Welding Quality Control Plan Req
Welding Quality Control Plan Req
Page 1 of 2
8/6/15
14. The methods, procedures, and log to track rejected lengths of weld by welder,
position, process, joint configuration, and piece number.
15. Standard procedures for identifying members distorted by welding and monitoring
methods for straightening members distorted by welding.
16. Fracture Control Plans which are applicable to the welding being performed.
WPS and PQR
17. Prequalified Welding Procedure Specifications (WPS), if applicable.
18. Documentation, when applicable, of Procedure Qualification Record (PQR) tests
within the allowable period of effectiveness including all worksheets.
19. Non-prequalified Welding Procedure Specifications (WPSs) supported by PQR
testing.
20. Documentation of the filler metal, flux, filler metal flux combination and
shielding gas certifications to be used in the work and documentation of
manufacturers recommended operating ranges.
NDT Other Than Visual Procedures
21. Written Practice of the NDT inspection personnel or firm.
22. Name of certifying authority and outside Level III, if applicable.
23. Names, qualifications, and documentation of certifications of NDT personnel to
be used to include level of certifications and expiration date.
24. List of NDT equipment, calibration procedures, frequencies and current
qualification/calibration documentation of equipment to be used.
25. Procedures, methods and frequencies for performing all required NDT as required
by the contract documents to include minimum amounts required.
26. Code of Safe Practices when Radiographic Testing (RT) is performed.
27. Copies of NDT report forms to be used.
After final approval of the WQCP, amended WQCP, or addendum, the Contractor shall submit
7 copies to the Engineer of the approved documents. A copy of the Engineer approved document
shall be available at each location where welding is to be performed.
It is expressly understood that the Engineer's approval of the Contractor's WQCP shall not relieve
the Contractor of any responsibility under the contract for the successful completion of the work
in conformance with the requirements of the plans and specifications. The Engineer's approval
shall not constitute a waiver of any requirement of the plans and specifications nor relieve the
Contractor of any obligation thereunder; and defective work, materials, and equipment may be
rejected notwithstanding approval of the WQCP.
Page 2 of 2
8/6/15