Manual Invertor TRIO 27.6
Manual Invertor TRIO 27.6
TRIO-20.0-TL / TRIO-27.6-TL
http://www.power-one.com
1
1 - Introduction and general information
Warranty and supply conditions
The warranty conditions are described in a special certificate supplied with the equipment. The warranty conditions are also considered to be valid if the customer complies with what is described in this
manual; any conditions departing from those described below must be
expressly agreed in the purchase order.
Power-one declares that the equipment is in conformity with the current provisions
of law in the European Economic Community and issues a DECLARATION OF CONFORMITY for it.
000002AG
-2-
Contents
Contents............................................................................................................................3
Reference number index.................................................................................................7
Graphical representation of references........................................................................8
Analytical index................................................................................................................9
The document and who it is for ..................................................................................13
Purpose and structure of the document................................................................................13
List of annexes . ....................................................................................................................13
Staff characteristics................................................................................................................13
2 - Characteristics.................................................................................17
General conditions........................................................................................................17
Models and range of equipment..................................................................................18
Identification of the equipment and the manufacturer...........................................................18
Overall dimensions................................................................................................................21
Tightening torques.................................................................................................................21
Efficiency curves............................................................................................................22
Power Derating...............................................................................................................23
Power reduction due to environmental conditions.................................................................23
Power reduction due to the input voltage..............................................................................23
Operating diagram.................................................................................................................26
Connection of several inverters together...............................................................................27
Notes on the sizing of the system..........................................................................................27
Functionality and components of the equipment . ................................................................28
Topographic diagram of the equipment.................................................................................29
000003BG
Protective devices.........................................................................................................31
Anti-Islanding.........................................................................................................................31
Ground fault in the photovoltaic panels.................................................................................31
String fuses............................................................................................................................31
Overvoltage surge arresters..................................................................................................31
Further protective devices.....................................................................................................31
-3-
Residual Risks................................................................................................................35
5 - Installation........................................................................................40
General conditions .......................................................................................................40
Environmental checks............................................................................................................41
Installations above 2000 metres............................................................................................41
Installation position.................................................................................................................42
Wall mounting.................................................................................................................43
Operations preparatory to PV generator connection................................................44
Checking the correct polarity of the strings...........................................................................44
Checking of leakage to ground of the photovoltaic generator...............................................44
Choice of differential protection downstream of the inverter.................................................44
000003BG
Communication card.....................................................................................................58
-4-
6 - Instruments......................................................................................69
General conditions .......................................................................................................69
Display and keypad.......................................................................................................70
Description of symbols and display fields..............................................................................70
Description of the keypad......................................................................................................72
7 - Operation..........................................................................................73
General conditions .......................................................................................................73
Monitoring and data transmission...............................................................................74
User interface mode...............................................................................................................74
Types of data available..........................................................................................................74
Commissioning..............................................................................................................75
LED behaviour................................................................................................................78
AUTOTEST procedure...................................................................................................88
Description of the tests that can be carried out.....................................................................88
8 - Maintenance.....................................................................................90
General conditions .......................................................................................................90
000003BG
Routine maintenance.............................................................................................................91
Special maintenance..............................................................................................................91
Alarm Messages....................................................................................................................92
000003BG
-6-
000003BG
-7-
23 - 24
25
01
09
06
13 12
MEMORY
CARD
BASE / S2
COM
CARD
03
10
11
14 17 16
10
11
14
09
04
02
15
21 16
13 12
18
05
MEMORY
CARD
S2X
COM
CARD
10
22
14 17 16
09
07
10
000003BG
08
-8-
19 20
14
21 16
Analytical index
A
AC cable gland 16............................................................................................................................... 21, 56, 57
accident-prevention regulations........................................................................................................................ 32
AC+DC disconnect switch 14...................................................................................................... 18, 46, 49, 75
AC output terminal board 17............................................................................................................... 21, 56, 57
AC overvoltage surge arresters 18.............................................................................................. 18, 31, 46, 91
AC voltage.................................................................................................................................................. 56, 71
alarm............................................................................................ 28, 62, 63, 80, 85, 91, 92, 93, 94, 96, 97
altitude............................................................................................................................................................... 41
analogue sensors................................................................................................................................ 28, 64, 86
anomaly................................................................................................................... 34, 44, 72, 78, 79, 91, 94
anti-condensation valve 21............................................................................................................................... 46
array............................................................................................................................................. 25, 29, 49, 50
autotest................................................................................................................................................ 84, 88, 94
B
bracket 01................................................................................................................................................. 35, 43
C
clamp screw 05................................................................................................................................................. 43
cleaning...................................................................................................................................................... 35, 90
clothing....................................................................................................................................................... 15, 34
communication card 09.................................................................................................. 47, 58, 59, 62, 66, 91
connection to the grid..................................................................................................... 71, 76, 78, 85, 94, 95
connectors............................................................................. 18, 35, 37, 46, 49, 50, 51, 59, 60, 62, 64, 91
connector screws 07......................................................................................................................................... 43
cooling.......................................................................................................................................... 16, 35, 41, 91
country of installation................................................................................. 2, 15, 28, 32, 33, 36, 56, 67, 101
country standard........................................................................................................................................ 67, 68
cover 04.............................................................................................................................................. 43, 49, 56
000003BG
-9-
F
fans.................................................................................................................................................................... 91
fault................................................................................. 31, 44, 45, 52, 55, 72, 78, 79, 80, 91, 93, 94, 98
field of use......................................................................................................................................................... 16
fire.............................................................................................................................................................. 34, 52
firmware..................................................................................................................................................... 28, 87
flammability........................................................................................................................................... 2, 16, 33
front cover 08.................................................................................................................................................... 91
G
grid. 16, 23, 25, 26, 27, 28, 29, 31, 34, 41, 44, 56, 57, 62, 63, 66, 67, 68, 70, 71, 72, 74, 75, 76, 7
7, 78, 79, 84, 85, 86, 87, 88, 89, 90, 91, 93, 94, 95, 96, 100
grid company......................................................................................................................... 28, 70, 94, 95, 96
grid standard......................................................................................................................... 67, 71, 75, 87, 88
grid voltage....................................................... 23, 25, 31, 71, 72, 75, 76, 78, 85, 88, 89, 93, 94, 95, 96
grounded............................................................................................................................................. 15, 16, 60
ground fault.................................................................................................................................. 31, 45, 72, 98
ground leakage..................................................................................................................... 44, 92, 93, 98, 99
H
handles 06.................................................................................................................................................. 39, 43
heatsink 26........................................................................................................................................................ 91
humidity................................................................................................................................. 16, 33, 35, 36, 41
000003BG
I
input channels................................................................................................................ 37, 46, 47, 58, 92, 93
Input connectors (MPPT1) 19........................................................................................................................... 46
Input connectors (MPPT2) 20........................................................................................................................... 46
input power........................................................................................................................................................ 78
inputs................................................................................................... 28, 47, 48, 49, 50, 78, 86, 87, 92, 93
input voltage........................................................................................ 23, 26, 44, 63, 70, 78, 85, 92, 93, 96
installation conditions................................................................................................................... 18, 32, 47, 48
insulation resistance............................................................................... 44, 76, 78, 92, 93, 94, 95, 96, 100
inverter 03.................................................................................................................................... 43, 46, 49, 56
inverter operation................................................................................................................................ 23, 26, 48
islanding.............................................................................................................................................. 20, 25, 31
- 10 -
jumpers 12........................................................................................................................................................ 47
K
keypad 24.......................................................................................................................................................... 72
L
language............................................................................................................................... 46, 58, 67, 68, 84
LED panel 25................................................................................................................. 72, 74, 76, 78, 79, 80
lifting.................................................................................................................................................... 36, 38, 43
long distance..................................................................................................................................................... 60
long or prolonged stop.................................................................................................................................... 101
M
magnetic fields.................................................................................................................................................. 33
materials.......................................................................................................................................................... 101
models................................................................................................. 17, 18, 22, 37, 46, 49, 52, 57, 95, 96
monitoring............................................................................................................... 28, 31, 59, 60, 61, 62, 64
N
national electricity grid...................................................................................................................................... 25
national grid......................................................................................................................................... 16, 26, 57
noise...................................................................................................................................................... 2, 34, 41
O
operator................................................................................................................................. 13, 16, 69, 73, 80
output power.............................................................................................................................................. 18, 23
overheating......................................................................................................................................... 34, 35, 41
000003BG
packaging.......................................................................................................................................................... 36
personal protective equipment..................................................................................................... 13, 15, 34, 90
photovoltaic panels...................................................................................................................... 27, 31, 41, 91
photovoltaic system.............................................................................................................. 25, 26, 27, 45, 49
place of installation.............................................................................................................................. 35, 41, 42
plates............................................................................................................................................ 15, 18, 33, 35
polarity........................................................................................................................................................ 44, 96
pollution............................................................................................................................................. 20, 35, 101
power graph...................................................................................................................................................... 77
power reduction................................................................................................................................................ 23
professional figures.................................................................................................................................... 13, 17
protective devices............................................................................................................................... 29, 31, 34
PV generator.................................... 25, 44, 48, 49, 52, 71, 77, 78, 85, 92, 93, 94, 95, 96, 98, 99, 100
PV modules................................................................................................................................ 25, 52, 78, 100
- 11 -
S
SD Card............................................................................................................................................................ 66
serial interface............................................................................................................................................ 28, 74
serial line.................................................................................................................................................... 60, 74
service cable glands 10............................................................................................................................. 59, 62
short-circuit........................................................................................................................................ 52, 54, 100
signs........................................................................................................................................................... 14, 15
sizing of the system................................................................................................................................... 27, 44
spare parts.......................................................................................................................................... 32, 38, 90
staff...................................................................................................... 15, 16, 32, 34, 35, 36, 40, 73, 90, 91
statistics...................................................................................................................................................... 81, 82
storage............................................................................................................................................................ 101
string fuses 22....................................................................................................................... 18, 31, 46, 50, 52
strings.................................................................................... 25, 44, 48, 49, 50, 52, 53, 77, 87, 93, 94, 96
T
Table: Components supplied with the equipment............................................................................................. 37
Table: country standard and language............................................................................................................. 67
Table: electrical system components................................................................................................................ 46
Table: LED behaviour........................................................................................................................................ 78
Table of residual risks....................................................................................................................................... 35
Table: Symbols.................................................................................................................................................. 15
temperature...................................................... 15, 16, 23, 28, 34, 35, 41, 42, 53, 54, 55, 64, 70, 86, 93
temperature sensor........................................................................................................................................... 64
temporary repairs.................................................................................................................................. 2, 32, 90
training................................................................................................................................... 13, 14, 35, 40, 69
transformer.......................................................................................................................................... 15, 29, 85
transport.................................................................................................................................. 2, 36, 37, 38, 39
000003BG
warranty....................................................................................................................................................... 2, 13
weather conditions.............................................................................................................................. 35, 73, 91
wiring box 02.................................................................................................... 18, 21, 31, 43, 46, 49, 56, 91
work environment....................................................................................................................................... 34, 35
- 12 -
List of annexes
In addition to this operating and maintenance manual, (if applicable or
on request) the following attached documentation is supplied:
- EC declaration of conformity
- quick installation guide
- service manual for the installer
- warranty
WARNING: Part of the information given in this document is taken from the original
documents of the suppliers. This document contains only the information considered
necessary for the use and routine maintenance of the equipment.
