Decommissioning Insight 2016
Decommissioning Insight 2016
Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
Foreword
Executive Summary
Introduction
Decommissioning Expenditure and Activity on the
UK Continental Shelf in 2015
Decommissioning Activity Forecast 2016 to 2025
5.1
Well Plugging and Abandonment
5.2
Facilities and Pipelines Making Safe and
Topside Preparation
5.3
Topside and Substructure Removal
5.4
Subsea Infrastructure Decommissioning
5.5
Pipeline Decommissioning
5.6
Onshore Recycling and Final Disposal
5.7
Site Remediation and Monitoring
Forecast Decommissioning Expenditure
2016 to 2025
6.1
Forecast Expenditure on the
UK Continental Shelf
6.2
Key Expenditure Metrics on the
Norwegian Continental Shelf
Forecast Unit Costs 2016 to 2025
7.1
Well Plugging and Abandonment
7.2
Facilities Making Safe
(UK Continental Shelf Only)
7.3
Topside and Substructure Removal
(UK Continental Shelf Only)
Appendices
Glossary
4
6
10
11
12
12
20
27
36
38
42
46
47
47
57
59
59
63
64
67
69
1.
Foreword
Oil & Gas UKs Decommissioning Insight 2016 presents a unique forecast of offshore oil and gas infrastructure
decommissioning in the UK and Norway over the next ten years. The report gives the most comprehensive picture
to date of anticipated activity in these territories, providing asset operators with valuable insights to assist in
effective decommissioning planning and pointing the supply chain to where demand for services is likely to lie.
The analysis confirms that, despite low oil prices continuing to challenge the economics of many of the more
mature offshore assets, there has not been a rush to decommission. The reality is much more complex, with
different market forces influencing decommissioning strategies across the North Sea. While some companies are
delaying activity due to cash-flow constraints, others are deferring cessation of production as sustained efforts
to improve efficiency result in extended field life. Others are expediting decommissioning as the cost of some
decommissioning activities becomes cheaper at lower prices.
Yet it is clear that decommissioning is a growing, if still emerging, market. Last year, 1.1 billion was spent on
decommissioning in the UK and 1 billion in Norway, compared with 800 million and 770 million in the same
countries in 2014. This trend is expected to continue, as in 2015, decommissioning accounted for 5 per cent of total
industry expenditure, up from 2 per cent in 2010. This proportion is likely to exceed 12 per cent in the UK next
year. This not only reflects increasing decommissioning activity, but also needs to be set against the wider impact
of reducing operating costs and falling capital investment in the lower price environment.
Fifty-two new projects appear for the first time in this years report, bringing to more than 100 the number of
platforms forecast for complete or partial removal from both continental shelves over the next ten years. Over
1,800 wells are expected to be plugged and abandoned and some 7,500 kilometres of pipeline are scheduled for
decommissioning. Most of this activity has been long planned.
Overall, decommissioning on the UK Continental Shelf (UKCS) from now until 2025 represents an estimated
17.6 billion opportunity, with over 50 per cent of this market to be found in the central North Sea. This offers
considerable scope for companies to develop world-class competencies in decommissioning both for deployment
on the UKCS and export overseas. To make the most of this opportunity, the UKs supply chain will need to position
itself by offering high quality, cost-efficient goods and services if they are to win business in a fiercely competitive
global market.
The offshore oil and gas industry is one of the cornerstones of the UK economy. In 2016, total offshore expenditure
is expected to be 19 billion, while the supply chain is forecast to generate revenues of 30 billion. The industry
supports around 330,000 highly skilled, well-paid jobs, and provides a secure domestic supply of primary energy.
Oil and gas production rose in 2015 for the first time in 15 years, a trend that will continue in 2016.
It is believed that there could be up to 20 billion barrels of oil and gas still to recover. If the UK is to continue
to gain the full economic benefit from its oil and gas resource, it is important that the industry works with the
Oil and Gas Authority (OGA) and HM Treasury to attract fresh investment, avoid premature decommissioning,
retain the critical infrastructure required to access future reserves and ensure decommissioning is carried out in a
timely and most cost-effective way.
This work is strengthened by a competitive tax regime designed to promote new investment and government
funding for seismic surveys to open up new areas for exploration. Oil & Gas UK is now working with HM Treasury to
explore further avenues in its Driving Investment strategy for the sector, including the possibility of transferring
tax relief on decommissioning costs on the sale of assets.
4
In parallel, Oil & Gas UK is working on the MER UK Decommissioning Board with the OGA and the
Department for Business, Energy and Industrial Strategy (BEIS) to develop new fit-for-purpose technical,
commercial and operational solutions to lower the cost of decommissioning, while maintaining high safety and
environmental standards.
The industry fully respects its environmental obligations and is assisting BEIS as it prepares for the forthcoming
review of the OSPAR decision 98/3 by the OSPAR Offshore Industry Committee in 2018.
Broad comparisons of the 2016 survey with last years report suggest that the unit costs of decommissioning
are falling, particularly for well plugging and abandonment. This is partly due to a market-driven response to
the downturn as associated costs such as rig-rates have fallen, but it may also indicate that the industrys own
efficiency improvements and the experiences gained from past decommissioning activity being applied to new
projects are beginning to have effect.
This is good news. It will only be through focused and effective collaboration between industry, government
and the regulators that the outcomes from decommissioning North Sea assets can be optimised in a mutually
beneficial manner.
Michael Tholen,
Upstream Policy Director, Oil & Gas UK
N.B. The collection and analysis of the data by Oil & Gas UK on behalf of the industry has the support of the
Norwegian Petroleum Directorate and Norsk Olje & Gass.
8
2.
Executive Summary
Decommissioning Overview
This report captures data from 186 decommissioning projects1 across the UK (153) and Norwegian (33) Continental
Shelves. Fifty-two of these projects are new to this years report due to the survey timeframe shifting to 2016
to 20252; some projects being brought forward in response to the low oil price environment; or estimates only
now becoming available.
Seventeen projects have been postponed since last years survey to outside the timeframe as operators have
successfully extended field life.
Of the 134 existing projects included in both this years and last years survey, there have been some movements
in the timing of specific decommissioning activities within project scopes. For example, one company might
accelerate a well plugging and abandonment (P&A) campaign to take advantage of falling rig rates during the
current downturn, while another defers this activity due to cash-flow constraints.
Looking across the breadth of activity, there is more evidence of projects being brought forward in the
central and northern North Sea than in the southern North Sea, Irish Sea and Norwegian Continental Shelf.
On the UK Continental Shelf (UKCS), 94 per cent of the 153 projects in this region do not yet have firm timings
and are still in the early planning stages. This involves outlining the scope of the activities to be undertaken and
carrying out feasibility studies that will ultimately be influenced by changing market conditions over time.
Sustained efficiency improvements and cost reductions could defer cessation of production (CoP) and therefore
push back decommissioning in some cases, while the low oil price environment and access to infrastructure
issues might expedite it in other cases. For example, over the last 12 months, 33 assets within the timeframe on
the UKCS have deferred CoP, 72 have brought forward CoP, while for 135 CoP remains unchanged.
Current Activity
The decommissioning market is an emerging sector across the UK and Norwegian Continental Shelves.
Twelve operators carried out decommissioning activity across these regions in 2015.
In 2015, 1 billion was spent on decommissioning on the Norwegian Continental Shelf and 1.1 billion on the
UKCS, compared with 770 million and 800 million3 in 2014, respectively4.
