Transformer Testing
Transformer Testing
TRANSFORMERS
TESTING
AT
NTPC RAMAGUNDAM
A thesis report submitted to the
SREENIDHI INSTITUTE OF SCIENCE AND TECHNOLOGY
YAMNAMPET, GHATKESAR, R.R DIST.
AFFILIATED TO JNTU-H
In partial fulfillment of the degree of
TRAINING IN ELECTRICAL ENGINEERING
SUBMITTED BY
S.KASI VISHWANATH
13311A0279
V.ASHOK BABU
13311A0264
1
1
CERTIFICATE
This is to certify that the project entitled
TRANSFORMERS TESTING
By
S.KASI VISHWANATH
13311A0279
V.ASHOK BABU
13311A0264
PROJECT GUIDE
ORDINATOR
PROJECT CO-
SRI B.V.SUBRAMANYAM,
SUPERINTENDENT (EMD),
AGM (EMD),
NTPC RAMAGUNDAM.
NTPC RAMAGUNDAM .
2
2
ACKNOWLEGEMENT
We take this opportunity to record our gratitude to all those who helped us in successful
completion of the project.
3
3
INDEX
Sl.no.
1.
2.
3.
4.
5.
Sl.no.
Pg.no.
NTPC OVERVIEW
07
TRANSFORMER
14
TRANSFORMERS IN RSTPS
17
TRANSFORMER TESTING
21
TEST PROCEDURES
a)Oil test
31
b)Voltage ratio measurement
32
c) Vector group & polarity
33
d)3- excitation at 415v no load
35
e)Winding resistance m/m
36
f) Insulation resistance m/m
37
g) Capacitance & tandelta m/m
39
h)Separate source applied voltage test 41
i) No load &magnetizing m/m
42
j) Harmonics of no load current
44
k)Lighting impulse test with transfer
voltage measurements
l) Switching impulse voltage withstand
45
test
m) Load loss & impedance m/m
n) Temp. rise test
o) Cooler loss m/m
47
48
50
52
4
4
Pg.no.
53
54
55
6.
CONCLUSION
56
7.
REFERENCES
57
6
6
NTPC- OVERVIEW
NTPC, the major power utility, generating over one fourth of the total
thermal power in the country, the corporation established its credentials
over a period of two decades and is maintaining its impeccable record by
consistently generating reliable and quality power. . NTPC established in
1975 and its mission has been to construct commission and operate
power projects most economically and efficiently.
NTPC has chalked out a capacity addition program of adding ambitious
38,014 MW by installing a number of coal and gas based power plants in
the ten years.
NTPC VISION
TO BE THE WORLD'S LARGEST AND BEST POWER PRODUCER, POWERING
INDIA'S GROWTH.
MISSION
DEVELOP AND PROVIDE RELIABLE RELATD, PRODUCTS AND SERVIES AT
COMPETITIVE PRICES, INTERGRATING MULTIPLE ENERGY SOURCES WITH
INNOVATIVE AND ECO FRIENDLY TECHNOLOGIES & CONTRIBUTE TO
SOCIETY.
Devoted
INTRODUCTION TO RSTPS
APPROVAL OF RSTPS:
RSTPS was declared by government of India in 1978.
Late Sri Morarji Desai, the then PM laid the foundation stone of
RSTPS.
RSTPS began commercial operation by 1983.
Ramagundam Super Thermal Power Station spread over 10000
acres of land is situated in Karimnagar district of A.P. It has an installed
capacity of 2600 MW having 3*200 MW three units in Stage-I, 4*500 MW
four units in Stage-II & III. This is the biggest power station in Southern
India.
UNIT WISE POWER GENERATION:The whole plant is divided into 3 Stages, each Stage being planned at one
time.
