Formwork PDF
Formwork PDF
INTRODUCTION ............................................................................................................................
................................ 3
DESIGN
REQUIREMENTS ...........................................................................................................................
.................... 4
FACTORS RELATING TO
FORMWORK ........................................................................................................................... 6
HIGH WALL
FORMWORK ..................................................................................................................................
........ 6
Timber Framed
Formwork. .......................................................................................................................................
7
SHEATHING ...................................................................................................................................
............................ 8
WALL TYING
SYSTEMS ......................................................................................................................................
........ 8
CONSTRUCTION
JOINTS ...........................................................................................................................................
.9
SLIPFORM .....................................................................................................................................
.......................... 10
CLIMBING OR JUMP
FORMS ................................................................................................................................... 10
Formwork
Striking ............................................................................................................................................
.......... 11
Standards relating to
formwork ................................................................................................................................. 12
ERECTION FOR COLUMNS, BEAMS, SLABS AND
STAIRS ............................................................................................. 13
Columns .........................................................................................................................................
......................... 13
Column Formwork
Construction ............................................................................................................................ 13
Formwork Page 2
BALUSTRADING. ...................................................................................................................... 26
STRIKING, MAINTENANCE, STORAGE OF
FORMWORK .......................................................................................... 27
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 3
INTRODUCTION
A number of fundamental principles apply to all formwork.
Consideration must be given to:
Acceptable tolerances permitted;
Use of appropriate materials;
Standards of workmanship;
Construction for ease of erection and stripping;
Care and maintenance of the formwork, so that the maximum number of re-uses can be achieved.
Formwork is a temporary construction; however care must be taken to prevent damage to permanent
work. Three general principles govern formwork design and construction:
Quality accuracy of the concrete shape and the final finished surface quality.
Safetystrength of the formwork structure. Personal safety of people, both carpenters and the public.
EconomyThe structural frame is usually the most significant cost component, a dominant and critical
factor in the time of construction.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 4
DESIGN REQUIREMENTS
When designing formwork, consider the following:
1. Strength: Forms and shutters have to be designed to support dead weight, live load and hydrostatic
pressure. Sheathing must be rigid enough to resist bulging.
Formwork for vertical concrete elements i.e. columns and walls are subject to pressures on the form face.
This is caused by the fluid action of the fresh concrete. The pressure of the fluid concrete on the vertical
faces increases proportionately with the depth of concrete. The maximum pressure being at the bottom of
the form. This maximum pressure for the full depth fluid concrete is the hydrostatic pressure for concrete
and usually occurs when the concrete is placed very quickly.
It should not be possible for the bracing to be dislodged by impact, or wind, acting from any direction.
Refer to illustration below.
Design Pressure
Distribution
Pressure Distribution
Hydrostatic Pressure
Walers
2. Speedy erection and dismantling: The formwork design and the methods of assembly must be as
simple as possible to reduce time spent in erection and dismantling. The formwork should be simple to
remove without causing damage to the concrete.
3. Tightness of joints: The liquid retaining properties of the formwork must be adequate to prevent leakage
of cement and fine aggregate from the concrete.
UNITEC New Zealand Applied Technology Institute Revised 2009
P max
Vertical stud
Formwork Page 5
4. Rigidity: Brace formwork and support to ensure no movement may take place under wind pressure, or
when the concrete is being placed and vibrated. The shutters must be rigid enough to keep the concrete
member within the allowable tolerances.
5. Reuse: Design for unit construction, if possible, so that you can strike and reuse as soon as possible.
Use clamps, wedges, and similar devices to hold sections of formwork in place. Avoid nailing as much as
possible, nail holes and bruising of the timber will spoil formwork for further use. The formwork material
must be durable and capable of producing a good surface finish.
6. Ease of handling: Forms and shutters must be of a size and weight that can be handled by the labour
and plant available on site.
Adjustment: Arrange all props, shores, and struts so that they can be properly adjusted. They must bear
on sole plates, so that the load is safely distributed on to the structure below.
Removal of debris: Provide all formwork with special cleanout holes to allow for the removal of sawdust,
shavings, and other debris from the bottom of the formwork before the pour begins.
Formwork Tolerances and variations in alignment
Columns Up to 3m high 6 mm
Piers 3m to 6m 10 mm
Walls Above 6 m 18 mm
Variations from level 6 mm in 6m 10 mm max.
Variations from plan position 6 m bay
over 6m bay
Not to encroach over boundary.