The decommissioning market has expanded from 2 per cent of total industry expenditure in 2010 in both the UK
and Norwegian Continental Shelves to 5 per cent of total expenditure in 2015.
Annual expenditure on decommissioning is expected to reach around 2 billion on the UKCS by 2017 making up
12 per cent of total expenditure, but it is likely to remain close to 1 billion on the Norwegian Continental Shelf
and 5 per cent of total expenditure.
Project is defined by the operator and can range from a single well for P&A to multi-platforms.
The 2015 survey covers the timeframe 2015 to 2024 and the 2016 survey covers the timeframe 2016 to 2025.
3
This survey covers data from end-of-field-life decommissioning projects and does not include expenditure of activity
associated with mid-life decommissioning.
4
Figures for Norway are taken from the Norwegian Petroleum Directorate. See www.npd.no/en
1
2
Ten-Year Outlook
More than 100 platforms are forecast for complete or partial removal.
Forecast activity on the UKCS is significantly higher than on the Norwegian Continental Shelf over the next ten
years. This reflects the relative maturity of the two regions, with more fields reaching the end of their field life
in the UK.
On the UKCS, 17.6 billion is forecast to be spent on decommissioning between 2016 and 2025.
This is an increase of 0.7 billion on the 2015 reports ten-year forecast of 16.9 billion, primarily due to 41 new
UKCS projects in this years survey.
Fifty-three per cent (9.4 billion) of the forecast expenditure on the UKCS will be concentrated in the central
North Sea.
The Norwegian Petroleum Directorate estimates that annual expenditure on decommissioning will average
around 1 billion per year on the Norwegian Continental Shelf until 20205, compared with close to 1.7 billion
per annum on the UKCS.
7
With exception of one well in the Norwegian Sea, all decommissioning activity in Norway over the next decade
is planned in the Norwegian North Sea area.
The largest category of expenditure on the UK and Norwegian Continental Shelves is well P&A at 47 per cent and
56 per cent, respectively.
Compared with last years survey, the ten-year outlook for the average unit cost of platform well P&A has fallen
by one-third in the southern North Sea and Irish Sea to 2 million, but has remained unchanged across the
central North Sea, northern North Sea and west of Shetland at 4.1 million.
Average subsea exploration and appraisal well P&A unit costs over the next ten years are forecast to fall by over
35 per cent in the southern North Sea and Irish Sea to 5.6 million. The cost per well in the central North Sea,
northern North Sea and west of Shetland is also set to be around 20 per cent cheaper at 6.2 million compared
with forecasts made last year.
Subsea development well P&A unit costs over the next decade have fallen by around 20 per cent on average in
the southern North Sea and Irish Sea to 7.6 million. The average forecast cost per well in the central North Sea,
northern North Sea and west of Shetland has increased by around 3 per cent to 10.2 million.
See Norwegian Petroleum Directorate www.npd.no/en. Total forecast decommissioning expenditure from 2016
to 2025 is not available.
7
Southern
North Sea
and Irish Sea
Central
North Sea
Northern
North Sea
and West of
Shetland
Number of
projects6
39
83
396
Proportion of wells
that are platform
wells
Total UK
Norwegian
Continental
Shelf
Total UK
and Norway
31
153
33
186
644
430
1,470
362
1,832
80%
37%
73%
60%
85%
64%
Number of
platforms for
removal
67
16
12
95
14
109
Topside weight to
be removed
90,260
tonnes
187,238
tonnes
262,022
tonnes
539,520
tonnes
112,612
tonnes
652,132
tonnes
Substructure weight
to be
removed
63,745
tonnes
71,056
tonnes
96,737
tonnes
231,538
tonnes
84,734
tonnes
316,272
tonnes
Number of
mattresses to be
decommissioned
4,526
5,979
1,162
11,667
188
11,855
Subsea
infrastructure to be
removed
4,268
tonnes
56,714
tonnes
1,697
tonnes
62,679
tonnes
1,745
tonnes
64,424
tonnes
Number of
pipelines to be
decommissioned
200
484
96
780
67
847
Length of
pipelines to be
decommissioned
3,426
kilometres
2,666
kilometres
1,038
kilometres
7,130
kilometres
297
kilometres
7,427
kilometres
Total tonnage
coming onshore
164,834
tonnes
369,190
tonnes
360,456
tonnes
894,480
tonnes
199,091
tonnes
1,093,571
tonnes
Project is defined by the operator and can range from a single well for P&A to multi-platforms.
Average Forecast Plugging and Abandonment Costs per Well from 2016 to 2025
Central and
Southern North Sea Northern North Sea
and Irish Sea
and West of
Shetland
UKCS
Norwegian
Continental Shelf
10 million
2 million
4.1 million
3 million
Subsea suspended
exploration and
appraisal well P&A
5.6 million
6.2 million
6.1 million
Subsea
development
well P&A
7.6 million
16.1 million
10.2 million
9.6 million
Average Forecast Cost per Tonne for Removal from 2016 to 20257
Southern North Sea and Irish Sea
Topside removal
Substructure removal
Some of the average cost forecasts are significantly different to those presented in the 2015 survey. These changes
will be discussed in section 7.
3. Introduction
3.1 Survey Development and Methodology
The Decommissioning Insight 2016 provides the first joint decommissioning activity forecast for the UK and
Norwegian Continental Shelves for the period 2016 to 2025 so that operators and the supply chain have a more
comprehensive picture across the North Sea and can effectively plan for decommissioning in the most cost
efficient way8. The report also provides detailed expenditure forecasts for activity on the UK Continental Shelf
(UKCS) and some key expenditure metrics for the Norwegian Continental Shelf. Complete expenditure information
was not available for Norway.
The report is compiled through primary data collection from 25 operators on the UKCS and 6 operators on the
Norwegian Continental Shelf between June and September 2016. This provides over 95 per cent coverage in both
regions. There are more operators on the UKCS with forecast decommissioning activity, reflecting the relative
maturity of the two shelves.
The survey was structured around the components of the decommissioning Work Breakdown Structure described
in Oil & Gas UKs Decommissioning Cost Estimation Guidelines9. Following feedback received from the industry
and the joint industry-Oil and Gas Authority (OGA) MER UK Decommissioning Board, the report has also been
expanded to include additional insight into topside and substructure removal activity on the UKCS, splitting the
activity into work already contracted out and work that is still to be contracted.
The information collected is presented in a non-attributable and aggregated format. Analysis has been carried out
on a regional basis and split into groups the central (CNS) and northern North Sea (NNS) and west of Shetland
(W o S); the southern North Sea (SNS) and Irish Sea; and the Norwegian Continental Shelf. Almost all of the
activity on the Norwegian Continental Shelf is concentrated in the Norwegian North Sea area. Wherever possible,
information has been split further into more specific regions. Where particular projects are referred to, this
information has been gathered from publicly available data.
This survey covers data from end-of-field-life decommissioning projects and does not include expenditure of activity
associated with mid-life decommissioning.
9
The Guideline on Decommissioning Cost Estimation is available to download at www.oilandgasuk.co.uk/product/op061
8
10
Analysis was carried out to assess actual decommissioning activity in 2015 on the UKCS, outlined in Figure 1
below. All of the planned activity was undertaken last year totalling 1.1 billion.
Total
50
17
Mattresses decommissioned
575
5,886 tonnes
357 kilometres
13
34
10
5.