Staff characteristics
The customer must make sure the operator has the necessary skill and training to do
his/her job. Staff in charge of using and maintaining the equipment must be skilled,
aware and mature for the described tasks and must have the reliability to correctly
interpret what is described in the manual.
The employment of a person who is NOT qualified, is drunk or on narcotics, has a
prosthetic mitral valve or a pacemaker is strictly forbidden.
000004AG
The customer is civilly liable for the qualification and mental or physical condition of
the professional figures who interact with the equipment. They must always use the
personal protective equipment provided for by the laws of the country of destination
and whatever is provided by their employer.
- 13 -
Reference regulations
The reference standards complied with in the design and manufacture of the equipment are described below.
2006/95/EC Low voltage directive (ex 73/23/EEC).
2004/108/EC Electromagnetic Compatibility Directive, Italian Legislative Decree D.Lgs. 6/11/2007 no. 194 (ex 89/336/EEC).
D.Lgs. no. 81 of 9/4/2008 Implementation of the Consolidation Act on
safety (ex D.Lgs. 626/94 of 18/9/1994), directives for improvement of
occupational health and safety.
UNI EN ISO 14121-1: 2007 Safety of machinery - Principles for risk
assessment.
IEC EN 60204-1: 2006 Safety of machinery - Electrical equipment of
machines. Part 1: General requirements.
UNI EN 12198-2: 2009 Safety of machinery - Assessment and reduction of risks arising from radiation emitted by machinery.
UNI 9513:1989 Vibration and shock. Vocabulary. - Defines terms relating to vibration and shock.
IEC 70-1 (EN 60529 June 1997) Degrees of protection provided by
enclosures (IP code).
UNI 10893: 2000 Technical product documentation - instructions for
use. Organization and order of contents.
UNI ISO 10015: 2001 Guidelines for training.
ISO 7000 - DIN 30600 Graphic symbols and signs for function identification.
000005BG
- 14 -
Table: Symbols
In the manual and/or in some cases on the equipment, the danger or
hazard zones are indicated with signs, plates, symbols or icons, like the
CE marking.
This points out that it is mandatory to consult the manual or original document, which must be available for future use and must not be damaged
in any way.
This points out operations or situations in which staff must be very careful, respectively:
Generic hazard or hazardous voltage
This points out a hazard due to the presence of heated areas or in any
case areas that have hot parts (danger of burns).
This points out that the examined area must not be entered or that the
described operation must not be carried out.
This points out that the equipment must not be worked on by anyone
with a pacemaker, prosthetic mitral valve or prostheses with electronic
circuits.
This points out that it is mandatory to carry out the described operations
using the clothing and/or personal protective equipment provided by the
employer.
IP65
This indicates the risk of electric shock. Time needed to discharge stored
energy: 10 minutes
This indicates that the equipment must be disposed of in accordance
with the regulations in force in the country of installation.
000006AG
- 15 -
Power-One accepts no liability for damage of any kind that may arise
from incorrect or careless operations.
The equipment must not be used for uses that do not fall within the intended field of
use. The equipment MUST NOT be used by inexperienced staff, or by experienced
staff to carry out operations on the equipment that are not in accordance with what is
described in this manual and in the attached documents.
000007AG
IP65
2
2 - Characteristics
General conditions
The description of the characteristics of the equipment allows its main
components to be identified, to refine the technical terminology used in
the manual.
The technical terminology and the quick information finding system are
assisted by the following:
Contents
Numerical index of references
Index.
The Characteristics chapter contains information about the models, the
composition of the equipment, the characteristics and technical data, the
overall dimensions and the identification of the equipment.
This manual should be read in chronological order as established by the manufacturer and the reader assumes responsibility for failure to do so. All the information is
given considering each time that the information of the preceding chapters has been
acknowledged.
000008AG
In some cases, there may be a need to separately document the operation of the software or to attach supplementary documentation to this
manual for more qualified professional figures.
- 17 -
Characteristics
The specific models of multi-string inverter that this manual is about are
divided into two groups according to the maximum output power (20 kW
or 27.6 kW).
For inverters of equal output power, the variant between the various
models is the layout of the wiring box 02.
The choice of model of inverter must be made by a qualified technician who knows
about the installation conditions, the devices that will be installed outside the inverter
and possible integration with an existing system.
20 kW three-phase MODELS
TRIO-20.0-TL-OUTD: Basic version wiring box
TRIO-20.0-TL-OUTD-S2: S2 wiring box version (with AC+DC disconnect switch 14)
TRIO-20.0-TL-OUTD-S2X: S2X wiring box version (with quick fit connectors, string fuses 22, DC overvoltage surge arresters 15, AC overvoltage surge arresters 18 and AC+DC disconnect switch)
27.6 kW three-phase MODELS
TRIO-27.6-TL-OUTD: Basic version wiring box
TRIO-27.6-TL-OUTD-S2: S2 wiring box version (with AC+DC disconnect switch)
TRIO-27.6-TL-OUTD-S2X: S2X wiring box version (with quick fit connectors, string fuses, DC overvoltage surge arresters, AC overvoltage
surge arresters and AC+DC disconnect switch)
000009AG
The technical data shown in this manual do not in any case replace
those shown on the plates attached to the equipment.
The plates attached to the equipment must NOT be removed, damaged, dirtied, hidden, etc.
- 18 -
Characteristics
000047AG
TRIO-20.0-TL-OUTD
TRIO-27.6-TL-OUTD
20750 Wp
22700 Wp
620 V
360 V (adj. 250...500 V)
0.7 x Vstart...970 V
200...950V
12000 W
440...800 V
28600 Wp
31000 Wp
620 V
360 V (adj. 250...500 V)
0.7 x Vstart...970 V
200...950V
16000 W
500...800 V
Yes
30.0 A
2 for each MPPT
3 (Class II) for each
MPPT
In accordance with the
local standard
(0.12uF/kW) * 20kW =
2.4uF
40 A / 1000 V
12 A / 1000 V
Yes
40.0 A
2 for each MPPT
3 (Class II) for each
MPPT
In accordance with the
local standard
(0.12uF/kW) * 27.6kW =
3.3uF
40 A / 1000 V
12 A / 1000 V
- 19 -
Characteristics
Maximum apparent Output Power (Sacmax)
000047AG
User Interface
Environmental
Ambient Temperature
Storage Temperature
Relative Humidity
Noise Emission
Maximum Operating Altitude
Environmental pollution classification for external
environment
Environmental Category
22300VA
The rated power is also
guaranteed with cos(fi)
= 0.9
400 Vac / N / PE
320...480 Vac (1)
33.0 A
50 Hz
47...53 Hz (2)
> 0.995 (adj. 0.9)
< 3%
Screw terminal board,
maximum cross-section
35 mm2
31000 VA
The rated power is also
guaranteed with cos(fi)
= 0.9
400 Vac / N / PE
320...480 Vac (1)
45.0 A
50 Hz
47...53 Hz (2)
> 0.995 (adj. 0.9)
< 3%
Screw terminal board,
maximum cross-section
35 mm2
Not applicable
Not applicable
98.2%
98.0% / 98.0%
40 W
< 8W
<1W
110 VAR
15.8 kHz
98.2%
98.0% / 98.0%
40 W
< 8W
<1W
110 VAR
15.8 kHz
PVI-USB-RS485_232,
PVI-DESKTOP
PVI-AEC-EVO, AURORA-UNIVERSAL
PVI-DESKTOP with PVIRADIOMODULE
Graphic Display
PVI-USB-RS485_232,
PVI-DESKTOP
PVI-AEC-EVO, AURORA-UNIVERSAL
PVI-DESKTOP with PVIRADIOMODULE
Graphic Display
-25...+60C /-13...140F
with derating above
45C/113F
-40...80C (-40...+176F)
0...100% condensing
< 50 db(A) @ 1 m
2000 m / 6560 ft
3
-25...+60C /-13...140F
with derating above
45C/113F
-40...80C (-40...+176F)
0...100% condensing
< 50 db(A) @ 1 m
2000 m / 6560 ft
3
External
External
- 20 -
Characteristics
Physical
Environmental Protection Rating
Cooling system
Air Flow Required for Cooling
Overvoltage Category in accordance with IEC
62109-1
Dimensions (H x W x D)
Weight
Packaging Dimensions (H x W x D)
Full Packaging Weight
Mounting System
Exposure to UV rays
Safety
Safety Class
Isolation Level
IP 65
Natural
Not applicable
II (DC input)
III (AC output)
1060 x 751 x 291 mm
41.7" x 29.6" x 11.4"
Basic and -S2: 67.0 kg /
147.70 lb
S2X: 75.0 kg / 165.30 lb
737 x 800 x 1200 mm
29 x 31.5 x 47.2
Basic and -S2: 79.0 kg /
174.10 lb
S2X: 87.0 kg / 191.80 lb
Wall bracket
Plastic covers suitable
for outdoor use.
Exposure to UV rays
(in accordance with UL
746C)
IP 65
Natural
Not applicable
II (DC input)
III (AC output)
1060 x 751 x 291 mm
41.7" x 29.6" x 11.4"
Basic and -S2: 72.0 kg /
158.70 lb
S2X: 80.0 kg / 176.30 lb
737 x 800 x 1200 mm
29 x 31.5 x 47.2
Basic and -S2: 84.0 kg /
185.10 lb
S2X: 92.0 kg / 202.80 lb
Wall bracket
Plastic covers suitable
for outdoor use.