UNITEC New Zealand Applied Technology Institute Revised 2009
12 mm
25mm
Variations in size and position of openings, sleeves
6 mm
Variations in cross-sectional size Up to 600mm + 6mm or 3 mm
Over 600 mm 6 mm
Variations in footings + 25mm or 12mm
Thickness 0.05 of dimension
Variations in consecutive steps
Rise 1.5 mm
Tread 3 mm
Formwork Page 6
Acknowledgement to the Australian Government Publishing Service for the use of their Wall formwork
illustrations.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 7
Formwork Page 8
SHEATHING
There are various types sheathing available. The appropriate sheathing must be selected to obtain the
specified finish required. Options include:
Sawn or planed timber - edges may be square cut or tongue and grooved, to prevent grout leakage. An
alternative is a foam strip inserted between the boards.
Plywood - exterior grade or formply are available in various thickness. The grain on the outer face must
be parallel with the span of the wall formwork framing.
Tempered hardboard - produces a good finish, however, is less resistant to damage and multiple use.
Plastic linings give a good finish, however, it must have a solid backing.
Rubber linings are sometimes used for textured finish.
Glass fibre or other similar moulds maybe used for various architectural features on wall or window
panels.
Formwork Page 9
CONSTRUCTION JOINTS
Stop ends and construction joints must always be formed at right angles to the concrete pour. If keyed
stop ends are required, use an angled fillet or a split insert for a parallel sided slot. Construction joints at
the top of a pour may require a batten fixed to the formwork to finish the concrete in a straight line.
At the ends of walls and at the planned positions of construction joints, stop- ends must be constructed.
Due to reflection and rebound of the energy of vibration from the face of the stop-end, the concrete
pressure acting on it can exceed that generally acting on the form face.
In most cases the studs of the formwork do not coincide with the stop-end and as a result, the plywood
deflects under the concrete pressure and grout and water escapes past the stop-end.
A common method of resisting the forces on the stop end is by wedging it off the wall ties.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 10
SLIPFORM
This is a form which is continually being moved upwards, or sideways, as the concrete is being
poured.The rate of movement is regulated so that the forms leave the concrete only after it is strong
enough to retain its shape and support the weights imposed on it.
Vertical structures such as chimneys (Huntly Power Station) and cooling towers (Ohaaki Thermal Power
Station) are often done this way. Kerbing and channelling can also be slipformed. Jacking of the forms
can be done by screw, electric, pneumatic, but usually hydraulic.
Formwork Page 11
Formwork Striking
The process of removing the formwork. The earliest time this
can be done is when the concrete has developed sufficient
strength. Reinforced concrete structural elements
need to be able to carry themselves and any other
superimposed loads over their intended spans.Stripping transfer
parts or loads to concrete structure should be gradually
transferred. Consideration should be given to:
Specification requirements, check
site documents for the concrete
strength required and stripping times.
The concrete age and minimum
strength at the time of stripping.
The method and sequence of stripping.
Limits on the loads to be placed on the structure.
Remove formwork components with minimum damage.
The condition of the components will determine the reuse
and costs.
UNITEC New Zealand Applied Technology Institute Revised 2009
Striking piece
Formwork Page 12
Formwork Page 13
Formwork Page 14
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 15
Acknowledgement to the Australian Government Publishing Service for the use of their Column
illustrations.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 16
Formwork Page 17
Formwork Page 18
Braced column
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 19
TEE BEAMS
L BEAMS
Design and construction of beam formwork
Beam soffit must be thickened timber or strengthened plywood.
Beam sides 18mm plywood or 25mm boards, with studs (cleats) at 500 to 600mm centres.
Deep beams (over 600mm) should have walers and ties.
Props or falsework must be placed under the headtree, or under the bearers, and must be spaced to
suit the weight of concrete.
Use angle fillets in the beam side to soffit joint where possible.
Allowance must be made for height adjustment of the props or falsework.
Erection sequence for constructing beam formwork includes:
Position of sole plates;
Marking out and setting heights for falseworks;
Assemble and position props, adjustable head jacks,
falseworks , bearers and Spreaders;
Construct and erect side walls and beam soffit.
Position of sole plates
The purpose of a sole plate is to transfer vertical load from one vertical support member to the foundation.
The vertical support requires a base plate fitted to help distribute the load to the sole plate, which is
usually a sleeper. If the sole plate is positioned on natural ground, it is important the ground is graded and
consolidated to a level surface. The objective is to achieve maximum bearing beneath the sole plate.
Once sole plates are positioned and firmly bedded they should be checked for level.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 20
Formwork Page 21
SUSPENDED SLABS
Suspended floor slabs can be constructed using cast in- situ, precast units or a combination of both.