The North Sea decommissioning market does not end at the median line and, as such, forecast activity on
both the UK and Norwegian Continental Shelves has been compiled to provide a more complete overview. The
following sections focus on specific areas of decommissioning activity. A great opportunity exists for the supply
chain offering decommissioning services. However, companies must be able to compete successfully for this
work in a global marketplace on quality, efficiency and cost, while maintaining focus on high environmental and
safety standards.
In total, this report captures data on 186 decommissioning projects across the UK (153) and Norway (33) Continental
Shelves11. Fifty-two of these projects are new to this years report due to the survey timeframe shifting to 2016 to
202512; some projects being brought forward in response to the low oil price environment; or estimates only now
becoming available. Seventeen projects have been postponed since last years survey to outside the timeframe as
operators have successfully extended field life.
It should be noted that the peaks of activity over the next decade shown in the following sections are likely to
smooth out over the years. This is because decommissioning activities tend to be spread over a number of years,
but for the purposes of this survey operators will often select a specific year for particular work to be undertaken.
Over the next decade, forecast activity on the UKCS is significantly higher than on the Norwegian Continental
Shelf. This reflects the relative maturity of the two shelves, with more fields reaching the end of their life in the UK.
Project is defined by the operator and can range from a single well for P&A to multi-platforms.
The 2015 survey covers the timeframe 2015 to 2024 and the 2016 survey covers the timeframe 2016 to 2025.
13
Guidelines on the Abandonment of Wells and Qualification of Materials for Abandonment are available to download at
www.oilandgasuk.co.uk/product/op105 and www.oilandgasuk.co.uk/product/op109
14
See www.legislation.gov.uk/uksi/1996/913/made
15
See NORSOK Standard D-010 Well Integrity in Drilling and Well Operations, (Rev.4 June 2013) at http://bit.ly/20BWqdD
11
12
12
The region with the highest number of wells of all types forecast for P&A within the survey timeframe is the
central North Sea where 35 per cent (644) of the wells are located. The region with the least amount of activity is
the Norwegian Continental Shelf where 362 wells are due to be plugged and abandoned of which there is only a
single well in the Norwegian Sea.
Figure 2: Combined Well P&A Forecast for the UK and Norwegian Continental Shelves
CNS - Platform Wells
NNS and W o S - Platform Wells
SNS and Irish Sea - Platform Wells
NCS - Platform Wells
250
Increased Uncertainty
in Forecasts
200
Number of Wells
150
100
6
50
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
There are a variety of factors that affect the timing of well P&A activity, including but not limited to changes to the
CoP date, alignment of well activity with other fields, available rig slots and the availability of capital to carry out
the work. Where the following forecasts by region indicate high peaks in activity, Oil & Gas UK would expect these
to smooth out as operators further develop and define their projects.
13
140
120
Platform
Subsea Development
Suspended Subsea E&A Wells
Increased Uncertainty
in Forecasts
Number of Wells
100
80
60
40
20
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
14
The number of wells forecast for P&A over the next ten years in the northern North Sea and west of Shetland
has increased to 430 from 326 in the 2015 survey.
The addition of 81 platform wells and 23 subsea wells is due to two large platform removal projects and a
subsea project that now expect to carry out decommissioning earlier due to the challenges of operating in a low
oil price environment.
Seventy-three per cent of wells for P&A in these regions are platform wells.
Forty-eight wells are forecast to be plugged and abandoned in 2016, with an annual average of 65 wells between
2016 and 2018.
4
As several P&A campaigns are likely to start earlier to take advantage of current low rig rates, 80 more wells are
expected in the near term (2016 to 2018).
Activity is forecast to spike at 79 wells in 2023 due to the three new projects in the northern North Sea.
140
Platform
Subsea Development
Suspended Subsea E&A Wells
120
Increased Uncertainty
in Forecasts
Number of Wells
100
80
60
40
20
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
Total
1,074
52%
CNS
644
37%
NNS and W o S
430
73%
15
Platform
Subsea Development
Suspended Subsea E&A Wells
Increased Uncertainty
in Forecasts
70
Number of Wells
60
50
40
30
20
10
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
16
396
80%
Approximately 800 of the 3,800 wells that will eventually require decommissioning on the Norwegian Continental
Shelf have already been plugged and abandoned16. Of the remaining 3,000 wells, 12 per cent (362) are forecast to
be decommissioned between 2016 and 2025, rising from 284 reported earlier this year due to ten new projects
that lie at the end of the survey timeframe.
Eighty-five per cent of wells for P&A over the next decade are platform wells compared to 95 per cent forecast
in the last Norwegian Decommissioning Insight as the new projects have a higher proportion of subsea wells.
All of the well P&A activity is concentrated in the Norwegian North Sea region of the basin with the exception of
one suspended subsea E&A well in the Norwegian Sea.
Activity in the near term (2016 to 2020) has increased as the durations of a number of large P&A campaigns have
reduced in light of experience gained from previous activity.
Forty-eight wells are forecast to be plugged and abandoned in 2016, with an average of 41 wells per year from
2016 to 2020.
Activity is estimated to peak at 90 wells in 2025 due to the new projects included.
Figure 6: Number of Wells Forecast to be Plugged and Abandoned on the Norwegian Continental Shelf
100
Increased Uncertainty
in Forecasts
Platform Wells
Subsea Wells
90
80
Number of Wells
70
60
50
40
30
20
10
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
16
Total
362
85%
361
85%
Norwegian Sea
0%
Barents Sea
No activity
No activity
See Abandonment of Obsolete Wells and Installation on the Norwegian Continental Shelf; a Study into the Magnitude
and Technical and Economic Challenges, June 2014, University of Stavanger, at http://bit.ly/1m8jpNW
17
Rig Type
There are a number of methods that can be used for well P&A and the rig type will primarily depend on the well type
and water depth. In some instances, the availability of well P&A technologies could remove the requirement for a
rig altogether. For example, a low-cost method of well P&A without the requirement of a rig was recently trialled
onshore by Centrica in Canada in a collaboration with Interwell P&A, BP, Statoil, and the Norwegian Research
Council. The new technology uses a thermite plug to seal off the well by melting both the well components and the
rock formation around them to recreate the cap rock. The trial results demonstrated that this technology could
potentially reduce well P&A costs in the North Sea by more than 50 per cent.
Platform wells are typically plugged and abandoned in phases. The first phase can be rig-less and uses lower cost
methods such as wireline, coil tubing, or a hydraulic workover unit. This is followed by the second and third phases
that are more likely to require a rig.
For platform wells on the central and northern North Sea and west of Shetland, and the Norwegian Continental
Shelf, 86 and 68 per cent, respectively, will be plugged and abandoned using an integral rig.
Modular rigs are also popular for platform well P&A in Norway, although most of the wells using this rig type fall
outside the survey timeframe.
For operators planning to use an integral rig for platform well P&A, the opportunity exists for alternative
approaches that preclude the use of the platforms existing drilling derrick, which can prove challenging and
expensive to upgrade.
In the southern North Sea and Irish Sea, the majority (64 per cent) of platform wells will be plugged and
abandoned using a standalone jack-up rig.
Operators are also considering rig-less, lower cost solutions to well P&A. For example, in the southern North Sea
and Irish Sea, 30 per cent of platform wells are forecast to use rig-less methods such as coil tubing and wireline.
For subsea wells, a standalone jack-up rig will be used for 98 per cent of wells on the Norwegian Continental
Shelf and 70 per cent on the southern North Sea and Irish Sea.
In the central and northern North Sea and west of Shetland, 63 per cent will use a semi-submersible rig for
subsea well P&A due to the greater water depths.
