Engineering Management Summary Notes 2
Engineering Management Summary Notes 2
Bar charts
A planning tool listing the operations to be carried out on the left hand side of
the chart, and carrying a time schedule along the horizontal scale.
The start duration and the finish of each activity is shown as a line or bar.
A Gantt chart is constructed by firstly listing all the things that you can think
of that need to be done in a project. This could be quite a long list
Uses (plan, coordinate, and track specific tasks in a project.)
1.
2.
3.
Define only the sequences and inter relations between the activities.
The analysis of the diagram to produce a working schedule for the project
depends on the particular technique adopted.
A network is a project graph which clearly depicts the various operations
which has to be performed to complete a project and their inter-relationships.
Means of representing a plan so that it displays clearly the series of
operations, which must follow in order to complete the project. It also shows
clearly their inter-relationship and interdependence of the activities.
Each of these operations can often be carried out in a variety of different
ways by varying the amount of labor, number and size of gangs, working
hours, plant employed and other inputs,
4. Networks may have only one initial event with no predecessor and one
terminal event with no successor.
5. Arrows imply logical precedence only. Length and direction no significance.
6. At either end of the arrow must appear an event
Nodes network system (Precedence Diagramming Method)
Rules
1. All activities entering a node must be complete before any activity starts from
that node.
2. Activities are defined by their start and finish node.
3. When two activities are running in parallel, dummy activities are used to
distinguish between them. These dummy activities are logical restraints used
to maintain the logic of a network.
4. Dummy activities are also used when some activity is dependent on
completion of another activity.
5. All networks are constructed logically on the principle of dependency.
An event is a milestone or a point at which an operation, the activity, is
complete or another can start. Node or connector.
NETWORK ANALYSIS DIAGRAMS
Where two activities running in parallel start and finish at the same nodes a
dummy activity is inserted to enable a distinction to be made between them.
Merge nodes: Events into which a number of activities enter and one (or
several) leave.
Burst nodes: Events that have one (or more) entering activities generating a
number of emerging activities.