Method Statement For Backfilling Works
Method Statement For Backfilling Works
Page | 1
Method Statement
Backfilling will be done using two types of materials.( i.e. Existing excavated soil and sand). Only
the uncontaminated portions of the excavated soil were kept for this purpose and the rest of the
material was already disposed.
3. Backfilling execution
Backfilling will be executed in layers and the thickness of the layers shall be maximum 30 cm in
height.
Paint marks could be used on back of formwork/shoring surfaces to indicate the levels of each
layers.
A routine investigation of levels of layers will be carried out by the surveying crew.
Back filling material will be filled and appropriate water quantity specified by the laboratory test
report will be added. (The existing excavated soil to be used initially until the remaining quantity is
over and then onwards sand will be used until the completion of work)
Soil will be spread in layers in accordance to the layer thickness. Each layer will be compacted
either by plate or roller compactor depending on the size of the area to be filled.
At the end of each two layers of compacted soil the sand cone test shall be carried out to
determine the compaction percentage. And test will be conducted in 3 locations per each layer of
testing. The compacted (by submerging in water) sand layers sill be subjected to visual
inspection.
Section C: Inspections
The three phases of inspection are:
1. Initial Inspection checklist-01: The contractor will perform an initial inspection as soon as a bed
levels of the backfilling are prepared to receive the backfilling. Upon the readiness of the work,
contractor will submit an inspection request to the consultant for obtain the approval. This inspection
request will verify the following items.
a.
b.
c.
d.
2. Intermediate Inspections (Soil layers): Checklist-02 to Checklist-x : The contractor will perform an
initial inspection of the work i.e each compacted two soil layers and will conduct the sand cone test.
Upon the readiness of the work, contractor will submit an inspection request to the consultant for
obtain the approval.
Page | 2
Method Statement
3. Intermediate Inspections (Sand layers): Checklist-(x+1) to Checklist-y : The contractor will perform
an initial inspection (A visual inspection) of the work i.e each compacted two sand layers. Upon the
readiness of the work, contractor will submit an inspection request to the consultant for obtain the
approval.
4. Final Inspection (for final cleaning and leveling) Checklist-(y+1): The contractor, upon the
readiness of the work will submit an inspection request to the consultant for obtain the approval for
the final cleaning and to check the final levels of the backfill.
5. Approved shop drawings, concrete dimension drawings and coordinate drawings are pre-requisite
documents for performing a checklist, unless having a special consent from the engineer.
6. The successive work stages will be commenced only upon successfully obtaining the approval for
its predecessor work stage.
Section C: Safety
The entire works will be carried out as per the guidelines established in the Project Specific HSE Plan.
Utmost importance shall be given to safety of personnel and protection of services. It will be ensured that
the personnel involved are thoroughly aware of the Employer Safety regulations. To achieve the above the
following shall also be ensured:
Tool Box Meetings will be conducted before starting the works.
All personnel will be provided with suitable Personal Protective Equipment.
Proper and safe access will be provided for workmen to reach the work spot and carry out their
works safely.
Necessary and essential lighting and ventilation will be provided during the course work.