and
with the highest quality results.
Tip 1: End the Walk on by Culture and Involve the Entire Project
Team
Risk management must be a part of your project embraced by all team
members. Rather than teams looking blindly to the project manager and
assuming he is managing all risk for the project, the entire team must be
involved. In my experience, the organizations that are the most successful
at project risk management have both a top down and a bottom up
approach risk management is mandated and supported from senior
management, and each team member is empowered to speak up and take
action. Employees who identify risks early are recognized and rewarded.
Tip 2: Identify Risks Early Even in the Bid-Phase
Before the project even begins, your team should be already working to
identify risks. Begin by gathering all project members (and other
employees and partners who have worked on related projects) into
workshops and brainstorm a list of potential risks and opportunities.
Consult the project plan, old project plans, online resources, and outside
experts to make sure your list of probable risks is as complete as possible.
Tip 3: Communicate, Communicate, Communicate
To ensure risks are continuously identified and communicated
appropriately, add project risks and opportunity discussions as a standing
topic to the teams regular meetings. The benefits of open communication
trickle up, as the project manager will have better information to report to
the project sponsor or principal, ensuring that the customer doesnt have
unexpected surprises. Open communication also allows for the
identification of interrelated risks risks that appear small on their own,
but may act as a catalyst for larger problems.
Tip 4: Analyze and Prioritize then Reprioritize
As risks are identified during a project, teams must decide how to prioritize
them. Overall, risks should be measured by the impact they could have on
the project goals, and start with those that could cause the biggest losses
and gains, and those with the highest probability of occurrence. Once you
have a set of risk criteria, use it to assess all risks as they are identified
during a project.
Risks may be rescored and reprioritized as they pass up the project
hierarchy and organization, based on the different priorities at each level.
What may be seen as a less important risk by a single project might be
viewed as more important at the program or organizational level. Here a
wider picture becomes clear across multiple projects and strategic
priorities, rather than operational needs, apply. For example, a lack of skills
seen in multiple projects may be best addressed by a company-wide
training program.
Tip 5: Plan and Implement Risk Responses
Once your risks are identified, analyzed, and prioritized, the risk response
is the activity that adds value to your project. The right response can
Page 7 of 8
prevent a risk from occurring or minimize its negative effects. Responses
include risk avoidance, risk minimization, risk transfer and risk acceptance.
By implementing risk management into a project early, and ensuring risks
are openly communicated throughout the project, teams can be more
successful in delivering on time and on budget, by avoiding unexpected
risks and sticking to the project timeline. And last of all, share what worked
and what didnt, throughout the business so the future bids and projects
have a library of best practices to call on.
How has risk management helped your organization complete projects
successfully? Are you sharing best practices across the business?
Page 8 of 8