For a greater proportion of subsea wells, the rig type has not yet been determined as operators consider
alternative solutions (25 per cent in the southern North Sea and Irish Sea and 19 per cent in the central and
northern North Sea and est of Shetland).
18
Figure 7: Forecast Rig Type for Well Plugging and Abandonment on the
UK and Norwegian Continental Shelves from 2016 to 2025
Jack-Up Rig
9%
Rig-Less Intervention
3%
4
Integral Rig
86%
Semi-Submersible Rig
63%
Rig-Less Intervention
30%
7
Rig-Less Intervention
5%
Jack-Up Rig
64%
Jack-Up Rig
70%
Modular Rig
11%
Jack-Up Rig
21%
Integral Rig
68%
Jack-Up Rig
98%
19
20
Figure 8: Combined Facilities Making Safe and Topside Preparation Forecast for the
UK and Norwegian Continental Shelves
Norwegian Continental Shelf
Northern North Sea and West of Shetlands
120
Increased Uncertainty
in Forecasts
100
80
60
40
20
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
Making Safe
Preparation
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Figure 9: Combined Pipelines Making Safe Forecast for the UK and Norwegian Continental Shelves
1,400
Kilometres of Pipeline
1,200
Increased Uncertainty
in Forecasts
1,000
9
800
600
400
200
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
21
Making Safe
Increased Uncertainty
in Forecasts
Topside Preparation
70
60
50
40
30
20
10
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
22
383
26 platforms
2 FPSOs
Topside preparation
406
29 platforms
1 FPSO
Figure 11: Forecast Length of Pipelines for Making Safe in the Central and Northern North Sea
Increased Uncertainty
in Forecasts
700
Kilometres of Pipeline
600
500
400
300
200
100
7
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
23
Increased Uncertainty
in Forecasts
Making Safe
Topsides Preparation
16
14
12
10
8
6
4
2
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
24
Number of Platforms
2016 to 2025
83
38 NUIs
32 manned platforms
Figure 13: Forecast Length of Pipelines for Making Safe in the Southern North Sea and Irish Sea
700
Increased Uncertainty
in Forecasts
600
Kilometres of Pipeline
500
400
300
4
200
100
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Operators forecast that 108 topside modules on 13 platforms and 2 FPSOs will be made safe in preparation for
removal over the next ten years.
Topside preparation is slightly higher with a forecast of 111 topside modules on 14 platforms and 2 FPSOs, as
making safe work has already been carried out on one platform.
The bulk of work is planned between 2019 and 2023, peaking at over 40 topside modules in 2023.
Just over 350 kilometres of pipeline are forecast for making safe on the Norwegian Continental Shelf over the
next decade. All of this activity is in the Norwegian North Sea.
Activity will vary significantly year-on-year, peaking at 120 kilometres in 2020.
Forecast pipeline making safe activity in the Norwegian North Sea region of the Norwegian Continental Shelf
has increased since estimates made last year as ten new projects are captured.
The bulk of the pipeline decommissioning activity associated with these projects however lies outside the
survey timeframe.
In contrast to the 2015 report, no pipeline decommissioning activity is forecast in the Norwegian Sea due to the
deferral of a subsea project.
25
Figure 14: Forecast Number of Topside Modules for Making Safe and Topside Preparation
on the Norwegian Continental Shelf
45
40
Increased Uncertainty
in Forecasts
35
30
25
20
15
10
5
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
26
Topside Preparation
2016 to 2025
Norwegian Sea
No activity
No activity
Barents Sea
No activity
No activity
Figure 15: Forecast Length of Pipelines for Making Safe on the Norwegian Continental Shelf
140
Increased Uncertainty
in Forecasts
120
Kilometres of Pipeline
100
80
60
40
20
5
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
354
Norwegian Sea
No activity
Barents Sea
No activity
17
27
For the substructure, the removal method depends on the type, weight and configuration. The substructures
to be decommissioned in the southern North Sea and Irish Sea are shallow-water jackets that typically weigh
less than 2,000 tonnes and are usually deployed in water depths of 55 metres or less so they may use a
single-lift removal method.
For larger substructures (barge-launched and some self-floaters), the jacket may be cut into smaller sections in situ
and removed in segments. These more complex projects are typically located in the central and northern North
Sea and on the Norwegian Continental Shelf. The decommissioning sector continues to innovate in developing
existing and new cutting technology to undertake this task.
Operators forecast that over 652,000 tonnes of topsides from 109 platforms are to be removed from the UK and
Norwegian Continental Shelves over the next decade.
While the majority of these platforms are located in the southern North Sea and Irish Sea (61 per cent), the area
with the greatest amount (40 per cent) to be removed by weight is the northern North Sea at over 262,000 tonnes.
This reflects the size of platforms in this region.
Topside removal activity in the near term (2016 to 2020) is lower with between 15,000 and 80,000 tonnes forecast
to be removed each year. This rises to 60,000 to 128,000 tonnes per annum from 2021 to 2025.
Considering the forecast for substructure removal, Figure 17 opposite shows that 316,272 tonnes of substructure
associated with 100 platforms are forecast to be removed between 2016 and 2025. Just over 30 per cent of this
weight comes from the northern North Sea region (96,737 tonnes).
Substructure removal on the UKCS is forecast to begin in 2017, while activity on the Norwegian Continental Shelf
is expected to start later in 2019. Again, substructure removal is lower in the near term (2017 to 2020) ramping
up to a peak of just under 60,000 tonnes in 2025. Although not captured in the dataset, activity beyond 2025
is likely to remain high as there are a number of projects that have removal activity scheduled for outside the
survey timeframe.
Overall, Figures 16 and 17 show that across the UK and Norway there will be decommissioning work available for
the supply chain in every year, although no single region anticipates a consistent stream of activity with fluctuations
from year to year and area to area. All of the activity on the Norwegian Continental Shelf is concentrated in the
Norwegian North Sea region.
A significant amount of work for both topside and substructure removal is yet to be contracted out, as demonstrated
in the following sections. This provides a significant opportunity for the supply chain to bid for this work as it
becomes available.
It should be noted that in the survey operators typically indicate a single year for removal activity, but removal
contracts commonly include a time window of several years in which the activity must take place.
