Proposed Project Execution Baseline Schedule Rev B

This document provides a proposed baseline schedule for offshore transportation, installation, and pre-commissioning activities for the SOGT PCSB project under contract number SOGT-CT-CTR-0501. The schedule outlines key project milestones and durations for transportation of linepipes by tug, onshore construction works in Kimanis, Sabah, and offshore installation from April 2012 through July 2012.

Uploaded by

seehari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views

Proposed Project Execution Baseline Schedule Rev B

This document provides a proposed baseline schedule for offshore transportation, installation, and pre-commissioning activities for the SOGT PCSB project under contract number SOGT-CT-CTR-0501. The schedule outlines key project milestones and durations for transportation of linepipes by tug, onshore construction works in Kimanis, Sabah, and offshore installation from April 2012 through July 2012.

Uploaded by

seehari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONTRACT NO: SOGT-CT-CTR-0501

CONTRACT TITLE: OFFSHORE TRANSPORTATION, INSTALLATION AND PRE-COMMISSIONING FOR PCSB SOGT PROJECT

DOCUMENT: PROPOSED BASELINE SCHEDULE

Activity ID Activity Name Original Start Finish Total 2012


Duration Float Mar Apr May Jun Jul Aug

SOGT PLs & PLEMs 459d 4h 11-Apr-11 A 30-Jul-12 32d 5h

PROJECT MILESTONES 459d 4h 11-Apr-11 A 30-Jul-12 0d

Contract 459d 4h 11-Apr-11 A 30-Jul-12 0d


MS-CON-1010 Effective Award Date 0d 11-Apr-11 A
MS-CON-1030 Commencement of Works 0d 09-May-12* 0d
MS-CON-1020 Completion of Mobilisation 0d 09-May-12* 0d
MS-CON-1040 Pre-Commissioning 0d 17-Jun-12* 0d
MS-CON-1050 Mechanical Completion 0d 25-Jul-12* 0d
MS-CON-1060 Commissioning Intital Acceptance 0d 30-Jul-12* 0d
Proposal 93d 22-Apr-12 23-Jul-12 6d 4h
MS-GEN-1020 Completion of Mobilisation 0d 22-Apr-12 17d 4h
MS-GEN-1030 Commencement of Works 0d 22-Apr-12 17d
MS-GEN-1040 Pre-Commissioning 0d 15-Jun-12 2d 4h
MS-GEN-1050 Mechanical Completion 0d 03-Jul-12 22d 4h
MS-GEN-1060 Commissioning Initial Acceptance 0d 23-Jul-12 6d 4h
TRANSPORTATION (LINEPIPES) 44d 21h 09-Apr-12 24-May-12 99d 3h

250C CB + Tug #01 39d 21h 09-Apr-12 19-May-12 104d


Loadout #01 20d 09-Apr-12 29-Apr-12 3h 7h
72d
Loadout #08 16d 21h 02-May-12 19-May-12 104d
250C CB + Tug #02 39d 9h 12-Apr-12 22-May-12 3h
101d
Loadout #02 20d 7h 12-Apr-12 03-May-12 15h
71d
Loadout #09 17d 9h 04-May-12 22-May-12 12h
101d
250C CB + Tug #03 38d 21h 15-Apr-12 24-May-12 15h3h
99d
Loadout #03 20d 14h 15-Apr-12 06-May-12 70d
Loadout #10 17d 21h 06-May-12 24-May-12 17h3h
99d
250C CB + Tug #04 20d 21h 18-Apr-12 09-May-12 114d
Loadout #04 20d 21h 18-Apr-12 09-May-12 3h
114d
250C CB + Tug #05 20d 21h 21-Apr-12 12-May-12 3h 3h
111d
Loadout #05 20d 21h 21-Apr-12 12-May-12 111d 3h
250C CB + Tug #06 20d 21h 24-Apr-12 15-May-12 108d
Loadout #06 20d 21h 24-Apr-12 15-May-12 3h
108d
250C CB + Tug #07 20d 9h 27-Apr-12 18-May-12 3h
105d
Loadout #07 20d 9h 27-Apr-12 18-May-12 15h
105d
123d 9h 01-Mar-12 02-Jul-12 15h
27d
ONSHORE CONSTRUCTION
19h
OEP Onshore Works @ SOGT, KImanis, Sabah 123d 9h 01-Mar-12 02-Jul-12 27d
Mobilisation 14d 01-Mar-12 14-Mar-12 19h
23d
Construction Of Cofferdam (for 36" PL) 35d 10-Mar-12 13-Apr-12 9d
Holdback Anchor & Winch (for 36" PL) 16d 30-Mar-12 14-Apr-12 8d
System Function Test (for 36" PL) 1d 15-Apr-12 15-Apr-12 8d
Beach Pull (36" PL) 3d 21-Apr-12 23-Apr-12 2d 5h
Assist on 36" PLEM to SOGT PL Pre-commissioning 5d 12h 19-May-12 27-May-12 2d 5h
Construction Of Cofferdam (for 28" PL) 25d 21-Mar-12 14-Apr-12 23d
Holdback Anchor & Winch (for 28" PL) 21d 25-Mar-12 14-Apr-12 23d
Winch System Function Test (for 28"PL) 1d 15-Apr-12 15-Apr-12 23d
Beach Pull (28" PL) 3d 06-May-12 09-May-12 2d 5h
Assist on 28" PLEM to SOGT PL Pre-commissioning 5d 12h 27-May-12 03-Jun-12 2d 5h
28" Gooseneck and Onshore Pipeline Installation (KP0.057 to KP0) 8d 29-May-12 06-Jun-12 27d
Post-Trench in g Reinstatement Work (28" PL) 26d 07-Jun-12 02-Jul-12 20h4h
27d
36" Gooseneck & Onshore Pipeline Installation (KP0.057 to KP0) 8d 29-May-12 06-Jun-12 27d
Post-Trench in g Reinstatement Work (36" PL) 26d 07-Jun-12 02-Jul-12 20h4h
27d
OFFSHORE INSTALLATION 119d 5h 13-Mar-12 10-Jul-12 52d 4h