Exposure to UV rays
(in accordance with UL
746C)
I
Transformerless
I
Transformerless
75
Overall dimensions
- 2
9,6
7.5 Nm
5 Nm
2.7 Nm
5 Nm
2.4 Nm
6 Nm
2.5 Nm
- 21 -
32
1
11 m
,4 m
000047AG
To maintain the IP65 protection of the system and for optimal
installation, the following tightening torques must be used:
1060 mm - 41,7
Tightening torques
Characteristics
Efficiency curves
100
99
98
97
96
95
94
93
500 Vdc
92
620 Vdc
91
800 Vdc
90
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
TRIO-27.6-TL-OUTD
TRIO-27.6-TL-OUTD-S2
TRIO-27.6-TL-OUTD-S2X
100
99
98
97
96
95
94
93
500 Vdc
000048AG
92
620 Vdc
91
800 Vdc
90
0%
10%
20%
30%
40%
50%
60%
- 22 -
70%
80%
90%
100%
Characteristics
Power Derating
TRIO-20.0-TL-OUTD
TRIO-20.0-TL-OUTD-S2
TRIO-20.0-TL-OUTD-S2X
25000
Pout [W]
20000
15000
10000
5000
0
01
00
2003
000048AG
- 23 -
00
4005
00
Vin [V]
600
700
800
900
1000
Characteristics
P [W]
20000
15000
10000
5000
0
01
00
2003
00
4005
00
6007
00
8009
00
1000
Vin [V]
TRIO-27.6-TL-OUTD
TRIO-27.6-TL-OUTD-S2
TRIO-27.6-TL-OUTD-S2X
30000
25000
P [W]
20000
15000
10000
5000
0
01
00
2003
00
4005
00
6007
00
800
900
1000
Voltage [V]
P [W]
20000
15000
10000
5000
000048AG
0
01
00
2003
00
- 24 -
4005
00
Voltage [V]
6007
00
800
900
1000
Characteristics
In order to considerably reduce the cost of installing a photovoltaic system, mainly associated with the problem of wiring on the DC side of the
inverter and subsequent distribution on the AC side, the string technology has been developed. A photovoltaic panel consists of many photovoltaic cells mounted on the same support.
A string consists of a certain number of panels connected in series.
An array consists of two or more strings connected in parallel.
Large photovoltaic systems can be made up of several arrays, connected to one or more inverters.
By maximizing the number of panels inserted in each string, it is possible to reduce the cost and complexity of the connection system of the
photovoltaic system.
000011AG
The current of each array must fall within the limits of the inverter.
To work, the inverter must be connected to the national electricity grid since its operation can be equated to a current generator that supplies power in parallel with the grid
voltage. That is why inverters cannot support the grid voltage (islanding).
- 25 -
Characteristics
This equipment is a multi-string inverter that converts direct electric current from a photovoltaic generator into alternating electric current and
feeds it into the national grid.
Photovoltaic panels transform energy from the sun into direct current
(DC) electrical energy (through a photovoltaic field, also called photovoltaic (PV) generator; however, to feed the grid and so that this energy
can be used, it has to be transformed into alternating current (AC). This
conversion, known as DC to AC inversion, is made efficiently without using rotating parts and only through static electronic devices.
In order to allow inverter operation in safe thermal and electrical conditions, in the event of adverse environmental conditions or unsuitable input voltage values, the unit automatically reduces the value of the power
fed into the grid.
When used in parallel with the grid, the alternating current generated by
the inverter flows directly into the domestic electrical circuit, which is in
turn connected, through a distributor, to the national grid.
The solar energy system therefore powers all connected electrical devices, from lighting to household appliances, etc.
When the photovoltaic system is not supplying sufficient power, the
power needed to ensure normal operation of the connected electrical
devices is drawn from the national grid. If, on the other hand, excess
power is produced, this is fed directly into the grid, so becoming available to other consumers.
In accordance with local and national regulations, the power produced
can be sold to the grid or credited towards future consumption, so bringing about a saving of money.
Operating diagram
Inverter
Distributor
000012BG
PV generator
- 26 -
Grid company
Characteristics
000012BG
- 27 -
Characteristics
000013AG
- 28 -
Characteristics
000014BG
- 29 -
- 30 -
-S2 VERSION
IN2
IN1
IN2
IN1
STANDARD VERSION
IN2(-)
IN2(+)
IN1(-)
IN1(+)
IN2(-)
IN2(+)
IN1(-)
IN1(+)
000014BG
*IN2E(-)
IN2D(-)
IN2C(-)
IN2B(-)
IN2A(-)
*IN2E(+)
IN2D(+)
IN2C(+)
IN2B(+)
IN2A(+)
*IN1E(-)
IN1D(-)
IN1C(-)
IN1B(-)
IN1A(-)
*IN1E(+)
IN1D(+)
IN1C(+)
IN1B(+)
IN1A(+)
PT 100
IN MODE
AN 2
AN 1
PMU
PC
SERVICE OR NORMAL
ON/OFF EXT
IN2
PT 1000
IN2
IN1
OVP
MONITORING
OVP
MONITORING
-S2X VERSION
CURRENT
READING
CURRENT
READING
IN1
OVP MONITORING
CURRENT READING
SD
CARD
LINE
FILTER
CONTROL CIRCUIT
INVERTER
(DC/AC)
DC/DC
DSP
CONTR.
BULK CAPS
PVI-RADIO
MODULE
(OPT)
DC/AC
DSP
CONTR.
GRID PARALLEL
RELAY
MPPT 2
(DC/DC)
MPPT 1
(DC/DC)
ALARM
REMOTE CONTROL
PC_RS485
PMU_RS485
N.O
N.C
GND
+R
GND
- T/R
+ T/R
GND
- T/R
+ T/R
PE
L3
L2
L1
L3
L2
L1
-S2 VERSION
PE
N, S
L3, S
L2, S
L1, S
L3
L2
L1
-S2X VERSION
02
03
PE
N, S
L3, S
L2, S
L1, S
Characteristics
Characteristics
Protective devices
Anti-Islanding
In the event of a local grid outage by the electricity company, or when the
equipment is switched off for maintenance operations, the inverter must
be physically disconnected safely, to ensure protection of people working on the grid, all in accordance with the relevant national standards
and laws. To prevent possible islanding, the inverter is equipped with an
automatic protective disconnection system called Anti-Islanding.
String fuses
In the S2X versions, string fuses 22 that protect the equipment from
currents above the limit value, independently for each string, are pre-installed inside the wiring box 02. The sizing of the fuses must be carefully
considered during installation.
000015AG
3
3 - Safety and accident prevention
Safety instructions and general information
The equipment has been manufactured in accordance with the strictest
accident-prevention regulations and supplied with safety devices suitable for the protection of components and operators.
For obvious reasons, it is not possible to anticipate the great number of installations
and environments in which the equipment will be installed; it is therefore necessary
for the customer to appropriately inform the manufacturer about particular installation
conditions.
Power-One accepts no liability for failure to comply with the instructions
for correct installation and cannot be held responsible for the systems
upstream or downstream of the equipment it has supplied.
It is essential to provide operators with correct information. They must therefore read
and comply with the technical information given in the manual and in the attached
documentation.
The instructions given in the manual do not replace the safety devices
and technical data for installation and operation stuck on the product,
and they certainly do not replace the safety regulations in force in the
country of installation and common sense rules.
The manufacturer is willing to train staff, at its premises or on site, in accordance with conditions to be set out in the contract.
Do not use the equipment if you find any operating anomalies.
Avoid temporary repairs. All repairs should be carried out using only
genuine spare parts, which must be installed in accordance with their
intended use.
000016AG
- 32 -
000017AG
The plates must be cleaned regularly and kept visible at all times, and
therefore they must NOT be hidden with objects and extraneous parts
(rags, boxes, equipment, etc.).
The technical data shown in this manual do not in any case replace
those shown on the plates attached to the equipment.
- 33 -
Thermal hazard
10 min
000017AG
- 34 -
Residual Risks
Despite the warnings and safety systems, there are still some residual
risks that cannot be eliminated.
These risks are listed in the following table with some suggestions for
preventing them.
Suitable local ventilation that does not cause overheating of the equipment and is sufficient not to create discomfort to people in the room.
Ensure the devices have discharged their energy before working on them.
000018AG
- 35 -
4
4 - Lifting and transport
General conditions
Transport and handling
Transport of the equipment, especially by road, must be carried out by
suitable ways and means for protecting the components (in particular,
the electronic components) from violent knocks, humidity, vibration, etc.
During handling, do not make any sudden or fast movements that
can create dangerous swinging.
Lifting
Power-One usually stores and protects individual components by suitable means to make their transport and subsequent handling easier, but
as a rule it is necessary to turn to the experience of specialized staff in
charge of loading and unloading the components.
Where indicated and/or where there is provision, eyebolts or handles,
which can be used as anchorage points, are inserted and/or can be
inserted.
The ropes and means used for lifting must be suitable for bearing
the weight of the equipment.
Do not lift several units or parts of the equipment at the same time, unless otherwise indicated.
000019AG
Quantity
Connector 21.2500MF/3
Connector 21.2500MF/8
Cylinder, TGM58
Gasket, 36A3M2025
Quantity
Quantity
8 (20 kW)
10 (27.6 kW)
8 (20 kW)
10 (27.6 kW)
16 (20 kW)
20 (27.6 kW)
000020BG
- 37 -
A list of spare parts that are compatible with the TRIO inverter and in
stock at the Power-One warehouse is given below.
Description
Quantity
4 handles
2 eyebolts
KIT 10 FUSES 8A
Kit of 8A fuses
10
10
10
10
000020BG
Code
- 38 -
Mass
weight in kg
Lifting
points
Minimum
rope height
Holes or Eyebolts
UNI2947
n#
INVERTER unit
TRIO-20.0: 60 kg
TRIO-27.6: 65 kg
1.200
M 12
mounting kit with
handles 06 and
eyebolts (to order)
NO
000020BG
M12
- 39 -
5
5 - Installation
General conditions
Installation of the equipment is carried out based on the system and the place in which
the equipment is installed; therefore, its performance depends on the correctness of
the connections.
Staff authorized to carry out the installation must be specialized and experienced in this job; they must also have received suitable training on
equipment of this type.
000021AG
- 40 -
Installation
The installation must be carried out with the equipment disconnected from the grid
(power disconnect switch open) and with the photovoltaic panels shaded or isolated.
Environmental checks
OK OK
NO OK
NO
OK OK
NO
NO
000022AG
All installations at altitudes of over 2000 metres must be assessed case by case considering the aforesaid criticalities.
- 41 -
Installation
Installation position
NO
NO
OK
NO
When choosing the place of installation, comply with the following conditions:
Install on a wall or strong structure suitable for bearing the weight.
Install in safe, easy to reach places.
If possible, install at eye-level so that the display and status LEDs can
be seen easily.
Install at a height that considers the heaviness of the equipment. If
this condition is not complied with, it can create problems in the event of
servicing unless suitable means are provided to carry out the operation.
Install vertically with a maximum inclination of +/- 5. If this condition
is not complied with, the inverter could go into temperature derating because of the worsening of heat dissipation.
To carry out maintenance of the hardware and software of the equipment, remove the covers on the front. Check that there are the correct
safety distances for the installation that will allow the normal control and
maintenance operations to be carried out.
Comply with the indicated minimum distances.
80
cm
50 cm
50 cm
50
cm
OK
OK
If the space available does not allow this arrangement, position the
inverters in a staggered arrangement as shown in the figure so that heat
dissipation is not affected by other inverters.