DISTRIBUTION OF ELECTRICITY:8
8
STATE
MW
% AGE
Andhra Pradesh
610 MW
29 %
Tamilnadu
470 MW
22 %
Karnataka
345 MW
16 %
Kerala
245 MW
12 %
Goa
100 MW
5%
50 MW
2%
Pondicherry
2600MW
Unit Sizes
Stage I
3*200 MW
Stage II 3*500 MW
Stage III 1*500 MW
Location
Ramagundam, Karimnagar, AP
Coal Source
Water Source
Pochampad Dam
Coal Consumption
Water Consumption
250 Cusecs
Transmission Line
2475km of 400KV
Approved Investment
Coal Transportation
Height of Chimney
9
9
225m Stage I
250m Stage II
275m Stage III
Ultimate Manpower
Total Land
:
:
3200
10,000 acres
It achieved Raj Bhasha award for the year 1998-1999 for the first
time NTPC featured in 1997 edition of the Limca Book of
Records as the largest thermal power plant suppliers and the first
to construct and commission the HVDC transmission link in the
country.
10
10
ENERGY TRANSFER
In the Boiler chemical energy in fuel is converted into thermal
energy by heating water and converting it into steam. The steam
produced in the boiler is expanded. In the turbine, the thermal energy is
converted into kinetic energy. As the steam expands it rotates the turbine.
This motion of the turbine is transmitted to generator in which the
mechanical energy is converted into electrical energy, which is
transmitted to various load centers through transmission line.
THERMAL
ENERGY
BOILER
11
11
MECHANICAL
ENERGY
TURBINE
COAL TO STEAM
COAL HANDLING
Coal from the coal wagons is unloaded in the coal handling plant, here the
coal is crushed. This coal is transported up to the raw coal bunkers with
the help of belt conveyers. Coal is transported to Bowl Mills by coal
feeders. These coal feeders are of two types, volumetric and gravimetric.
The coal is pulverized in the Bowl mills, where it is ground to a powder
form. The BOWL MILL is one of the most advanced designs of coal
pulverizer presently manufactured. The advantages of this mill are:
The mill consists of a round metallic table on which coal particles fall. This
table is rotated with the help of a motor. There are three large steel
rollers, which are spaced 120 degrees apart. When there is no coal, these
rollers do not rotate but when the coal is fed to the table it packs up
between roller and the table and this force the rollers to rotate. Coal is
crushed by the crushing action between the rollers and rotating table. This
crushed coal is taken away to the furnace through coal pipes with the help
of hot and cold air mixture from Primary Air Fan. The P.A. Fan takes
atmospheric air from F.D Fan is heated in the air heaters and sent to the
furnace as combustion air.
STEAM CIRCUIT
Water from the boiler feed pump passes through the economizer
and reaches the boiler drum. Water from the drum passes through down
comers and goes to bottom ring header. Water from the bottom ring
header is divided to all the four sides of the furnace. Due to heat and the
density difference the water rises up in the water wall tubes. Water is
partly converted to steam as it rises up in the furnace. This steam and
water mixture is again taken to the boiler drum where the steam is
separated from the water. Water follows the same path while the steam is
sent to super heaters for super heating. The super heaters are located
inside the furnace and the steam is superheated (540 deg.) and finally it
goes to the turbine.
Flue gases from the furnace are extracted by I.D fan, which
maintains balance draft in the furnace with F.D Fan. These flue gases
emits their heat energy to various super heaters in the pant house and
finally passes trough air pre-heaters and goes to electrostatic precipitators
where the ash particles are extracted. Electrostatic precipitators consist of
metal plates, which are electrically charges. Ash particles are attracted on
to these plates, so that they do not pass through the chimney to pollute
the atmosphere. Regular mechanical hammers blows cause the
accumulation of ash to fall to the bottom of the precipitators where they
are collected in a hopper for disposal. This ash is mixed with water to form
slurry and is pumped to ash pond. But nowadays 80% of the ash is used in
formation of ash bricks which is cheaper and stronger than the normal
bricks other 20% is sent into the atmosphere through the chimney.
PLANT LAYOUT
TRANSFORMERS
Construction:
Transformers can be classified by tank construction and core construction.
a) Tank Construction
Several types of transformer tank construction are used to prevent
exposing liquid to the atmosphere. These types are as follows:
Free breathing: This type is open to the atmosphere (i.e., the airspace
above the liquid is at atmospheric pressure). The transformer breathes as
the air pressure and temperature change outside the tank. Some of these
transformers can be equipped with dehydrating compounds in the
breather.