PRE-INSTALLATION SURVEY 16d 13-Mar-12 29-Mar-12 20d


Mobilisation 3d 12h 13-Mar-12 16-Mar-12 14h
11d
Pre-Installation Survey 10d 12h 16-Mar-12 27-Mar-12 20d
Demobilisation 2d 27-Mar-12 29-Mar-12 14h
20d
INSTALL 28" & 36" PLs, PLEMS & SPMs' HOSES (1MAS 300) 86d 20h 14-Apr-12 10-Jul-12 14h4h
52d
Mob LB 1 Mas 300 7d 14-Apr-12 21-Apr-12 2d 5h
Install 36" X .6 Km Beach Pull 3d 21-Apr-12 24-Apr-12 2d 5h
Install 36" X 9.7 KM Pipeline upto PLEM end 11d 18h 24-Apr-12 06-May-12 2d 5h
Install 28" X 0.6 Km Beach Pull 3d 2h 06-May-12 09-May-12 2d 5h
Install 28" X 11.2 Km Pipeline upto PLEM end 10d 6h 09-May-12 19-May-12 2d 5h
Pre-commision 36" Pipeline from PLEM end to Onshore Location 7d 12h 19-May-12 27-May-12 2d 5h
Precommission 28" Pipeline from PLEM end to Onshore Location 7d 12h 27-May-12 03-Jun-12 2d 5h
28" Pipeline PLEM-2 Installation 6d 03-Jun-12 09-Jun-12 2d 5h
36" Pipeline PLEM-1 Installation 5d 18h 09-Jun-12 15-Jun-12 3d 15h
Install L-1390 SPM 1d 12h 15-Jun-12 17-Jun-12 3d 15h
Install Hoses for L-1390 SPM (36") 8d 17-Jun-12 25-Jun-12 3d 15h
Install L-3380 SPM 1d 12h 25-Jun-12 26-Jun-12 3d 15h
Install Hoses for L-3380 SPM (28") 6d 12h 26-Jun-12 03-Jul-12 3d 15h
DeMob 1 MAS 300 7d 12h 03-Jul-12 10-Jul-12 52d 4h
SPM CHAINS INSTALLATION (TYPE 2 DP VESSEL) 18d 22h 30-May-12 18-Jun-12 74d
Mobilisation 5d 30-May-12 04-Jun-12 12h
88d
36" SPM Chains Installation 1d 04-Jun-12 05-Jun-12 10h
86d
36" SPM Chains Pre-Tensioning 3d 6h 05-Jun-12 08-Jun-12 18h1h
25d
28" SPM Chains Installation 2d 16h 09-Jun-12 12-Jun-12 23d
28" SPM Chains Pre-Tensioning 3d 6h 12-Jun-12 15-Jun-12 19h
23d
Demobilisation 2d 12h 15-Jun-12 18-Jun-12 19h
74d
POST-TRENCHING WORKS 36d 22-Apr-12 28-May-12 12h
95d
Mobilisation 7d 22-Apr-12 29-Apr-12 45d
Post-Lay Trenching of 36" PL 11d 29-Apr-12 10-May-12 23h
45d
Post-Lay Trenching of 28" PL 11d 10-May-12 21-May-12 23h
45d
Demobilisation 7d 21-May-12 28-May-12 23h
95d
PL POST-INSTALLATION SURVEY 10d 6h 13-May-12 23-May-12 99d
Mobilisation 2d 18h 13-May-12 16-May-12 22h
5d 17h
Post-Installation Survey 6d 12h 16-May-12 22-May-12 10d 5h
Demobilisation 1d 22-May-12 23-May-12 99d
22h

Actual Work Critical Remaining Work Page 1 of 1 Date Rev... Checked Approved
22-Jun-11 A nain.saim azmi.mdsaid
Remaining Work Milestone
08-Oct-11 B nain.saim azmi.mdsaid