000022AG
NO
- 42 -
Installation
Wall mounting
10 x 10 mm
03
04
02
01
07
06
05
000023BG
04
05
- 43 -
Installation
000024AG
Installation
max for the 30 mA/sec change, they are shortened respectively to 150
msec and 40 msec for 60 mA and 150 mA changes.
It should in any case be noted that the integrated device only protects the
system against ground faults that occur upstream of the AC terminals of
the inverter (namely towards the DC side of the photovoltaic system and
consequently towards the photovoltaic modules). The leakage currents
that can occur in the AC section between the draw/feed in point and the
inverter are not detected and require an external protection device.
For protection of the AC line, on the basis of the aforesaid with regard
to the differential protection integrated in Power-One Aurora inverters, it
is not necessary to install a type B ground fault interrupter.
In accordance with article 712.413.1.1.1.2 of Section 712 of IEC Standard 64-8/7, we
hereby declare that, because of their construction, Power One Aurora inverters do not
inject ground fault direct currents.
000024AG
The use of an AC type circuit breaker with differential thermal magnetic protection
with tripping current of 300 mA is advisable so as to prevent false tripping, due to the
normal capacitive leakage current of photovoltaic modules.
- 45 -
Installation
13 12
MEMORY
CARD
COM
CARD
For both models of inverter 03 (20 kW or 27.6 kW), three wiring box 02
are available with different layouts:
TRIO-XX.X-TL-OUTD: Basic version wiring box
TRIO-XX.X-TL-OUTD-S2: S2 wiring box version, like the basic version
but with AC+DC disconnect switch 14
TRIO-XX.X-TL-OUTD-S2X: S2X wiring box version, more complete version with quick fit connectors, string fuses 22, DC overvoltage surge
arresters 15, AC overvoltage surge arresters 18 and AC+DC disconnect
switch.
S2X version
09
10
11
14 17 16
15
13 12
18
MEMORY
CARD
COM
CARD
a05 a01
1
10
11
14
MEMORY
CARD
21 16
COM
CARD
000025BG
10
10
22
19 20
14 17 16
14
21 16
Description
communication card
service cable glands
DC cable glands
jumpers
DC input terminal board
AC+DC disconnect switch
DC overvoltage surge arresters
AC cable gland
AC output terminal board
AC overvoltage surge arresters
Input connectors (MPPT1)
Input connectors (MPPT2)
anti-condensation valve
string fuses
Switch for setting parallel-connected or independent input channels
Rotary switches for setting the country and the language of the display
- 46 -
Installation
All versions of the inverter are equipped with two input channels (therefore with double maximum power point tracker MPPT) independent of
each other, which can however be connected in parallel using a single
MPPT.
Strings of photovoltaic modules having the same type and number of
panels in series must be connected to each single channel; they must
also have the same installation conditions (in terms of orientation to the
SOUTH and inclination from the horizontal plane).
When connecting the two input channels in parallel, the aforesaid requirements must be observed with the benefit of being able to use the
full power that can be supplied by the inverter on a single channel.
Whereas the double MPPT structure allows the management of two
photovoltaic generators that are independent of each other (one for
each input channel) and can differ from each other in installation conditions, type and number of photovoltaic modules connected in series. A
necessary condition so that the two MPPTs can be used in independent
mode is for the photovoltaic generator connected to each of the inputs to
have a power lower than the power limit of the single input channel and a
maximum current lower than the current limit of the single input channel.
All the input parameters that must be observed for correct operation of the inverter are
shown in the technical data table.
MEMORY
CARD
COM
CARD
a01
This configuration involves the use of the two input channels (MPPT)
connected in parallel. This means that the jumpers 12 between the two
channels (positive and negative) of the DC input terminal board 13 must
be installed and that the switch a01 situated on the communication card
09 must be set to PAR (see user interface).
MEMORY
CARD
000025BG
COM
CARD
This configuration involves the use of the two input channels (MPPT) in
independent mode. This means that the jumpers 12 between the two
channels (positive and negative) of the DC input terminal board 13 must
not be installed and that the switch a01 situated on the communication
card 09 must be set to IND (see user interface).
a01
- 47 -
Installation
Channel configuration examples
PV generator characteristics
000025BG
MPPT configuration
MPPT configuration
has to be INDEPENDENT
Notes
A NECESSARY condition so that the two
MPPTs can be used in independent mode is for
the photovoltaic generator connected to each
of the inputs to have a power lower than the
power limit of the single input channel AND a
maximum current lower than the current limit
of the single input channel.
- 48 -
Installation
Once the preliminary checks have been made and it has therefore been
verified that there are no problems on the photovoltaic system, and once
the channel configuration has been chosen (parallel or independent),
the inputs can be connected to the inverter.
The connections can also be made with the wiring box 02 detached from
the inverter 03 that can be connected later for commissioning.
When working with the wiring box 02 detached, pay particular attention to outdoor
installations, where the coupling connector must always be protected by installing the
cover 04 on its housing.
The DC side connections are different according to the wiring box used:
The basic and S2 models use cable glands whereas the S2X model
uses quick fit connectors (one for each pole of each string).
On the basic and S2 versions, the connection in parallel of the strings (array composition) must take place upstream of the input in the inverter and must be made by technicians during installation.
The S2X version accepts direct connection of the single strings, with
connectors accessible from the outside of the wiring box 02.
To prevent electrocution hazards, all the connection operations must be carried out
with the AC+DC disconnect switch 14 open and locked.
000025BG
13 12
11
14
11
14
For these two models, connection with the DC input terminal board 13 is
made by inserting the cables in the DC cable glands 11.
The maximum accepted cable cross-section ranges from 10 to 17 mm,
whereas each individual terminal of the terminal board accepts a cable
with cross-section of up to 50 mm2.
Unscrew the cable gland, remove the cover, insert the cable of suitable
cross-section and connect it to the terminals on the DC input terminal
board 13.
Once the connection to the terminal board is complete, screw in the
cable gland firmly and check the tightness.
- 49 -
Installation
For string connections using the S2X wiring box, the quick fit connectors
(multicontact or weidmuller) situated at the bottom of the mechanism
are used.
For each input channel, there are two groups of connectors:
Input connectors (MPPT1) 19 with codes 1A, 1B, 1C, ...
Input connectors (MPPT2) 20 with codes 2A, 2B, 2C, ...
Connect all the strings included in the design of the system and always
check the tightness of the connectors.
22
14
If some string inputs are not used, check that there are covers on the
connectors and install them if they are missing.
This operation is necessary for the tightness of the inverter and to avoid
damaging the free connector that could be used at a later date.
19 20
14
000025BG
In this version of the wiring box, it is NECESSARY not to carry out the paralleling of
the strings outside the inverter. This is because the string fuses 22, situated on each
input, are not sized to take strings in parallel (array). This operation can cause damage
to the fuse and consequently malfunctioning of the inverter.
- 50 -
Installation
12 mm
Clik
000026AG
WARNING: To prevent damage to the equipment, pay particular attention to the polarities when wiring the cables.
- 51 -
Installation
Sizing of fuses
22
The sizing of the string fuses 22 to be used to protect from return currents is very important because it can considerably limit the risk of fire
and damage to the PV generator.
A return current can be generated in the event of a fault and relevant
short-circuit at the ends of one or more PV modules of the system; this
condition can cause all the current supplied by the strings not involved
in the fault, but connected to the same input channel, to pass through
the faulty string.
The sizing of the string fuses 22 depends on the technical characteristics of the PV modules making up the PV generator.
The value of the correct fuses to be installed is given in the technical
data by some suppliers of PV modules.
If this information is not available, the correct value can be calculated
using the procedure for choosing the fuses.
The value of the chosen fuse must in any case be lower than the maximum return current indicated in the technical data of the PV module.
000042AG
- 52 -
Installation
NO
Number N strings
in parallel N > 3?
It is not necessary
to use fuses
YES
UOC_MOD (Voltage without load of the modules)
M (number of modules connected in series)
Do you know
the TMIN_P?
(Minimum working temperature of the panel)
NO
YES
Do you know
[%/C]?
(temperature coefficient for
voltage without load)
NO
YES
Do you know
[mV/C]?
(temperature coefficient for
voltage without load)
NO
Consider
=0.4%/C
YES
000042AG
- 53 -
Installation
Evaluation of the capacity of the fuse
Do you know
IIRREFF?
(Actual maximum irradiation expected on the
panels)
NO
Consider IIRREFF = 1200 W/m2
YES
Do you know
TMAX_P?
(Maximum working temperature of the panel)
NO
YES
Do you know
[%/C]?
(temperature coefficient for
short-circuit current)
Do you know
[mA/C]?
(temperature coefficient for
short-circuit current)
NO
YES
NO
Consider
=0.1 %/C
YES
000042AG
- 54 -
Installation
Evaluation of the capacity of the fuse (continued)
Do you know Tf ? NO
(Temperature of the fuse or
the junction box)
NO
Consider Tf = 65C
YES
Evaluate the derating
coefficient of the fuse for the
working temperature.
Subject to conditions 1), 2) and 3), consider the fuse that, for the calculated
estimated fault current, blows with the shortest theoretical pre-arc time.
000042AG
Ig = ISC_MOD* (N - 1)
- 55 -
Installation
For the connection of the inverter to the grid, you can choose between a
star connection (3 phases + neutral) and a delta connection (3 phases).
In any case, connection of the inverter to ground is mandatory.
The cable you use can be 5-pole (star configuration) or 4-pole (delta
configuration) and must pass through the AC cable gland 16 to make the
connections to the AC output terminal board 17.
14 17 16
The connections can also be made with the wiring box 02 detached from
the inverter 03 that can be connected later to be put in service.
When working with the wiring box 02 detached, pay particular attention to outdoor
installations, where the coupling connector must always be protected by installing the
cover 04 on its housing.
max 35 mm 2
20 32 mm
The table shows the maximum length of the line conductor based on the
cross-section of this conductor:
TRIO-27.6-TL-OUTD
30m
50m
78m
98m
000027AG
The values are calculated considering an energy loss along the line (in rated power
conditions) not exceeding 1%.
- 56 -
Installation
To protect the AC connection line of the inverter, we recommend installing a device for protection against over current and leakage with the
following characteristics:
Type
Voltage/Current rating
Magnetic protection characteristic
Type of differential protection
Differential sensitivity
Number of poles
TRIO-20.0-TL-OUTD
TRIO-27.6-TL-OUTD
Automatic circuit breaker with differential thermal magnetic protection
40A/400V
63A/400V
B/C
B/C
A/AC
A/AC
300mA
300mA
3/4
3/4
Neutro R
T Terra
17
For all models, connection with the AC output terminal board 17 is made
by inserting the cables in the AC cable gland 16.