Conservator or expansion-tank: These transformers are equipped with
small expansion tanks above the transformer tank. The transformer tank
is completely filled with oil, and the transformer breathes by means of this
small tank, usually through a dehydrating compound. The purpose of the
small tank is to seal the transformer fluid from the atmosphere and to
reduce oxidization and formation of sludge.
Sealed tank: These transformers are equipped with an inert gas, such as
nitrogen that is under pressure above the liquid in the transformer tank.
Generally, the pressure range for this type of transformer is 8 to +8
lb/in2
Gas-oil sealed: These transformers have an auxiliary tank to completely
seal the interior tank, containing transformer liquid, from the atmosphere.
16
16
d) Rectifier Transformer
The rectifier transformer is also a special purpose transformer used in the
rectification of AC to direct current (DC) applications in the process
industry. These transformers are specially braced to withstand mechanical
stresses produced by high currents.
e) Power Transformer
The power transformer has a rating in excess of 500 kVA and is primarily
used in transforming energy from generating stations to transmission
lines, from transmission lines to distribution substations, or from utility
service lines to plant distribution substations.
OIL transformer
Tap changer
17000 liters
220 liters
90000Kg
30000Kg
15500Kg
135500Kg
YNa0d11
- ONAN
19
19
OFAF
420/3 KV
825 A
21KV
9250A
13.89%
50c max.
50c
55c
189
189
252
252
ONAF
315
315
Reactive (MVA)
LV Reactive
LV Active
63
3
MVA RATING
HV side:-voltage
LV side:-voltage
Impedance voltage at 420/3/21 KV
Ambient temperature
Maximum temperature oil rise: Winding: -
Noise level
84
4
105
5
315
-
420/3 KV
21KV
13.89%
50c max.
50c
55c
86.5dB Max.
YNyn0d11
Type of cooling
- ONAN / ONAF
60/100
60/100
HV side:-voltage
LV side:-voltage
Impedance voltage at 400/34.5 KV
Ambient temperature
Maximum temperature oil rise: Winding: -
OIL transformer
400KV
34.5KV
15.89%
50c max.
40c
55c
23400 liters
72000Kg
31500Kg
21000Kg
124500Kg
20
20
ONAN
60
53.5 KV
373.5V
LINE Amperes
HV
LV
Ambient temperature
Maximum temperature oil rise: Winding: DC Output
Max.
1.12
160.6
-
50c max.
50c
55c
70KV peak
800mA
TRANSFORMERS TESTING
DC TESTING: - The DC testing of transformers involves testing of the
solid winding insulation and the insulating fluids used in transformers. The
testing of solid winding insulation complements other transformer testing.
The solid winding insulation tests are not conclusive in themselves, but
provide valuable information on winding conditions, such as moisture
content, and carbonization. The DC tests are considered nondestructive
even though at times they may cause a winding failure.
It should be pointed out that a winding failure results from an
incipient failure that the test was supposed to detect. If it had gone
undetected, it might have occurred at an unplanned time. The DC tests
conducted for transformer winding insulation are:Insulation Resistance Measurement
This test is performed at or above rated voltage to determine if there are
low resistance paths to ground or between winding to winding as a result
of winding insulation deterioration. The test measurement values are
affected by variables such as temperature, humidity, test voltage, and
size of transformer.
This test should be conducted before and after repair or when
maintenance is performed. The test data should be recorded for future
comparative purposes. The test values should be normalized to 20C for
comparison purposes.
The general rule of thumb that is used for acceptable values for safe
energization is 1 M per 1000 V of applied test voltage plus 1 M.
22
22
30C
200
100
50
400
200
100
500
600
250
300
125
100
IR=CE / (KVA)
Where
IR is the minimum 1 min 500 V DC insulation resistance in megohms from
winding to ground, with other winding or windings guarded, or from
winding to winding with core guarded
23
23
25 Hz
1.0
20.0
20.0
15
24 kV DC dielectric test set
24
.