28
Figure 16: Combined Topside Removal Forecast for the UK and Norwegian Continental Shelves
140,000
120,000
Increased Uncertainty
in Forecasts
Tonnes to be Removed
100,000
80,000
60,000
4
40,000
20,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Figure 17: Combined Substructure Removal Forecast for the UK and Norwegian Continental Shelves
70,000
60,000
Increased Uncertainty
in Forecasts
Tonnes to be Removed
50,000
40,000
30,000
20,000
10,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
29
30
Figure 18: Uncontracted Topside Removal Forecast in the Central and Northern North Sea
and West of Shetland 2016 to 2025
80,000
Increased Uncertainty
in Forecasts
70,000
Tonnes to be Removed
60,000
50,000
40,000
30,000
20,000
10,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Topside Removal
Total
449,260
Contracted activity
119,880
5 platforms
Uncontracted activity
329,380
23 platforms
Figure 19: Uncontracted Substructure Removal Forecast in the Central and Northern North Sea
and West of Shetland 2016 to 2025
50,000
Increased Uncertainty
in Forecasts
45,000
Tonnes to be Removed
40,000
35,000
30,000
25,000
20,000
15,000
10,000
5,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Substructure Removal
Total
167,793
21 platforms
Contracted activity
21,000
2 platforms
Uncontracted activity
146,793
19 platforms
31
32
Figure 20: Forecast Number of Topside Modules and Topside Weight to be Removed in the Southern North Sea
and Irish Sea Split by Work Already Contracted
Topside Weight - Work Not Yet Contracted
18,000
16
Increased Uncertainty
in Forecasts
16,000
12
14,000
Tonnes to be Removed
14
10
12,000
10,000
8,000
6,000
4,000
20,000
2,000
0
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Topside Removal
Total
90,260
83 modules on 67 platforms
Contracted activity
3,510
9 platforms
Uncontracted activity
85,510
57 platforms
Not defined
1,240
1 platform
Figure 21: Forecast Substructure Weight to be Removed in the Southern North Sea
and Irish Sea Split by Work Already Contracted
14,000
12,000
Tonnes to be Removed
Increased Uncertainty
in Forecasts
Contracted Out
10,000
8,000
6,000
4,000
2,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
Substructure Removal
Total
63,745
67 platforms
Contracted activity
6,125
9 platforms
Uncontracted activity
56,770
57 platforms
Not defined
850
1 platform
33
40,000
Tonnes to be Removed
45
Topside Weight
Topside Modules
Increased Uncertainty
in Forecasts
40
35,000
35
30,000
30
25,000
25
20,000
20
15,000
15
10,000
10
5,000
0
2016
34
45,000
2017
2018
2019
2020
2021
2022
2023
2024
2025
Topside Removal
112,612
Norwegian Sea
No activity
No activity
Barents Sea
No activity
No activity
Figure 23: Forecast Substructure Weight to be Removed on the Norwegian Continental Shelf
35,000
Increased Uncertainty
in Forecasts
30,000
Tonnes to be Removed
25,000
20,000
15,000
10,000
5,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Substructure Removal
84,734
12 platforms
Norwegian Sea
No activity
No activity
Barents Sea
No activity
No activity
35
36
Figure 24: Forecast for Mattress and other Subsea Infrastructure Decommissioning on the
UK and Norwegian Continental Shelves
2,500
Increased Uncertainty
in Forecasts
2,000
1,500
1,000
4
500
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
18,000
16,000
14,000
6
Norwegian Continental Shelf
Increased Uncertainty
in Forecasts
12,000
10,000
8,000
6,000
4,000
2,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
5,979
56,714
1,162
1,697
4,526
188
No activity
No activity
4,268
1,745
No activity
No activity
37
1,800
1,600
180
Trunklines
Other Pipelines
Increased Uncertainty
in Forecasts
Umbilicals
160
140
1,400
120
1,200
100
1,000
80
800
60
600
Number of Pipelines
2,000
40
400
20
200
0
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
Trunklines are pipelines with a diameter greater than 14 inches and a length in excess of 18 kilometres. Umbilicals are
utility support pipelines.
18
38
Operators plan to decommission 580 pipelines with a total length of 3,700 kilometres from these regions over
the next decade.
Around 25 kilometres of pipeline are forecast to be decommissioned in 2016, rising to an average of over
300 kilometres per year between 2018 and 2022.
Activity is expected to peak at over 1,000 kilometres in 2024.
The majority of this activity involves inter-field pipelines connecting fields to host facilities, although some
import/export lines are included.
Pipeline decommissioning activity is one of the later activities in a decommissioning project and there is therefore
a high degree of uncertainty in the timing.
Figure 26: Forecast of Pipeline Decommissioning Activity in the Central and Northern North Sea
and West of Shetland
1,200
Umbilicals
Other Pipelines
Trunklines
1,000
Increased Uncertainty
in Forecasts
800
Total Length (km)
600
8
400
200
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
Pipeline Decommissioning
2016 to 2025
Pipeline Decommissioning
(Kilometres) 2016 to 2025
Total
580
3,704
Umbilicals
221
1,027
Trunklines
68
1,117
Other pipelines
291
1,560
39
Umbilicals
Other Pipelines
Trunklines
700
Increased Uncertainty
in Forecasts
600
500
400
300
200
100
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
40
Pipeline Decommissioning
2016 to 2025
Pipeline Decommissioning
(Kilometres) 2016 to 2025
Total
200
3,426
Umbilicals
46
443
Trunklines
21
1,603
Other pipelines
133
1,380
Sixty-seven pipelines with a total length of 297 kilometres will be decommissioned from 2016 to 2025.
The majority are inter-field connectors that link fields to host facilities.
Ten kilometres of pipeline are to be decommissioned in 2016, with activity forecast to peak at over 100 kilometres
in 2022.
3
For many of the projects included in the survey, pipeline decommissioning lies outside the timeframe.
Figure 28: Forecast of Pipeline Decommissioning Activity on the Norwegian Continental Shelf
120
4
Umbilicals
Other Pipelines
Trunklines
Increased Uncertainty
in Forecasts
100
80
60
40
20
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Pipeline Decommissioning
2016 to 2025
Pipeline Decommissioning
(Kilometres) 2016 to 2025
67
297
Umbilicals
28
Trunklines
39
45
Other pipelines
23
224
Norwegian Sea
No activity
No activity
Barents Sea
No activity
No activity
Total
Norwegian
North Sea
41
19
20
42
Figure 29: Combined Forecast of Tonnage Coming Onshore for Recycling and Disposal
on the UK and Norwegian Continental Shelves
250,000
200,000
Increased Uncertainty
in Forecasts
3
150,000
4
100,000
50,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
43
120,000
100,000
80,000
60,000
40,000
20,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
44
369,190
360,456
Over 164,800 tonnes are to come onshore for recycling and disposal in these regions between 2016 and 2025.
This is an increase of close to 37,500 tonnes compared to the 2015 report, as new projects are included for the
first time.
The spread of activity again correlates with topside and substructure removal, peaking in 2021 at 28,200 tonnes.
3
Figure 31: Forecast of Tonnage Coming Onshore for Recycling and Disposal
in the Southern North Sea and Irish Sea
Increased Uncertainty
in Forecasts
30,000
25,000
5
20,000
15,000
10,000
7
5,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Southern North Sea and Irish Sea Onshore Recycling and Disposal (Tonnes) 2016 to 2025
164,834
45
45,000
40,000
35,000
30,000
25,000
20,000
15,000
10,000
5,000
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
46
The 2015 survey covered the timeframe 2015 to 2024, whereas the 2016 survey covers the period 2016 to 2025.
An Asset Retirement Obligation (ARO) is a liability associated with the eventual retirement of a fixed asset.
23
A comparative assessment is used to compare options, examine differences and identify the most preferred option in
the development of decommissioning programmes for:
a) All installations for which derogation is sought under OSPAR Decision 98/31
b) All pipelines being decommissioned under the Petroleum Act 1998
c) All drill cuttings piles that are not screened-out at Stage 1 of OSPAR Recommendation 2006/51
24
Further information on the Association for the Advancement of Cost Engineering (AACE) classification scheme is
available at http://web.aacei.org
21
22
47
None of the UKCS projects included in the survey are reported as Class 1. These would have project definition
levels of 50 to 100 per cent with many of the activities already in execution. Projects that were classified as Class
1 in the 2015 report have now been completed and no new projects have moved into this category. Only two
projects were reported as Class 2, where project definition is between 30 and 70 per cent and is either at the
contracting stage or being executed.
Figure 33 shows the percentage of annual expenditure for projects on the UKCS split by AACE classification.
Sixty-nine per cent of expenditure in 2016 comes from the large number of Class 4 or 5 projects, each contributing
a small amount of expenditure, typically for operator project management or well P&A. Companies often start
well P&A while they develop and define the scopes of the other decommissioning activities.