The maximum accepted cable cross-section ranges from 20 to 32 mm,
whereas each individual terminal of the terminal board accepts a cable
with cross-section of up to 35 mm2.
Unscrew the cable gland, remove the cover, insert the cable of suitable
cross-section and connect the conductors (Neutral, R, S, T and Ground)
to the terminals on the AC output terminal board 17.
The connection of the inverter to the grid can be with three wires (delta
configuration) or with four wires (star configuration).
Be careful not to change round one of the phases with neutral!
Once the connection to the terminal board is complete, screw in the
cable gland firmly and check the tightness.
MEMORY
CARD
000027AG
COM
CARD
- 57 -
Installation
Communication card
a01
5
a20
a19
a02
a18
a17
a03
a16
a04
MEMORY
CARD
COM
CARD
a05
a15
a14
a06
a13
a12
a07
Ref.
a01
a02
a03
a04
a05
a06
a07
a08
a09
a10
000028BG
a11
a12
a13
a14
a15
a16
a17
a18
a19
a20
a08
a09
a10
communication card 09
a11
Description
Switch for setting parallel-connected or independent input channels
Connector for the installation of WIFI modules (NOT ACTIVE)
Connectors for radiomodule card installation
Housing for memory card SD CARD
Rotary switches for setting the standard of the country and the language of the display
Ethernet port (NOT ACTIVE)
Switch for setting analogue sensor 1 to Volts or mA
Switch for setting analogue sensor 2 to Volts or mA
Connection to the multi-function relay
Connection of environmental sensors: AN1, AN2, PT100, PT1000 and tachometer (wind
version only)
Connection of the RS485 (PC) line, RS485 (PMU) line, of the auxiliary 5V and of the
remote ON/OFF
Switch for setting the termination resistance of the RS485 (PMU) line
Switch for setting the termination resistance of the RS485 (PC) line
Connection of the RS485 (PC) line on RJ45 connector
RS485 (PC) communication card housing
Connection of the RS485 (PMU) line on RJ45 connector
RS485 (PMU) communication card housing
Switch for setting the inverter in normal or service mode
Inverter data memory card housing
Battery housing
- 58 -
Installation
000028BG
- 59 -
Installation
TOP
FRONT
Use a connector with metal
body to provide cable shield
continuity!
-T/R +T/R
A
B
RTN
Function
not used
not used
+T/R
not used
-T/R
not used
GND
not used
Symbol
+T/R
-T/R
RTN
Pair
A
A
B
Cable
1
2
1+2
Shield continuity must be provided along the communication line using the SH terminal and must be grounded at a single point.
Connect all the units of the RS485 chain in accordance with the daisychain arrangement (in-out) observing the correspondence between
signals, and activate the termination resistance of the communication
line in the last element of the chain by switching switch a12 or a13 (to
ON position) being careful to switch the switch of the serial line used (PC
or PMU).
a12 = ON
a13 = ON
000028BG
MEMORY
CARD
a13
COM
CARD
a12
- 60 -
a12 = OFF
a13 = OFF
a12 = OFF
a13 = OFF
PC/
PMU
Installation
MEMORY
CARD
COM
CARD
000028BG
Please note that these devices may also require an external termination
impedance, whereas this is not necessary with the Aurora PVI-USBRS485_232.
RS485/PMU
RS485/PC
Gestore rete
- 61 -
PVI-USB-RS485_232
PVI-Desktop
PVI-AEC-EVO
Installation
Configurable relay
The inverter has a multi-function relay a09, whose switching can be
configured. It can be connected with normally open contact (being connected between the NO terminal and the common contact C) and with
normally closed contact (being connected between the NC terminal and
the common contact C).
This contact can be used in four different operating configurations that
can be set in the dedicated menu.
MEMORY
CARD
COM
CARD
a09
1
Operating modes
NO
NC
ALARM
000028BG
NC = Normally closed
C = Common contact
NO = Normally open
Production: the relay switches whenever a connection to (and therefore a disconnection from) the grid occurs.
So if the NO (or NC) contact is chosen, the contact will stay open (or
closed) until the inverter is connected to the grid; once the inverter connects to the grid and starts to export power, the relay switches state and
therefore closes (or opens).
When the inverter disconnects from the grid, the relay contact returns to
its position of rest, namely open (or closed).
- 62 -
Installation
Maximum Current: 1 A
Direct current
Maximum Voltage: 30 Vdc
000028BG
Cable requirements
External diameter: from 5 to 17 mm
Conductor cross-section: from 0.14 to 1.5 mm2
- 63 -
Installation
Environmental sensors
External sensors for monitoring environmental conditions can be connected to the connectors of the environmental sensors a10:
AN1 - Analogue sensor 1 connection
AN2 - Analogue sensor 2 connection
PT100 - Connection of a PT100 temperature sensor
PT1000 - Connection of a PT1000 temperature sensor
MEMORY
CARD
COM
CARD
a10
15
A1
A2 RTD1 RTD2
PT PT
COM 1000
1000
RTD1 RTD2
A2 PT PT
100 100
Setting of the connected analogue sensors must be carried out by setting the following values in the relevant menu:
- GAIN
- OFFSET
- Unit of measure
16
RTD3
PT
1000
RTD3
PT
100
+WTACH
A1
COM
-WTACH
MEMORY
CARD
COM
CARD
For each analogue sensor, AN1 and AN2, it is also necessary to set the
switch, a07 or a08, to select whether the reading is in Volts or mA.
Each sensor model has precise configuration values that must be set meticulously.
The power supply to the sensors must be installed outside the inverter, according to
the manufacturers specifications.
000028BG
Model
PVI-AEC-IRR
PVI-AEC-IRR-T
Type
Irradiation sensor
Irradiation sensor with integrated
cell temp. sensor
PVI-AEC-RAD-13TC
Irradiation sensor
PVI-AEC-RAD-13-TC-T
Irradiation sensor with integrated
cell temp. sensor
PVI-AEC-CONV-T100
PT100/0...10V converter
PVI-AEC-T1000-INTEGR
Ambient temperature sensor with
integrated converter
PVI-AEC-WIND-COMPACT Wind speed sensor
PVI-AEC-PYR-1300
Pyranometer (0...1300W/m2)
PVI-AEC-T100-ADH
Adhesive PT100 module
temperature sensor (back cell)
PVI-AEC-T1000-BOX
PT1000 ambient temperature
sensor
Gain
120
Irradiation: 120
Cell temp.: 10.869
130
Irradiation: 130
Cell temp.: 11.507
15
10
Offset
0
Irradiation: 0
Cell temp.: -20
0
Irradiation: 0
Cell temp.: -26.1
-50
-50
U.d.M.
W/mq
Irradiation: W/m2
Cell temp.: C
W/m2
Irradiation: W/m2
Cell temp.: C
C a 0...10V
C
5
65
N/A
0
0
N/A
m/s
W/m2
N/A
N/A
N/A
N/A
- 64 -
Installation
Model
Output signal
PVI-AEC-IRR
PVI-AEC-IRR-T
PVI-AEC-RAD-13TC
PVI-AEC-RAD-13-TC-T
PVI-AEC-CONV-T100
PVI-AEC-T1000-INTEGR
PVI-AEC-WIND-COMPACT
PVI-AEC-PYR-1300
PVI-AEC-T100-ADH
0...10Vdc
0...10Vdc
0...10Vdc
0...10Vdc
0...10Vdc
0...10Vdc
0...10Vdc
0...20mA
3-wire connection on terminals: RTD1PT100
RTD2PT100 RTD3PT100
3-wire connection on terminals: RTD1PT1000
RTD2PT1000 RTD3PT1000
PVI-AEC-T1000-BOX
External power
supply
YES
YES
YES
YES
YES
YES
YES
YES
NO
TRIO 20/27.6
compatibility
YES
YES
YES
YES
YES
YES
YES
NO
YES
EVO
compatibility
YES
YES
YES
YES
YES
YES
YES
YES
YES
NO
YES
YES
N.C.
A1/A2
-Vcc_Heat
-Vcc
(external)
+Vcc_Heat
+Vcc
+Vcc
(external)
A1/A2
-Vcc
A1/A2_RTN
A1/A2_RTN
(Wind speed)
PVI-AEC-T1000-BOX
RTD1PT1000
(PT_RTN)
RTD2PT1000
Ground
(PT_SENSE)
RTD3PT1000
(PT_ALIM)
PVI- AEC-T100-ADH
A2
N.C.
A1
+Vcc
(Irradiance)
(PT_RTN)
+Vcc
RTD2PT100
(PT_SENSE)
RTD3PT100
(PT_ALIM)
- 65 -
PVI-AEC-RAD-13TC
PVI-AEC-IRR
A1/A2
(temperature)
RTD1PT100
000028BG
PVI-AEC-RAD-13-TC-T
PVI-AEC-IRR-T
-Vcc
A1/A2_RTN
-Vcc
A1/A2_RTN
Installation
Remote control
1
MEMORY
CARD
COM
CARD
a11
1
PC +T/R
PC -T/R
SH
GND
PMU +T/R
PMU -T/R
R ON/OFF
15
+5V OUT
16
The connection and disconnection of the inverter to and from the grid
can be controlled through an external control.
The function must be enabled in the relevant menu. If the remote control
function is disabled, the switching on of the inverter is dictated by the
presence of the normal parameters that allow the inverter to connect to
the grid.
If the remote control function is operating, besides being dictated by the
presence of the normal parameters that allow the inverter to connect to
the grid, the switching on of the inverter also depends on the state of the
R ON/OFF terminal compared to the GND terminal present on the connector a11 of the communication card 09.
When the R ON/OFF signal is brought to the same potential as the GND
signal (i.e. by making a short circuit between the two terminals of the
connector), this causes the inverter to disconnect from the grid.
The remote control OFF condition is shown on the display.
The connections of this control are made between the R ON/OFF input
and GND. Since this is a digital input, there are no requirements to be
observed as regards cable cross-section (it only needs to comply with
the sizing requirement for passing cables through the cable glands and
the terminal connector).
Auxiliary 5 V output
There is an auxiliary 5 V output on connector a11. The maximum allowed absorption by this auxiliary supply voltage is 100 mA.
000028BG
SD card
- 66 -
Installation
MEMORY
CARD
COM
CARD
a05
1
Switch 1
0
0
0
0
0
0
0
0
0
0
0
0
1
1
1
1
1
1
F
Switch 2
0
1
5
6
8
9
A
B
C
D
E
F
0
1
2
3
6
7
F
000028BG
- 67 -
Installation
The settings become fixed after 24 hours of operation of the inverter (it
does not need to be connected to the grid, and only needs to be powered).
The time remaining before the settings become fixed can be seen in the
dedicated menu, and a notice appears if the time has expired.