Dielectric Test Values for Routine Maintenance of Liquid-Filled
Transformers
Transformer Winding Rated Voltage (kV)
Maintenance DC Voltage (kV)
Factory Test AC
Routine
Voltage (kV)
1.2
2.4
4.8
8.7
15.0
18.0
25.0
34.5
10
15
19
26
34
40
50
70
10.40
15.60
19.76
27.04
35.36
41.60
52.00
72.80
DC High-Potential Test
The DC hi-pot test is applied at above the rated voltage of a transformer
to evaluate the condition of winding insulation. The DC high-voltage test is
not recommended on power transformers above 34.5 kV; instead the AC
hi-pot test should be used. Generally, for routine maintenance of
transformers, this test is not employed because of the possibility of
damage to the winding insulation. However, this test is made for
acceptance and after repair of transformers. If the hi-pot test is to be
conducted for routine maintenance, the AC test values should not exceed
65% of factory AC test value. The routine maintenance AC voltage value
should be converted to an equivalent DC voltage value by multiplying it
by 1.6, that is, 1.6 times the AC value for periodic testing (i.e., 1.6 65 =
104% of AC factory test value). The DC hi-pot test can be applied as a
step-voltage test where readings of leakage current are taken for each
step. If excessive leakage current is noticed, voltage can be backed off
before further damage takes place. For this reason, the DC hi-pot test is
considered to be a nondestructive test. Some companies conduct the AC
hi-pot test at rated voltage for 3 min for periodic testing instead of the
65% of factory test voltage.
The procedure for conducting this test is as follows:
Transformer must have passed the insulation resistance test
immediately prior to starting this test.
Make sure transformer case and core are grounded.
Disconnect all high-voltage, low-voltage, and neutral connections, lowvoltage control systems, fan systems, and meters connected to the
transformer winding and core.
Short-circuit with jumpers together all high-voltage bushings and all lowvoltage bushings to ground.
If a hi-pot test is to be conducted for routine maintenance,
consider the following in advance: (1) assume that a breakdown will occur,
(2) have replacement or parts on hand, (3) have personnel available to
25
25
perform work, and (4) is the loss of the transformer until repairs are made
beyond the original routine outage.
AC VOLTAGE TESTS
The AC voltage tests can be classified into the categories as listed below:
1. PF and DF
2. AC high potential tests
3. Very low frequency (VLF)
4. AC series resonant
5. Induced frequency
6. Partial discharge (PD)
7. Impulse tests
The AC tests may be classified as destructive and nondestructive tests.
The PF and DF tests are considered nondestructive since the test voltages
used in performing these tests do not exceed line-to-neutral voltages of
the equipment being tested. The basic principle of the nondestructive
testing is the detection of a change in the measurable characteristics of
an insulation that can be associated with the effects of contaminants and
destructive agents without overstressing the insulation. The AC high
potential, VLF, and AC series resonant tests may be classified as
destructive since the test voltages associated with these tests are higher
than normal operating voltages which may overstress the insulation. The
effect of repeated high voltage (HV) tests on insulation are cumulative
and therefore thoughtful consideration should be given on the benefits of
these tests for routine field and maintenance testing, except for special
investigations or for acceptance testing. The induced frequency, PD, and
impulse tests are primarily conducted at the factory during manufacturing
of electrical apparatus and equipment.
PF/DF Testing
28
28
WINDING RESISTANCE
It helps in determining the following: I2 R losses in transformer
Winding temperature at the end of temperature rise test of
transformer
As a bench mark for assessing possible damages in the field.
Central
phase
BN
180 V
230 V
Right side
phase
CN
50 V
115 V
180 V
230 V
Procedure for magnetic balance test for transformer:1. First keep the tap changer of the transformer in normal position.
2. Now disconnect the neutral from the ground.
3. Apply the single phase AC supply 230volts across HV and Neutral
terminal.
4. Now measure the voltages in the other terminals with respect to
neutral.
5. Repeat the test for each other three phases.
The TTR detects high resistance connections in the lead circuitry or high contact
resistance in tap changer by higher excitation current and difficulty in balancing
the bridge.
VECTOR GROUP
This test is done to conform whether the vector group provided in the
name plate is correct or not and also to confirm that the winding has not
been damaged during transport, installation and erecting. A vector group
is a means of identifying which combination of three phase connection
(wye-delta, delta-delta, delta-wye etc.) will allow three phase transformer
to be paralleled with each other as some combination cannot be
paralleled.
on all insulating fluids but a very critical one.BDV is test of choice because
it takes very less time to conduct and is a precursor to the condition of the
insulating liquids, before carrying out extensive series of tests.