Figure 33: AACE Cost Class Breakdown
100%
90%
80%
70%
60%
Class 5
Class 4
50%
Class 3
Class 2
40%
Class 1
30%
20%
10%
0%
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Source: Oil & Gas UK
48
Increased Uncertainty
in Forecasts
2,500
2,000
1,500
7
1,000
500
0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
2011
2012
2013
2014
2015
2016
Regional Breakdown26
Looking at the regional breakdown of UKCS decommissioning expenditure from 2016 to 2025, 53 per cent
(9.4 billion) is estimated to be spent in the central North Sea and 30 per cent (5.3 billion) in the northern North
Sea and west of Shetland. The remaining 17 per cent (3 billion) is allocated to the southern North Sea and Irish
Sea, of which over 90 per cent is concentrated in the southern North Sea.
This survey covers data from end-of-field-life decommissioning projects and does not include expenditure or activity
associated with mid-life decommissioning.
26
All forecasts by region and component are rounded and so the sum of them may not come to the total
forecast expenditure.
25
49
The higher proportion of expenditure in the central and northern North Sea regions reflects the number, size and
degree of complexity of projects in these regions. While the number of platforms to be removed is greater in the
southern North Sea and Irish Sea, these are typically much smaller installations that are simpler and therefore
cheaper to decommission.
Operators start planning for decommissioning far ahead of CoP. The complex decisions on the timing of CoP and
the subsequent schedule of decommissioning activity are made by the operator in conversation with industry
regulators and take many factors into account, including future recovery potential, tie-back opportunities to
existing infrastructure, oil price and the wider business environment.
Analysis has been carried out on the key changes that have taken place on the UKCS since publication of the 2015
report, looking at shifts in both CoP and forecast expenditure. This analysis has been split into two regions the
central and northern North Sea and west of Shetland, and the southern North Sea and Irish Sea.
Central and Northern North Sea and West of Shetland
Seventy-five per cent (114) of the projects on the UKCS are located in these regions. At an individual project
level, there have been significant shifts in the anticipated cost and timing of decommissioning projects since
forecasts were made a year ago, with the number of projects that have been delayed replaced by those that have
accelerated decommissioning.
There has been an increase of 500 million from existing projects that now have a greater proportion of expenditure
within the survey timeframe, plus 24 new projects are now expected to be decommissioned earlier bringing a
further 1.5 billion of expenditure into the survey timeframe. However, this 2 billion increase has been partially
offset by an expected fall in decommissioning costs by 500 million since last year and 14 project deferrals moving
an additional 1 billion outside of the survey timeframe. Overall expenditure has increased by a net 500 million
to 14.6 billion.
Fourteen projects have been deferred where operators have succeeded in extending field life in line with the
statutory obligation to achieve MER UK. These projects range from small subsea tie-backs to larger fields with
platforms and multiple subsea tie-backs.
By contrast, 24 new projects are included because CoP and decommissioning dates have moved forward in light
of the low oil price environment and a shift in survey timeframe. Many of these are small-scale projects involving
single suspended subsea E&A wells or small subsea tie-backs. There are, however, some large new projects
involving multiple platform removals.
The associated expenditure has led to an increase in the annual expenditure forecast from 2016 to 2020 in
comparison to last year (shown in Figure 35 opposite). By contrast, as several projects have deferred
decommissioning activity, the peak year of expenditure has shifted from 2022 to 2024.
For projects included in both this years and last years surveys, the majority (87) of assets report no change in
planned CoP, while 57 have brought their expected date forward. Operators have cited the low oil price and the
knock-on effect of host facilities shutting down earlier than anticipated as the principal reasons for accelerated
CoP dates. By contrast, for 19 assets, CoP dates have been postponed due to improved economic outlook or
decommissioning being delayed to align with other assets27.
27
T he number of assets is higher than the number of projects as operators can assign different
CoP dates for assets within a project.
50
2,500
Increased Uncertainty
in Forecasts
2016 Survey
2015 Survey
2,000
3
1,500
1,000
500
0
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
For those projects included in this years and last years survey, there has been no change in planned CoP for the
majority (48) of assets, although dates have changed for 29 assets, with 15 brought forward and 14 deferred.
Increased costs to tie fields back to host facilities, the accelerating CoPs of host facilities and poor results on wells
that were drilled to extend field life have all been cited as reasons for earlier CoP.
28
Overall, Figure 36 shows that near-term expenditure (2016 to 2019) in the southern North Sea and Irish Sea is
lower than was forecast a year ago. This can be attributed to the deferral of some activity to preserve cash-flow
in the current business climate, larger campaigns spreading their activities across the decade, and lower unit costs
for well P&A and removals. The marked increase in forecast expenditure in the latter part of the decade is due to
the inclusion of new projects to this years report.
Figure 36: Comparison of Forecast Decommissioning Expenditure in the Southern North Sea and Irish Sea
500
2016 Survey
2015 Survey
450
Increased Uncertainty
in Forecasts
400
350
300
250
200
150
100
50
0
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
52
Owners costs are expenses incurred to operate the decommissioning programme post-CoP through to completion.
These costs include management of the facility in both the pre-NUI and NUI stages. This covers expenditure
associated with logistics, the decommissioning team itself, deck crew, power generation, platform services,
integrity management (inspection and maintenance) and specialist services.
As shown in Figure 37 overleaf, owners costs are forecast to remain relatively stable across the timeframe, with
an average annual expenditure of 340 million per year. Expenditure is forecast to increase towards the end of the
survey timeframe as activity increases, peaking at 450 million in 2025.
However, owners costs over the next decade are 300 million less than those outlined in the 2015 report,
despite the increase in the level of activity and overall expenditure in this years survey. This reflects efficiency
improvements seen across the industry being projected onto future estimates of facility running costs for
decommissioning projects.
Well P&A costs, meanwhile, include rig upgrades, studies to support wells programmes, project management,
operations support, and specialist services such as wireline or conductor recovery. This expenditure is forecast to
peak in 2024 at almost 1.2 billion, with an average annual spend of just over 820 million over the next ten years.
This compares with an average annual expenditure of 770 million in the 2015 report and 640 million in the
2014 report.
Removal and other associated activity include expenditure on:
Making safe
Topsides preparation
Removal of topsides, substructures and subsea infrastructure
Pipeline decommissioning
Transportation and onshore-load in
Disposal
Recycling
Site remediation and monitoring
Expenditure from 2016 to 2025 associated with removal activities is forecast to be lower in the near term, rising
year-on-year from just under 300 million in 2016 to a peak of just over 900 million in 2024. Expenditure over the
decade has increased by 500 million compared to the 2015 report.
53
Figure 37: Total Forecast Decommissioning Expenditure on the UKCS by Work Breakdown Structure Category
3,000
2,500
2,000
1,500
1,000
500
0
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
3.4 billion
Well P&A
8.3 billion
Removal
3.4 billion
2.6 billion
In line with previous reports, well P&A remains the largest category of forecast expenditure, accounting for
47 per cent (8.3 billion) of total forecast expenditure over the next ten years. Owners costs and expenditure
associated with topsides, substructure and subsea infrastructure removal each account for 19 per cent of total
forecast expenditure at 3.4 billion each. For subsea projects, well P&A accounts for 65 per cent of the total,
compared with 8 per cent for owners costs (4 billion total expenditure on subsea projects).