Once the settings are fixed, turning the rotary switches will produce no effect. In this
condition, only the language can be changed through the dedicated menu.
At any time and for any reason, the ENGLISH language of the display menu can be set
by simultaneously pressing the ESC and ENTER buttons for at least 3 seconds.
000028BG
If it is necessary to change the standard of the country after the settings have been
fixed (after 24 hours of operation) please contact Power-Ones technical support department with the part number and serial number of the inverter to hand.
- 68 -
6
6 - Instruments
General conditions
One of the first rules for preventing damage to the equipment and to the
operator is to have a thorough knowledge of the INSTRUMENTS. We
therefore advise you to read this manual carefully. If you are not sure
about anything or there is discordance of information, please ask for
more detailed information.
Do not use the equipment if:
- you do not have suitable qualifications to work on this equipment or similar products;
- you are unable to understand how it works;
- you are not sure what will happen when the buttons or switches are operated;
- you notice any operating anomalies;
- there are doubts or contradictions between your experience, the manual and/or other
operators.
000029AG
- 69 -
Instruments
b1
b2
b3
b4
b5
b6
b7
b8
b9
23
b10
b17
b19
b23
DC
AC
b11
000030BG
N
b1
Symbol
b12
Function
Tx-R
b13
b14
b16
b15
b18
b21
b20
b22
Description
Indicates the transmission and reception of data through the RS485
line.
Indicates the presence of the RS485 communication line.
b2
RS485
b3
RF
b4
Bluetooth
b5
WiFi
b6
Warning
b7
Temperature
derating
b8
Instantaneous
power value
Displays the instantaneous power that the inverter is feeding into the
grid.
b9
MPP scan
b10
b11
Indicates that the MPP scan function has been enabled through the
menu.
Graphic Display Displays the inverter parameters in rotation and displays the error
codes (if present). It is used for moving through the menu.
Power graph Displays the power trend of the inverter (from 0 to 100%) over
8/16/24 hours; this parameter can be set.
- 70 -
Instruments
N
b12
Symbol
Function
Total Energy
Value
Description
Displays the total energy produced since installation of the inverter.
b13
Daily energy
value
b14
Photovoltaic
generator
b15
DC voltage
value
DC current
value
DC/DC circuit
part
DC/AC circuit
part
b16
b17
DC
b18
b19
123
b20
123
AC voltage
value
AC current
value
Connection
to the grid
b22
Grid status
b23
Cyclic display
activated/
deactivated
000030BG
b21
- 71 -
Instruments
Through the combination of LED panel 25 buttons, under the display 23,
values can be set or data can be displayed by scrolling them.
Some LEDs are also shown on the keypad 24 for status conditions.
23
24
POWER
ALARM
GFI
ESC
UP
DOWN
ENTER
25
ESC button
UP button
DOWN button
ENTER button
000030BG
In their various possible multiple combinations, the LEDs can indicate conditions that
are different from the original single one; see the various descriptions given in the
manual.
In their various possible multiple combinations, the buttons allow you to obtain actions that are different from the original single one; see the various descriptions given
in the manual.
- 72 -
7
7 - Operation
General conditions
Before checking the operation of the equipment, it is necessary to have
a thorough knowledge of the INSTRUMENTS chapter and the functions
that have been enabled in the installation.
The equipment operates automatically without the aid of an operator;
operating state is controlled through the instruments.
The interpretation or variation of some data is reserved exclusively for specialized and
qualified staff.
The incoming voltage must not exceed the maximum values shown in the technical
data in order to prevent damage to the equipment.
Consult the technical data for further details.
000031AG
Even during operation, check that the environmental and logistic conditions are correct (see installation chapter).
Make sure that the said conditions have not changed over time and that
the equipment is not exposed to adverse weather conditions and has
not been isolated with foreign bodies.
- 73 -
Operation
As a rule, the inverter operates automatically and does not require special checks. When there is not enough solar radiation to supply power
for export to the grid, (e.g. during the night) it disconnects automatically
and goes into stand-by mode.
The operating cycle is automatically restored when there is sufficient
solar radiation. At this point, the luminous LEDs on the LED panel 25 will
indicate this state.
000032BG
- 74 -
Operation
Commissioning
b2
b3
b4
b5
b6
b7
b8
b9
23
b10
b17
b19
b23
DC
AC
b11
b12
b13
b14
b16
b15
b18
b21
b20
b22
000033AG
Then, if there are no irregularities due to the checking of the grid voltage and frequency parameters, the grid connection sequence starts.
Once all the checks are finished, if all the grid parameters are complied
with, icon b22 comes on. During these checks, the icon b22 is flashing.
This check can take several minutes (from at least 30 seconds to no
more than a few minutes), depending on grid conditions and grid standard settings.
At this point, icon b17 flashes to indicate the start-up phase of the DCDC circuit part (booster). This icon will stay on steady once the booster
is operating at steady state (this icon will normally flash for only a few
seconds).
Almost at the same time as icon b17 comes on (steady), icon b18 will
come on to indicate that the inverter circuit part has begun working (DCAC).
- 75 -
Operation
Immediately after this, the procedure of connection to the grid will start,
during which icon b21 will come on and the icons on the line will be displayed in sequence until the inverter is connected. After the inverter is
connected, the icons on the whole line b21 will come on steady.
If the inverter disconnects from the grid, the icons of the left side (cable
and plug) of the line b21 will stay on.
Once the connection sequence has been completed, the inverter
starts to operate and indicates its correct operation by making a sound
and by the green LED coming on steady on the LED panel 25. This
means there is sufficient solar radiation to feed power into the grid.
If the checking of the grid does not give a positive result, the unit will
repeat the procedure until all the parameters that allow connection to
the grid (grid voltage and frequency, insulation resistance) are within the
range. During this procedure, the green LED flashes.
000033AG
At the end of the first starting of the inverter, the wiring box must be configured using
the dedicated Aurora Manager software. The software and relevant manual for carrying out this configuration are contained in the CD supplied with the inverter.
- 76 -
Operation
000033AG
If the icons b21 on the left side (cable and plug) stay on with the assembled plug off, it means the inverter is disconnected from the grid; if
the icons of the assembled plug and the pylons are on, it means the grid
is good for connection.
- 77 -
Operation
LED behaviour
= LED on
= LED flashing
= LED off
(x) = Any one of the conditions
described above
Status of the LEDs
green:
yellow:
red:
green:
yellow:
red:
green:
yellow:
red:
green:
yellow:
red:
green:
yellow:
red:
000034AG
green:
yellow:
red:
green:
yellow:
red:
green:
yellow:
red:
Operating state
Night mode (auto
switch-off of the
inverter)
Inverter initialization
(loading of settings and
wait for grid check)
Notes
The inverter is in night time switch-off mode (input voltage
70% less than the start-up voltage set for both inputs).
- 78 -
Operation
Next to each state of the inverter, indicated through the steady or intermittent lighting of the relevant LED, a message that identifies the operation it is carrying out or the detected fault/anomaly is also shown on the
display 23, section b10, (see relevant chapter).
b10
23
25
POWER
ALARM
GFI
ESC
UP
DOWN
ENTER
000035BG
If the inverter does not reconnect to the grid, make it safe by isolating it
(by means of the disconnect switches) on the both the DC side and the
AC side, and then contact the installer or an authorized service centre to
have the photovoltaic generator fault repaired.
- 79 -
Operation
The display 23 has a section b10 (graphic display) for moving through
the menu using the buttons of the LED panel 25.
Section b10 consists of 2 lines with 16 characters per line and can be
used to:
display the operating state of the inverter and the statistical data;
display the service messages for the operator;
display the alarm and fault messages for the operator;
changing the settings of the inverter.
b10
23
25
POWER
ALARM
GFI
ESC
UP
DOWN
ENTER
000035BG
- 80 -
Operation
Statistics menu
Selecting STATISTICS from the three main sub-menus gives access to:
Total
This section of the menu allows you to display the Total statistics:
Time: Total operating time
E-tot: Total energy produced
Val. : Total production value, calculated with the currency and conversion coefficient set in the relevant section of the SETTINGS menu
CO2: Amount of CO2 saved compared to fossil fuels
Partial
This section of the menu allows you to display the partial statistics:
Time: Partial operating time
E-par: Partial energy produced
PPeak: Peak power value
Val. : Partial production value, calculated with the currency and conversion coefficient set in the relevant section of the SETTINGS menu
CO2: Partial amount of CO2 saved
* To reset all the counters of this sub-menu, press the ENTER button
for more than 3 seconds. At the end of this time, you will hear a sound
repeated 3 times.
Today
This section of the menu allows you to display the daily statistics:
E-day: Daily energy produced
Ppeak: daily peak power value
Val. : Daily production value, calculated with the currency and conversion coefficient
set in the relevant section of the SETTINGS menu
CO2: Amount of CO2 saved daily
000035BG
Last 7 days
This section of the menu allows you to display the statistics for the last
7 days:
E-7d: Energy produced over the last 7 days
Val. : Value of production for the last 7 days, calculated with the currency
and conversion coefficient set in the relevant section of the SETTINGS
menu
CO2: Amount of CO2 saved over the last 7 days
- 81 -
Operation
Last month
This section of the menu allows you to display the statistics for the last
month:
E-mon: Energy produced during the current month
Val. : Value of production for the last month, calculated with the currency
and conversion coefficient set in the relevant section of the SETTINGS
menu
CO2: Amount of CO2 saved during the current month
Last 30 days
This section of the menu allows you to display the statistics for the last
30 days:
E-30d: Energy produced over the last 30 days
Val. : Value of production for the last 30 days, calculated with the currency and conversion coefficient set in the relevant section of the SETTINGS menu
CO2: Amount of CO2 saved over the last 30 days
Last 365 days
This section of the menu allows you to display the statistics for the last
365 days:
E-365: Energy produced over the last 365 days
Val. : Value of production for the last 365 days, calculated with the currency and conversion coefficient set in the relevant section of the SETTINGS menu
CO2: Amount of CO2 saved over the last 365 days
000035BG
User period
This section of the menu allows the statistics for a period selected by the
user to be displayed:
Once the start and end dates for the period have been set, the following
data are available:
E: Energy produced during the selected period
Val. : Value of production for the selected period, calculated with the
currency and conversion coefficient set in the relevant section of the
SETTINGS menu
CO2: Amount of CO2 saved during the selected period
- 82 -
Operation
Settings menu
When SETTINGS is selected from the three main sub-menus, the first
screen for the password is displayed in the display.
The default password is 0000.
This can be changed using the display buttons, always following the
same procedure:
Use ENTER to scroll the digits (from left to right)
Use ESC to return to the previous digit (from right to left)
Press ESC several times to return to the previous menus
Use DOWN to progressively scroll the numerical scale downwards
(from 9 to 0)
Use UP to progressively scroll the numerical scale upwards (from 0 to
9)
After entering the password, press ENTER to access the information
gathered in this section:
Address
This section of the menu allows you to set the address for the serial
communication of single inverters connected to the RS485 line.
