Project Rundown C
Project Rundown C
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N
1 DESIGN STAGE 282 days
2 Submission of BA4 1 day
3 Site investigation 110 days
4 Submission of Ground investigation plans, obtaining approval and consent for GI 60 days
5 Submission of supervision plan and BA10 for RSC(GIFW) 1 day
6 site surveys and ground investigation 21 days
7 Submission of BA14 and getting approval 28 days
8 Submission of ground investigation report and geotechnical assessment 1 day
9 Superstructure design 21 days
10 Pile cap and ELS design 21 days
11 Pile foundation design 21 days
12 Submission of BA5,BA8, supervision plan for pile foundation and ELS, obtaining approval and cons 90 days
13 Submission of BA10 1 day
14 Submission of BA5 and supervision plan for pile cap, obtaining approval 60 days
15 CONSTRUCTION STAGE I 522 days
16 Site formation 5 days
17 Setting Out 2 days
18 Site check 2 days
19 Clearance and leveling of the site 3 days
20 HOARDING 60 days
21 Submission of BA19 60 days
22 footing of vertical member of coveredwalkway 4 days
23 Coveredwalkway member assembling 7 days
24 MOBLIZATION 14 days
25 Site office, mobile toilet, utilities and drainage system 14 days
26 Installation of Lighting system on hoarding and security system 14 days
27 First aid, fire safety equipment and sign boards 14 days
28 Submission ofBA5,BA8 and supervision plan for superstructure, obtaining approval and consent 90 days
29 FOUNDATION 129 days
30 BORING AND PILING 77 days
31 Detection and verification of the location of utilities 7 days
32 Pre-drilling, piles installation 28 days
33 test loading 14 days
34 Submission of piling record plans and reports 14 days
35 Post-construction test and submission of test report 14 days
36 Submission of BA14 and getting approval 28 days
37 Submission of BA8and supervision plan for pile cap and getting consent 30 days
38 EXCAVATION AND LATERNAL SUPPORTS 52 days
39 Sheetpiles installation 7 days
40 Submission of record plan and BA14 and getting approval 28 days
41 Construction of Temporary loading platform 3 days
42 dewatering 14 days
43 Excavation ,installation of lateral supports 14 days
44 PILE CAP 58 days
45 Formwork, reinforcement fixing and concreting of pile cap 30 days
46 Submission of BA14 and getting approval 28 days
47 SUPERSTRUCTURE WORK 215 days
Page 1
ID Task Name Duration Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N
48 Formwork, reinforcement fixing and concreting of core wall 7 days
49 Back filling and removing lateral supports 7 days
50 Formwork and reinforcement fixing of G/F slab, casting concrete 4 days
51 Formwork and reinforcement fixing of G/F (including 1/F slab), casting concrete 7 days
52 frame shoring on G/F 1 day
53 Formwork and reinforcement fixing of 1/F (including 2/F slab), casting concrete 7 days
54 frame shoring on1/F 1 day
55 Hoist installation 175 days
56 Bamboo Scaffolding 175 days
57 Formwork and reinforcement fixing of 2/F (including 3/F slab), casting concrete 7 days
58 frame shoring for 2/F 1 day
59 Tower crane installation 175 days
60 construction of 3/F,4/F and typical floor 175 days
61 CONSTRUCTION STAGE II 126 days
62 Construction of partition, external wall, Finishing 91 days
63 Installation of windows and doors 7 days
64 Installation of electrical system and inspection by E.M.S.D 21 days
65 Installation of lift and inspection by E.M.S.D 21 days
66 Installation of fire safety system and inspection by F.S.D 21 days
67 Installation of portable water system and drainage system, and inspection by W.S.D and D.S.D 21 days
68 Disassembling of hoarding 7 days
69 Construction of RC fence wall 7 days
70 OCUUPATION PERMIT 14 days
71 submission of BA 13 and a schedule of the use of accepted building materials and products 14 days