Breaking this down further, of the 8.3 billion expenditure associated with well P&A, 57 per cent (4.7 billion) is in
the central North Sea, an increase from the 4 billion forecast in 2015 due to the additional subsea wells included
that are more expensive to plug and abandon.
Ninety-seven per cent (3.3 billion) of the total owners costs are concentrated in the central and northern North
Sea and west of Shetland. In these areas, platforms are typically manned resulting in much higher facility running
costs. Projects are also larger and more complex, with, in turn, higher operator project management costs. The
owners costs account for 31 per cent (2.5 billion) of expenditure on platform removal projects in these areas
compared to four per cent (118 million) in the southern North Sea and Irish Sea.
54
Figure 38 overleaf breaks down the total forecast expenditure of 17.6 billion by Work Breakdown Structure
component proportion for different project types:
It is important to note that the graphs only include the breakdown of expenditure that falls within 2016 to 2025.
Decommissioning projects can span many years and therefore some expenditure associated with a project may
fall outside the survey timeframe.
There are 13 FPSOs forecast to be decommissioned on the UKCS over the next decade, 12 of which are located in
the central North Sea. Decommissioning a field serviced by an FPSO primarily involves subsea activity, although
some expenditure is also associated with disconnecting the FPSO. Following disconnection, FPSOs are typically
relocated or sold for reuse or recycling. These activities are reflected in the breakdown of expenditure seen in
Figure 38. The total forecast decommissioning expenditure for fields serviced by an FPSO is 2.6 billion.
29
Total expenditure for platform removal projects, FPSO projects and subsea projects is 17.3 billion. This does not equal
total forecast expenditure because some projects do not fall clearly into one category and therefore have not been
used to calculate the Work Breakdown Structure percentage for individual project types.
55
Figure 38: Total Forecast Decommissioning Expenditure on the UKCS by Work Breakdown Structure
Component and Project Type from 2016 to 2025
Subsea Projects
Monitoring
100%
100%
Site Remediation
Removals*: 19%
80%
70%
Substructure Removal
Topsides Removal
60%
Topsides Preparation
50%
90%
Removals*: 10%
90%
80%
70%
60%
50%
40%
Subsea Wells
Platform Wells
30%
Facility Running/Owner
Costs
Operator Project
Management
20%
10%
30%
20%
* Indicates expenditure
10%
0%
100%
Owners' Costs: 8%
0%
40%
Monitoring
100%
Site Remediation
Site Remediation
Removals*: 23%
80%
70%
Substructure Removal
60%
Topsides Removal
Topsides Preparation
50%
40%
Subsea Wells
30%
Platform Wells
20%
Facility Running/Owner
costs
Operator Project
Management
10%
* Indicates expenditure
90%
Proportion of Total Expenditure for Each Work
Breakdown Structure Component
90%
80%
Removals*: 27%
70%
100%
FPSO
Vessel Projects
Topsides Removal
Topsides Preparation
50%
Facility/Pipeline Mak
Safe
Subsea Wells
40%
Platform Wells
30%
20%
10%
56
80%
70%
60%
50%
40%
30%
20%
90%
Site Remediation
Subsea Infrastructure
Removals*: 13%
80%
Removals*: 13%
70%
Subsea Infrastructure
60%
50%
40%
Topsides Removal
Topsides Removal
Topsides Preparation
Topsides Preparation
Subsea Wells
Subsea Wells
20%
10%
0%
0%
Operator Project
Management
* Indicates expenditure
Owners' Costs: 12%
Substructure Removal
Substructure Removal
Platform Wells
30%
10%
Owners' Costs: 4%
0%
Site Remediation
Monitoring
Facility Running/Own
Costs
Operator Project
Management
* Indicates expenditure
Monitoring
90%
100%
Subsea Infrastructur
Substructure Remov
60%
0%
Platform Wells
Facility Running/Owner Costs
Operator Project
Management
* Indicates expenditure
UKCS
Total
Owners' costs
3.3 billion
118 million
3.4 billion
Well P&A
1.5 billion
8.3 billion
760 million
137 million
897 million
89 million
192 million
281 million
Topside removal
1.5 billion
104 million
1.6 billion
Substructure removal
544 million
503 million
1 billion
Mattress decommissioning
and other subsea
infrastructure removal
613 million
149 million
762 million
Pipeline decommissioning
847 million
193 million
1 billion
Onshore recycling
and disposal
161 million
53 million
214 million
Site remediation
94 million
16 million
110 million
Monitoring
21 million
5 million
26 million
The Norwegian Petroleum Directorate estimates that close to 1 billion will be spent on decommissioning in 2016 on
the Norwegian Continental Shelf30 and that annual expenditure will average at around 1 billion each year until 2020.
A detailed breakdown of forecast expenditure by decommissioning component is not available for the Norwegian
Continental Shelf, and operators have instead indicated the proportion of decommissioning expenditure associated
with the following four categories for 10 out of 14 removal projects within the survey timeframe.
30
31
With the exception of one suspended subsea E&A well in the Norwegian Sea, all of the decommissioning activity
over the next decade is located in the Norwegian North Sea region. As illustrated in Figure 39, the proportion of
forecast expenditure attributed to each Work Breakdown Structure component varies significantly across the
10 out of 14 platform removal projects that provided data.
Figure 39: Total Forecast Decommissioning Expenditure on the Norwegian Continental Shelf
by Work Breakdown Structure Component for Platform Removal Projects
80%
70%
60%
50%
40%
30%
20%
10%
0%
Owners' Costs
Well P&A
Topside Removal
Substructure Removal
58
Average
Range
Owners' costs
11%
3-32%
Well P&A
56%
33-75%
Topside removal
19%
6-33%
Substructure removal
12%
5-16%
7.
The cost of well P&A depends on a number of factors that differ across the regions of the North Sea. These include
water depth, weather, reservoir type, age and, in some cases, measures that may be required to prevent well
collapse caused by depressurisation.
The cost estimates included in this report vary significantly in their degree of maturity. While some are informed
by previous experience and data from well P&A work that has been carried out, other estimates are at an earlier
stage in their development and are inherently more uncertain.
On the UKCS, data from previous Decommissioning Insight reports have been used to compare expenditure
forecasts for well P&A activity. This analysis shown in Figures 40 and 41 overleaf considers the average and range
in well P&A forecasts for each survey year from 2011 to 2016. Platform well P&A is typically cheaper than for both
types of subsea wells as it is usually not subject to the same weather constraints or rig requirements and can also
be carried out more effectively in batches or campaigns, allowing the operator to share mobilisation costs and
other efficiency gains across a number of wells. Furthermore, experienced gained from ongoing platform well P&A
has helped to inform future forecasts.
For the first time, operators on the Norwegian Continental Shelf were surveyed on their forecast well P&A costs
for projects within the survey timeframe. Figure 42 on p62 shows the average and range in cost forecasts for
platform and subsea wells in this region.
Operators have advised that wells at the low end of the cost range are typically simple, rig-less P&As, using
wireline, pumping or crane jacks where the reservoir may already have been isolated. Wells at the top end are
more complex, rig-based P&As, with challenging access and cementing. They may require retrieval of tubing and
casing, milling and cement repairs (see section 5.1 on p18 on rig type for well P&A).
59
Sixty-three per cent of subsea wells in these regions plan to use a semi-submersible rig to carry out P&A. The
recent fall in rig rates could explain the fall in forecast unit costs for these wells.
However, rig rates are only one factor that impacts the cost of well P&A. The number of days to plug and abandon
a well is also an important factor, and operators have advised that expected well P&A durations have been
revised upwards for some large subsea projects based on data from completed projects and further studies on
the condition of the well stock.
