Risk Management Process
Risk Management Process
Development Network
Risk Management process
Risk Management is a five step process:
Step
Step
Step
Step
Step
1
2
3
4
5
Page 1 of 6
Page 2 of 6
The criteria for evaluating the risks at your club are shown below:
LIKELIHOOD
The potential for problems to occur in a year
RARE: very unlikely but not impossible, unlikely over a ten year
period
Rating
POTENTIAL IMPACT
In terms of the objectives of the club
Risk priority
The risk priority scale determines the nature of the risk and the action required.
They are indicators to assist in the decision making of what action is warranted for
the risks.
Question: what is the risk priority?
Page 3 of 6
L
I
K
E
L
5
Catastroph
ic
4
Major
3
Moderate
2
Minor
1
Negligible
5
Almost
certain
Extreme
(1)
Extreme
(1)
Major
(2)
Major
(2)
Medium
(3)
4
Likely
Extreme
(1)
Extreme
(1)
Major
(2)
Medium
(3)
Minor
(4)
3
Possible
Extreme
(1)
Major
(2)
Major
(2)
Medium
(3)
Minor
(4)
2
Unlikely
Major
(2)
Major
(2)
Medium
(3)
Minor
(4)
Minor
(4)
1
Rare
Medium
(3)
Medium
(3)
Minor
(4)
Minor
(4)
Minor
(4)
I
H
O
O
D
Key:
Extreme
Major
Major risks that are likely to arise and have potentially serious
consequences requiring urgent attention or investigation
Medium
Minor
Accepting the risk for example most people would consider minor
injuries in participating in the sporting activity as being an inherent risk.
Avoiding the risk is about your club deciding either not to proceed with
an activity, or choosing an alternate activity with acceptable risk which
meets the objects of your club. For example, a cricket club wishing to raise
funds may decide that a rock climbing competition without a properly
trained and accredited instructor, equipment etc may decide a safer way of
raising funds.
Reducing the risk likelihood or consequences or both is commonly
practiced treatment of a risk within sport, for example use of mouth guards
for players in some sports i.e. contact sports.
Transferring the risk in full or in part, will generally occur through
contracts or notices for example your insurance contract is perhaps the
most commonly used risk transfer form used. Other examples include
lease agreements, waivers, disclaimers, tickets, and warning signs.
Retaining the risk is knowing that the risk treatment is not about risk
elimination, rather it is about acknowledging the risk is an important part
of the sport activity and some must be retained because of the inherent
nature of the sport activity. It is important to consider the level of risk
which is inherent and acceptable.
Financing the risk means the club funding the consequences of risk i.e.
providing funds to cover the costs of implementing the risk treatment.
Most community non profit sport clubs would not consider this option.
Whichever option you choose to treat a risk, if the risk has rated highly you will
need to carefully consider necessary policies, procedures and strategies to treat
the risk. These will include:
Also, seek independent advice from your broker, insurer, solicitor, financial advisor
and/or affiliated state body.
Attachment A
How the risk rating works.
Step 1 & 2: Establish Context & Identify risk
A risk identified under physical sporting environment - Does our cricket
club take all reasonable steps to check field for foreign objects which may
result in injury to players would be considered as follows:
Question: Step 3 Analyse the risk
Is it likely that some of our club home field games may not be checked
properly or at all using the CricketNSW field check requirements
[likelihood]?
Answer:
Maybe (probability Yes)
Question:
If yes, how likely?
Answer: Table 1
Likelihood rating would be a 3 (reasonable likelihood) over a season.
Question: Table 2
If yes, what would be the consequences and/or the loss or damage impact
of those consequences [severity]?
Answer:
Impact rating would be a 3 (moderate, some objectives threatened i.e.
player injury may occur but can be easily remedied (prevented), with
some effort, objectives can be achieved).
Question:
What is the nature of the risk and the action required?
Answer: Table 3 rate the risk
Given the likelihood rating is a 3 (possible) and the impact rating is a 2
(minor), the risk rates as a medium (level 3) risk on the risk rating scale.
So it is a medium risk that is possible to arise over a five year period but
can be easily remedied.
Question: Step 4 Treat the risk
How should it be treated?
Answer: Step 4 and 5.
Ensure all volunteer cricket team coaches/managers are aware of their
game day obligations as required by Cricket NSW and Cricket Australia
under their risk management program. Club office bearers should ensure
that volunteer cricket team coaches/managers receive the appropriate
training, information and compliance checklists and provide feedback.
They should have first aid kits and medical plan.
Page 6 of 6