The addresses that can be assigned are 2 to 63. Use the UP and DOWN
buttons to scroll the numerical scale.
At present, the AUTO selection cannot be used
Setting of Display
This section of the menu allows you to set the characteristics of the
display:
1. Light: setting of the mode and adjustment of the brightness of the
display
Mode:
On: Light always on
Off: Light always off
AUTO: Automatic light control. The light comes on whenever a button is
pressed and stays on for 30 sec, after which it gradually goes out.
Intensity: adjustment of display brightness (scale from 1 to 9)
2. Contrast: adjustment of display contrast (scale from 1 to 9)
3. Buzzer: button sound setting
On: the sound of the buttons is activated
Off: the sound of the buttons is deactivated
000035BG
Service
This section of the menu is reserved for installers. To access this, it is
necessary to have a dedicated password that will be provided by the
Power-One Service.
- 83 -
Operation
New PW
This section of the menu allows you to change the password for accessing the settings menu (default 0000).
000035BG
We advise changing the activation voltage only if really necessary and to set it to the
correct value: the photovoltaic generator sizing instrument available on the Internet
site of Power-One indicates whether it is necessary to change the Vstart and the value
to set.
Autotest
After the Autotest procedure, the following information is available:
- Nominal threshold (set in the inverter)
- Value of the quantity found during autotest
- Nominal operation time (set in the inverter)
- Operation time found
The values can be used to fill in the attached ENEL documents.
If the test is not passed, the machine stops until the test is passed.
The tests that can be carried out are the following:
Max Voltage: Disconnection from the grid due to Overvoltage that can
be carried out on the three phases R, S and T.
Min Voltage: Disconnection from the grid due to Undervoltage that
can be carried out on the three phases R, S and T.
Max Frequency: Disconnection from the grid due to Over Frequency
Min Frequency: Disconnection from the grid due to Under Frequency
- 84 -
Operation
Alarm
This section of the menu allows you to set the switching of a relay contact (available as a normally open contact N.O. and also as a normally closed contact N.C.). This contact can be used, for example, to:
activate a siren or a visual alarm, control the disconnect device of an
external transformer, or control an external device. Maximum ratings of
the alarm contact: 240Vac/1A and 30Vdc/0.8A
The switching of the relay can be set in 4 different modes:
PRODUCTION: the relay switches when the inverter connects to the
grid.
ALARM: the relay switches when there is an alarm (code E).
ALARM (conf.): the relay switches if there are alarms (code E) or warnings (code W) chosen by the user from a list (the list may also show
choices that are not envisaged for the specific model).
CREPUSCULAR: the relay switches only when it exceeds the input
voltage set for connection to the grid.
Remote Control
This section of the menu allows you to enable/disable the connection/
disconnection of the inverter to/from the grid through the relevant control
signal (R ON/OFF).
Disable: the connection/disconnection of the inverter to/from the grid
is dictated by the input (voltage from the photovoltaic generator) and
output (grid voltage) parameters of the inverter.
Enable: the connection/disconnection of the inverter to/from the grid is
dictated by the state of the R ON/OFF signal compared to the GND signal as well as by the input (voltage from the photovoltaic generator) and
output (grid voltage) parameters of the inverter.
000035BG
UV prot. T
This section of the menu allows you to set the time for which the inverter
stays connected to the grid after the input voltage has dropped below
the Under Voltage limit (set at 70% of Vstart). Power-One sets the time
at 60 sec. The user can set it at from 1 to 3600 sec.
Example: with the UV Prot.time set at 60 seconds, if the Vin drops below
70% of Vstart at 9:00, the inverter stays connected to the grid (taking
power from it) until 9:01.
MPPT
This section of the menu allows you to set the parameters of the maximum power point search (MPPT) function. This function is useful when
there are shadowed areas on the PV generator that can create several
maximum power points in the work curve.
MPPT amplitude: the amplitude of the interference introduced in DC
is chosen through the setting of this parameter to establish the optimal
working point. There are 3 settings to choose from (LOW, MEDIUM,
HIGH). The default setting is MEDIUM.
Multi-max scan: through the setting of this parameter, you can enable/
disable the scan, decide the frequency with which the scan is carried out
and override it manually.
- 85 -
Operation
Enable/Disable: Enables/Disables the scan for identifying the maximum power point of the system.
Scan Interval: this allows you to set the interval of time between scans.
It must be borne in mind that, the shorter the interval between scans, the
greater will be the loss of production due to the fact that, during the scan,
energy is transferred to the grid but not at the maximum power point.
Each scan takes 2 seconds.
Manual Scan: Allows you to start (asynchronously to the periodicity set
through the Scan Interval) the manual scanning of the photovoltaic generator for peak point tracking.
Analogue Inputs
This section of the menu allows you to set the analogue sensors connected at the input (AN1 and AN2)
Setting of Gain: Allows you to set the gain of the sensor
Setting of Offset: Allows you to set the offset of the sensor
Setting of Unit of M.: Allows you to set the unit of measure of the sensor
For further details, specifications and connection diagrams of
compatible Power-One sensors, consult the Installation chapter.
SENSORS PT100 AND PT1000
(can be directly connected to the corresponding analogue input; the
PT100/PT1000 inputs of the acquisition card do not require the configuration of gain and offset)
PVI-AEC-T100-ADH: adhesive PT100 sensor for module temperature
measurement
PVI-AEC-T100-BOX: PT100 sensor for ambient temperature measurement in IP65 container.
PVI-AEC-T1000-BOX: PT1000 sensor for ambient temperature measurement in IP65 container.
000035BG
Alarm Msg
This section of the menu allows you to enter a customized message that
is displayed on the display immediately after the specific error message
has been displayed.
Enable/Disable: Enables/Disables the display of customized messages
Writing of Msg: you can write your customized message that can be
written on two lines of 16 characters each. To write the message, use the
UP/DOWN arrows to choose the character you wish to enter and press
ENTER to confirm.
- 86 -
Operation
Information menu
Product ID
Allows you to display the product identification code.
Serial No.
Allows you to display the serial number of the equipment.
Firmware
Allows you to display the revision of the firmware installed in the equipment.
Country selector
Allows you to display information regarding the grid standard set with the
rotary selectors.
- Current value: Displays the set grid standard.
- New value: If the position of the rotary switches is changed (a new
grid standard is therefore selected) during operation, the new standard selected will be displayed but will be made effective only after the
equipment has been switched off and then on again and only if the time
remaining for carrying out this operation has not expired (24h of operation).
- Set new: Allows you to confirm/set the new grid standard set in the
New value section of the previous menu. When this function is used,
there will be no correspondence between the standard selected on the
display and the position of the rotary selectors.
- Time remaining: Displays the time remaining in which it is still possible to set a new grid standard. When the time expires, Locked will be
displayed, which indicates it is not possible to change the grid standard
again.
Fuse control (only for -S2X versions)
Strings: Displays the voltage and the state of the strings present at
the input of the equipment. A string can be in one of the following states:
OK, OFF (damaged) and ABS (absent)
Currents: Displays the current and the state of the strings present at
the input of the equipment. A string current can be in one of the following
states: OK, UNB (unbalanced current) and ABS (absent)
000035BG
Analogue Inputs
Allows you to display the reading of the measurements associated with
the two analogue inputs A1/A2.
- 87 -
Operation
AUTOTEST procedure
Complies with the guide for connections to the electricity grid of ENEL distribuzione
According to the guide for connections to the electricity grid of ENEL
distribuzione, the autotest can be started through the display menu or
using an RS485/USB converter through the dedicated interface software.
The necessary conditions for being able to carry out the Autotest are as
follows:
To have set the ENEL grid standard.
The inverter must be connected to the grid so as to be able to simulate
the disconnection condition.
Do not carry out any operations during execution of the test.
Check that the device is permanently connected to the grid.
Execution of the autotest through the display menu
Go to SETTINGS > Autotest >
OV Test R
OV Test S
OV Test T
UV Test R
UV Test S
UV Test T
OF Test
UF Test
In the section of the menu dedicated to the Autotest, the type of test the
device is to start can be selected from the following:
OV Test: Disconnection from the grid due to Overvoltage
UV Test: Disconnection from the grid due to Undervoltage
OF Test: Disconnection from the grid due to Over Frequency
UF Test: Disconnection from the grid due to Under Frequency
The OV and UV tests can be carried out on each single phase
(R;S;T)
000036AG
OV Test
During this test, the limit set for the maximum grid voltage (AC) is gradually reduced until the threshold is reached where disconnection of the
inverter from the grid occurs. A message indicating the start of the test
is shown on the display.
Test V= ... V
OK
T= ... ms
At the end of the test, when the inverter has disconnected from the grid,
the test result will be shown on the display.
Press the ESC button to go to the Autotest menu again to select the next
test to be carried out.
- 88 -
Operation
Test in progress
.....
Test V= ... V
OK
T= ... ms
UV Test
During this test, the limit set for the minimum grid voltage (AC) is gradually increased until the threshold is reached where disconnection of the
inverter from the grid occurs. A message indicating the start of the test
is shown on the display.
At the end of the test, when the inverter has disconnected from the grid,
the test result will be shown on the display.
Press the ESC button to go to the Autotest menu again to select the next
test to be carried out.
Test in progress
.....
OF Test
During this test, the limit set for the maximum grid frequency (Hz) is
gradually reduced until the threshold is reached where disconnection of
the inverter from the grid occurs. A message indicating the start of the
test is shown on the display.
Test F= ... Hz
OK
T= ... ms
At the end of the test, when the inverter has disconnected from the grid,
the test result will be shown on the display.
Press the ESC button to go to the Autotest menu again to select the next
test to be carried out.
Test in progress
.....
UF Test
During this test, the limit set for the minimum grid frequency (Hz) is gradually increased until the threshold is reached where disconnection of the
inverter from the grid occurs. A message indicating the start of the test
is shown on the display.
Test F= ... Hz
OK
T= ... ms
At the end of the test, when the inverter has disconnected from the grid,
the test result will be shown on the display.
Press the ESC button to go to the Autotest menu again to select the next
test to be carried out.
000036AG
Once one of the tests (of the Autotest section) has been started, it takes place automatically. After the test has finished correctly, the inverter restores the factory-set
switch-off values.
- 89 -
8
8 - Maintenance
General conditions
Checking and maintenance operations must be carried out by specialized staff assigned to carry out this work.
Maintenance operations must be carried out with the equipment disconnected from
the grid, unless otherwise indicated.
For cleaning, DO NOT use rags made of filamentary material or corrosive products
that may corrode parts of the equipment or generate electrostatic charges.