Whichever method is used, it is important to support the proposed method of construction using a
combination of timber or steel bearers and adjustable shoring. The spacing and type of support system
required is determined by the load imposed during the construction process. Manufacturers provide tables
to assist in the selection and spacing of adjustable shoring systems.
The erection sequence for constructing a suspended floor slab includes:
Determining the bearer spacing;
Erecting bearers and joists;
Fixing the sheeting;
Preparation for concrete.
Formwork Page 22
Formwork Page 23
Joints are watertight.
Any panels cut to accommodate penetrations or openings are the correct shape and dimension and in
the required position.
All joints of sheets are fully supported.
Preparation For Concrete Tasks to be completed before the concrete is cast include:
Clearing the decking of all debris;
Marking out for reinforcing;
Apply a release agent to sheeting;
Check site documentation and with subcontractors to accommodate sleeves, penetrations and conduit
for services;
Fix reinforcing steel in accordance with structural details;
Final clean and inspection required.
PROPRIETARY FORMWORK
Proprietary formwork Systems are supplied by companies such as Boral Acrow, and Rapid Metal
Developments in NZ, and for specific projects are often supplied by overseas companies.
Boral Acrow supplies:
U Form ( Universal): for walls, columns, beams, and slabs with various accessories for scaffolding
support. Shutters are joined with snap ties.
"Flexible form": for curved structures, and can be combined with "U form".
For some projects, special formwork is designed and constructed, often working in conjunction with an
overseas company.
TEMPORARY PROPPING (SHORING)
As early striking of beam and slab soffit formwork is desirable for early re use, some form of temporary
support is generally needed.
Although of a temporary nature, it is often called permanent propping, with temporary propping being
used while concrete is poured.
Typical permanent shoring or propping
Undisturbed: Forms are struck without disturbing the props that are to be left in place. Proprietary
systems allow this.
Secondary: Props are placed in designed locations before disturbing any of the existing props.
Partial: The soffit formwork is struck shutter by shutter and new props are placed progressively.
Total: The complete soffit is struck and re propped before any construction work commences above.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 24
FALSEWORK
Falsework is temporary structure or framework used in construction to support materials, equipment, or
formwork. (See OSH Safety in Construction Guide No 7)
Most falsework is vertical, supporting beams and slabs. Falsework must be engineer designed.
As well as supporting the weight, allowance must be made for sideway pressures such as wind, stacks of
materials causing eccentric loading, props out of plumb, formwork being
struck by machinery or crane loads.
Falsework can be:
timber;
scaffold tube with adjustable screw jacks, top or bottom, or both;
proprietary prop such as Acrow prop;
proprietary braced frame such as Acrow shore;
proprietary floor centre (a telescopic beam);
proprietary beam clamps such as Acrow beam clamp which combines formwork and falsework.
Setting up falsework:
Base must be level and firm. A sole plate is preferable;
Props and frames must be placed as per design;
Place props centrally under members;
Brace falsework in two directions;
Floor centres must have full bearing for the end tongues;
Beams must be centred over props to prevent eccentric (out of line) loading.
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 25
STAIR FORMWORK
Points to consider when designing stair form work
Stair formwork must support the weight of concrete. The weight of the throat of the stair and the steps
will have to be supported.
Because of the slope of the stair, some of the force is transmitted sideways. All formwork must be well
tied together to prevent sideway movement.
Consider the finish of the stair treads and type of nosing. Space may have to be left for purpose made
nosing.
Step nosing
Riser, vertical or raked
Rebate for purpose made nosing
Throat
The design of the stair must conform to the stair design regulations e.g. residential or commercial. Refer
to the Building Code D1 for stair design and regulations.
Formwork Page 26
Raiser form
Beveled at 450 for trowel access
UNITEC New Zealand Applied Technology Institute Revised 2009
Formwork Page 27
Nosings Concrete nosings are very prone to chipping. It is common practice to reinforce the corner with a
purpose made nosing such as:
Vinyl, aluminium, ceramic, etc. Nosings also help to make the steps non slip.
Balustrading Provision must be made for fixing balustrading unless it is to be fixed at the surface using
masonry bolts. Balustrading can be made from galvanised wrought iron, galvanised pipe, aluminium,
stainless steel, etc., most of which is site measured after steps have been poured.
Balustrading acts as a guard railing. It must be strong enough to resist a person falling against it and be
least 900mm to 1m high.
Precast stairways In many buildings and in particular in multi-storey buildings, there are often a greater
number of identical stair flights. In these cases the advantages of precasting the stairs merit
consideration.