2. Standard:
IEC 422
3. Method:
A) BDV : IEC 156
B) PPM : IEC 814
4. Procedure:
A) BDV - A Sample of oil has to be taken from the sampling valve of
the transformer under test. The oil has to be put in the BDV
container & the distance between the 2 electrodes must be set to
2.5 mm.
B) PPM - A Sample of oil has to be taken from the sampling valve of
the transformer under test. Mistubishi Moisturemeter is used to
33
33
6. Connection Diagram:
YNd11:-
5. Instrument used:
Digital Multimeter (Make Motwane )
36
36
4. Instrument used:
a) Digital multimeter (MAKE- Rishabh)
b) Digital Clamp-meter
37
37
6. Instrument used:
a) Digital insulation resistance meter (Megger) with time
measurement.
b) RTDs with temp scanner for temp measurement (MAKE-RADIX)
7. Connection diagram:
For eg: (HV+N)/LV (TANK+EARTH) Combination
40
40
7. Connection diagram :
42
42
43
43
If the voltage indicated by both voltmeter is not the same, the no load loss
is corrected by:
Po = Pm / (P1+K*P2) in kW
Where K = (U/U)2
Where
Po = corrected no load loss
Pm = measured no load loss
U = mean voltage reading
U = rms voltage reading
P1 = ratio of hysteresis losses to total iron losses 0.5 for oriented steel
P2 = ratio of eddy current losses to total iron losses 0.5 for oriented steel
% excitation current = (avg excitation current measured) / (rated current of
excited winding)*100
6. Instrument used:
a) Yokogawa power analyser for measurement of voltage, current,
frequency, power and harmonics.
b) PT (potential transformer) for step down of voltage applied for voltage
measurement purpose.
c) CT (current transformer) for step down of current circulated for current
measurement purpose.
7. Connection diagram:
45
45
46
46
Chop time
2 to 6sec
BIL (kV)
+/- 3%
48
48
4. Connection diagram:
49
49
Stray loss @ to C = Total measured loss @ to C at rated current Total I2R loss @ to CStray loss @ 75oC = (235+t) / (235+75) x
Stray loss @ to C
Load loss @ 75oC = Total I2R loss @ 75oC + Stray loss @ 75oC
% impedance @ to C = (impedance voltage at rated current/
rated voltage) x 100
Impedance voltage at rated current
= (rated current/ measured current) x measured impedance
voltage @ to C
4. Instrument used:
a) Power analyzer for measurement of voltage, current,
frequency and power.
b) PT (Potential transformer)
c) CT (Current transformer)
d) RTDs for measurement of temp.
5. Connection diagram:
51
51
5. Instrument used:
Yokogawa power analyzer
Current transformer
Potential transformer
RTDs
Temperature scanner
Resistance meter
6. Connection diagram:
53
53
1. Purpose:
To check the oil tightness of the transformer.
2. Standard: CBIP Clause No. 17.3.1
3. Procedure:
All oil-filled compartments shall be tested for oil tightness by
completely filling oil of a viscosity not greater than that of
insulating oil conforming at ambient temp and applying a pressure
as per design and specification measured at the base of the tank.
This pressure shall be maintained for a period of not less than
12hrs for oil, during which time no leakage shall occur.
4. Acceptance criteria: No leakage shall occur.
1. Purpose:
To check the insulation withstand capability of core, frame and
auxiliary winding.
2. Standard: As per R & D Plate drawing
3. Procedure:
Auxiliary circuits insulation test:
The wiring for auxiliary power and control circuitry subjected to a 1
min AC separate source test of 2kV.
Core to Frame insulation test:
The core to frame insulation will be subjected to a 1 min AC separate
source test of 10kV.
Frame to tank insulation test:
The frame to tank insulation will be subjected to a 1 min AC separate
source test of 10kV.
4. Acceptance criteria:
The test is passed if voltage is withstood for 1 min.
56
56
Measurements in Ratiometer
Direct ratio readings and polarity indication will be observed.
4. Acceptance criteria:
57
57
58
58
59
59