50
45
40
35
30
25
20
15
10
5
Platform Wells
* Data cannot be split out for subsea E&A and development wells for 2011
Well P&A
60
2016
2015
2014
2013
2012
2011*
2016
2015
2014
2013
2012
2011*
2016
2015
2014
2013
2012
0
2011
Figure 40: Historical Variation in Well Plugging and Abandonment Cost Forecasts
in the Central and Northern North Sea and West of Shetland
Platform wells
4.1 million
4.1 million
7.8 million
6.2 million
9.9 million
10.2 million
The average forecast cost per well P&A in these regions has fallen to 2 million per platform well,
5.6 million per suspended E&A well and 7.6 million per subsea development well. The reason for
the decrease is two fold: wells included in both survey years are expected to be cheaper to perform
than they were a year ago and the new wells included in the survey have cost forecasts at the low end.
Operators have indicated that reduced well P&A durations and lower rig rates have contributed to the reduction
in forecast unit costs. Well P&A durations have reduced over the course of ongoing campaigns, reflected in
lower cost estimates for future wells.
Day-rates for jack-up rigs have fallen by over 40 per cent over the last year the lower rig rates are likely to be
reflected in the cost estimates as 64 per cent of platform wells and 70 per cent of subsea wells in these regions
plan to use a jack-up rig for well P&A.
Figure 41: Historical Variation in Well Plugging and Abandonment Cost Forecasts
in the Southern North Sea and Irish Sea
50
Average Forecast Cost Platform Well
45
40
35
30
25
20
15
10
5
Platform Wells
* Data cannot be split out for subsea E&A and development wells for 2011
2016
2015
2014
2013
2012
2011*
2016
2015
2014
2013
2012
2011*
2016
2015
2014
2013
2012
2011
Well P&A
Platform wells
3 million
2 million
8.8 million
5.6 million
9.6 million
7.6 million
61
30
25
20
15
10
0
Platform Well P&A
62
Well P&A
Platform wells
10 million
Subsea wells
16.1 million
The scope of work associated with making safe is believed to be broadly similar across different platform types.
Although activity will typically take longer on larger structures, the fixed costs will be similar, increasing the cost
per tonne forecasts for smaller, lighter structures commonly found in the southern North Sea and Irish Sea.
Many of the installations in the southern North Sea are smaller NUIs. NUIs require transport by helicopter or an
accommodation vessel for a team to carry out making safe activities, adding further cost.
Expenditure at the lower end of the range is in line with those seen in the central and northern North Sea and est
of Shetland areas and is likely to be associated with larger, manned platforms.
The average cost per tonne for making safe is 1,200 in the southern North Sea and Irish Sea compared to just
490 in the central and northern North Sea and est of Shetland.
The range of cost per tonne forecasts has increased significantly since the 2015 report as new projects fall at the
high end of the range.
5
Figure 43: Historical Variation in the Making Safe Cost per Tonne Forecasts for Topsides on the UKCS
3,500
3,000
2,500
7
2,000
1,500
8
1,000
500
9
0
2015
2016
2015
2016
63
64
Figure 44: Historical Variation in the Removal Cost per Tonne Forecasts for Topsides
and Substructures in the Central and Northern North Sea and West of Shetland
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
2011
2012
2013
2014
2015
2016
2011
Topside
2012
2013
2014
2015
2016
Substructure
Topsides
Substructures
65
Figure 45: Historical Variation in the Removal Cost per Tonne Forecasts for Topsides
and Substructures in the Southern North Sea and Irish Sea
Average Forecast Topside Removal Cost per Tonne
Average Forecast Substructure Removal Cost per Tonne
10,000
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000
0
2011
Topside and
Substructure
Topside
Substructure
Source: Oil & Gas UK
66
Topsides
4,600
2,600
Substructures
4,400
2,600
8. Appendices
Facility running/
owners' costs
Activities include logistics (aviation and marine), operations team, deck crew,
power generation, platform services, integrity management (inspection and
maintenance) and operations specialist services e.g. waste management.
Facilities/pipelines
'making safe'
Activities include operations (drain, flush, purge and vent), physical isolation
(de-energise, vent and drain), cleaning, pipeline pigging and waste management.
Topsides preparation
Topsides removal
32
Substructure removal
Topsides and
substructure onshore
recycling
Subsea infrastructure
(pipelines, umbilicals)
Site remediation
Monitoring
B.
The five estimate classes in the AACE Cost Estimation Classification Matrix are determined by level of project
definition with consideration to a set of secondary characteristics.
Primary
Characteristic
Estimate Class
68
Secondary Characteristic
Level of Project
Definition
End Usage Typical
(expressed as % of Purpose of Estimate
complete definition)
Methodology
Typical Estimating
Method
Expected Accuracy
Range Typical
Variation in Low and
High Range
L: -20% to -50%H:
+30% to +100%
Class 5
0% to 2%
Concept screening
Capacity factored,
parametric
models, judgement
or analogy
Class 4
1% to 15%
Study or feasibility
Equipment
factored or
parametric models
L: -15% to -30%H:
+20% to +50%
Class 3
10% to 40%
Budget
authorisation or
control
Semi-detailed unit
costs with assembly
level line items
L: -10% to -20%H:
+10% to +30%
Class 2
30% to 70%
Control or bid/
tender
L: -5% to -15%H:
+5% to +20%
Class 1
50% to 100%
Check estimate or
bid/tender
L: -3% to -10%H:
+3% to +15%
9. Glossary
AACE
Asset Retirement Obligations
Barge-launched jacket
Casing
Christmas tree
CNS
Coiled tubing
Comparative assessment
Cessation of Production
A large diameter pipe extending upwards from or beneath the seafloor to
the top of the well on the platform. The purpose of the conductor is to act
as a guide for drilling the well and a protective barrier from the elements
for the well casings and tubing during the life of the well.
A structure used to support crown blocks and drilling string of a rig.
Leaving infrastructure in place and carrying out appropriate work to ensure
that there is minimal risk to other sea users or the marine environment.
This could apply to any installed facilities on the seabed, such as pipelines,
manifolds, pipeline crossings and the footings of larger jackets.
Exploration and Appraisal Wells
Flexible flowlines usually transport hydrocarbons between subsea
infrastructure and the host platform or vessel. They are manufactured
from composite layers of steel wire and polymer sheathing that provide
protection and flexibility to the flowline.
69
FPSO
Lift-installed jackets
Making safe
Manifold
Mattresses
MER UK
NNS
A mill or similar downhole tool is used to remove casing in the well where
a barrier needs to be installed in case of pressure or potential movement
of hydrocarbons behind the casing. The objective is to prevent fluids
flowing into another formation or to the surface.
Rig designed in modules that can be lifted onto a platform by crane to be
erected on site.
Northern North Sea
NUI
OGA
Milling
Modular rig
Over-trawl surveys
Pig
70
Over-trawl surveys make sure the seabed is safe for normal fishing
activities to resume.
A device used to clean pipelines.
Piece-small
Production packer
Project estimate
Provisioning estimate
Reverse installation
Rigid pipelines
Risers
Satellite installations
Sea-fastening
Self-floaters
Single-lift
Semi-submersible rig
Shallow-water jackets
SNS
Spool
71
Subsea tie-back
Trunkline
Tubing
UKCS
Umbilical
Well-scale decontamination
Well P&A
Wellhead
Wireline
WoS
72
73
www.oilandgasuk.co.uk