Avoid temporary repairs. All repairs should be carried out using only genuine spare
parts.
The maintenance technician is under an obligation to promptly report any anomalies.
DO NOT allow the equipment to be used if problems of any kind are
found, and restore the normal conditions correctly or in case make sure
this is done.
Always use the personal protective equipment provided by the employer and comply
with the safety conditions of the Accident prevention chapter.
Power-One accepts no liability if the checking and maintenance cycles
indicated in this manual and in the attached documentation are not complied with correctly, and also when maintenance is entrusted to unqualified staff.
000037AG
To maintain the correct working performance, have the systems checked by your installer
after about 5 years of activity.
- 90 -
Maintenance
Routine maintenance
200 h
1,000 h
1,000 h
2,000 h
Special maintenance
Special maintenance operations can be carried out only by the installer
or qualified staff.
1,000 h
1,000 h
000038BG
1,000 h
2,000 h
Maintenance
Alarm Messages
b10
23
25
000038BG
POWER
ALARM
GFI
Cause
ESC
UP
DOWN
ENTER
Display
Message
Display
Codes
Alarm
Solution
Ground
Fault
Red LED
Degauss
error
---
Degaussing
state fail
Input OC
E001
Input
Overcurrent
The alarm appears when the inverter You must check whether the composition of the PV generator
input current exceeds the set overcurrent allows an input current that exceeds the maximum threshold
threshold.
allowed by the inverter and that the configuration of the
(independent or parallel) inputs is carried out correctly.
If the configuration of the PV generator and the setting of the
input channels are suitable, contact thePower-one Service
Input OV
E002
Input
Overvoltage
No
Parameters
E003
Internal
Parameters
Error
The main microcontroller is unable to This is an error inside the inverter that cannot be checked
correctly initialize the two DSPs (booster externally. If the problem persists (after switching the inverter
off and then on again), contact the Power-one Service.
stage and inverter stage).
This is usually due to communication
problems on the internal bus of the
inverter.
Bulk OV
E004
Bulk
Overvoltage
- 92 -
Maintenance
Comm.Error E005
Internal
cation Error
The alarm occurs when there are Error inside the inverter that cannot be checked externally.
communication problems between the If the problem persists (after switching the inverter off and
control devices inside the inverter.
then on again), contact the Power-one Service.
Output OC
E006
Output
Overcurrent
The alarm appears when the inverter Error inside the inverter that cannot be checked externally.
output current exceeds the output If the problem persists (after switching the inverter off and
overcurrent threshold of the inverter.
then on again), contact the Power-one Service.
IGBT Sat
E007
IGBT
Saturation
The alarm appears when one of the Once the error appears, the inverter attempts to resume
active devices of the inverter is in normal operation. If the error occurs sporadically, it may be
saturation state.
caused by a sharp transition of the grid voltage or the input
voltage but is not attributable to inverter malfunctioning.
If the error is associated with an internal fault, it will continue
to appear, and you must therefore contact the Power-one
Service.
000038BG
Bulk Low
E010
Low Bulk
Voltage
Ramp Fail
E011
Bulk ramp
timeout
Error inside the inverter regarding the Error inside the inverter that cannot be checked externally.
time for starting steady state operation If the problem persists (after switching the inverter off and
of the DC-DC circuit part (Booster).
then on again), contact the Power-one Service.
DcDc Fail
E012
Booster
module error
revealed by
Inverter
Error inside the inverter regarding the Error inside the inverter that cannot be checked externally.
operation of the DC-DC circuit part If the problem persists (after switching the inverter off and
(Booster).
then on again), contact the Power-one Service.
Wrong
Input Mode
(parallel
instead of
independent)
Make sure the setting of the "IN MODE" switch has been
intentionally positioned on "PAR" and that the jumpers have
been inserted between the two input channels.
If the configuration of the inverter is correct, check that the
input strings have the usual number of panels in series, of
the usual make and with the same inclination/orientation. If
both the configuration of the inverter and the characteristics
of the PV generator comply with the specifications, contact
the Power-one Service.
Over Temp.
E014
Overtemperature
Bulk Cap
Fail
E015
Bulk
Capacitor
Fail
Error inside the inverter regarding a Error inside the inverter that cannot be checked externally.
problem in the bulk capacitors.
If the problem persists (after switching the inverter off and
then on again), contact the Power-one Service.
Inverter Fail
E016
Inverter
module error
revealed by
Booster
The alarm is generated when a problem Error inside the inverter that cannot be checked externally.
is detected in the inverter circuit part If the problem persists (after switching the inverter off and
(DC/AC).
then on again), contact the Power-one Service.
Start
Timeout
E017
Inverter
Error inside the inverter regarding the Error inside the inverter that cannot be checked externally.
module start- time for starting steady state operation If the problem persists (after switching the inverter off and
up timeout
of the DC-AC circuit part (Inverter).
then on again), contact the Power-one Service.
Ground
Fault
E018
Leakage
current fail
- 93 -
Maintenance
Self Test
Error 3
E019
Leakage
current
sensor selftest fail
Self Test
Error 1
E020
Self Test
Error 2
E021
Self Test
Error 4
E022
Time taken to execute the autotest Error inside the inverter that cannot be checked externally.
carried out on the relays of the DC_AC If the problem persists (after switching the inverter off and
circuit part (inverter) is too long. This then on again), contact the Power-one Service.
may indicate a problem associated with
the aforesaid relays.
DC inj error
E023
Dc-Injection
out of range
The error is generated if the direct If the grid voltage is strongly distorted, report this anomaly
component of the current supplied to to the grid company for the resolution of the problem
the grid exceeds the threshold of 0.5% If there is an inverter fault, contact the Power-one Service.
of the rated operating current.
In any case, the inverter does not stop
because of the E023 error, but tries to
connect to the grid again.
Sporadic repetition of the error is a sign of
large grid distortions or sudden changes
in irradiation, whereas systematic
repetition of the error warning will be a
sign of an inverter fault.
Riso Low
000038BG
E025
(not
shown
on the
display)
Low
insulation
resistance
- 94 -
Maintenance
Vref Error
E026
Bad internal
reference
voltage
Wrong measurement of the reference Internal error that cannot be checked externally. If the
voltage inside the equipment
problem persists (even after switching the inverter off and
then on again), contact the Power-one Service.
Error Meas
V
E027
VGrid
Measures
Fault
Error Meas
F
E028
FGrid
Measures
Fault
Error Meas
Z
E029
ZGrid
Measures
Fault
Error Meas
Ileak
E030
ILeak
Measures
Fault
Error Read
V
E031
Wrong V
Measure
Measurement of the internal voltage at This is an error inside the inverter that cannot be checked
the ends of the output relay out of range. externally. If the problem appears repeatedly, you must
There is too great a difference in voltage contact the Power-one Service.
between the input and the output of the
output relay.
Wrong I
Measure
Measurement of the output voltage This is an error inside the inverter that cannot be checked
unbalance (carried out between the externally. If the problem appears repeatedly, you must
three phases) out of range (only in contact the Power-one Service.
three-phase models).
UTH
E033
Under
Temperature
Temperature outside the inverter below Wait for the temperatures to which the inverter
-25C
is exposed to return within operating range.
If the problem persists, contact the Power-one Service.
You must remember to wait for the time necessary to allow
the inverter to warm up.
Interlock fail
E034
IGBT not
ready
Remote Off
E035
(not
shown
on the
display)
Waiting
remote ON
E036
Average
Vout out of
range
Vout Avg
error
000038BG
- 95 -
Maintenance
000038BG
Riso Low
E037
Low
insulation
resistance
(amorphous
mode only)
Mid bulk OV
Sun Low
W001
(Low input
voltage
during
switch-on
on of the
inverter)
Insufficient irradiation.
Wrong configuration of the PV generator
or a configuration at the limit as
regards the minimum input voltage of
the inverter.
Input UV
W002
(Low input
voltage
during
switch-off)
Insufficient irradiation
Wrong configuration of the photovoltaic
generator or a configuration at the limit
as regards the minimum input voltage
of the inverter.
Grid Fail
W003
Grid Fail
(grid voltage
parameters
outside the
limits)
Table fail
W009
Empty Wind
Table
Fan Fail
W010
(not
shown
on the
display)
Fan Fail
Bulk UV
W011
Bulk Undervoltage
Battery low
W012
Low internal
clock battery
voltage
Internal battery for maintenance of Replace the battery with the inverter completely switched off
the date/time settings is discharged or (disconnect AC side and DC side) and be sure to observe
damaged.
the correct polarity.
Clk fail
W013
Internal clock The alarm appears when the time This is an error inside the inverter that cannot be resolved
fail
shown on the display differs by more with external operations. If the alarm is persistently repeated,
than 1 minute from the internal time of contact the Power-one Service.
the microprocessors and indicates clock
circuit malfunctioning.
Jbox fail
W017
Fuse-control
board fail
(DC string
fail)
Fuse(s) on the fuse boards is/are Using a multimeter, check the condition of the fuses (situated
damaged.
on the fuse boards).
Replace any open fuses and check that the input current on
the string(s) does not exceed the rating of the fuses (if string
parallels have been made outside the inverter).
If there are no damaged string fuses and the inverter
continues to display the alarm message, check whether
the settings to be made through the Aurora Manager
software are correct (presence or absence of one or more
input strings).
- 96 -
Maintenance
W018
SPD DC
protection
open
Overvoltage surge arresters situated on Look at the inspection window present on each surge
the DC side are damaged.
arrester (DC side). If it is red, the surge arrester is damaged
and the cartridge must be replaced.
If the alarm status continues to be present even though all
the surge arresters have a green inspection window, contact
the Power-one Service.
SPD AC
protection
open
W019
SPD AC
protection
open
Overvoltage surge arresters situated on Look at the inspection window present on each surge
the AC side are damaged.
arrester (AC side). If it is red, the surge arrester is damaged
and the cartridge must be replaced.
If the alarm status continues to be present even though all
the surge arresters have a green inspection window, contact
the Power-one Service.
000038BG
SPD DC
protection
open
- 97 -
Maintenance
If the inverter has reported a ground fault, there may be a ground leakage from the PV generator (DC side).
To check this, measure the voltage between the positive pole and ground
and between the negative pole (of the PV generator) and ground using a
voltmeter whose input accepts a voltage of at least 1000 Volts.
V
+Vs
t
Voc
-Vs
(-)
How to make the measurement:
(+)
000040AG
Volt
- 98 -
Maintenance
If the voltage measured between one of the two poles and ground does
not tend to 0V and stabilizes on a value, there is a ground leakage from
the PV generator.
Example: When the measurement is made between positive pole and
ground, a voltage of 200V is measured.
V
200 V
t
300 V
Va
1
50 V
50 V
50 V
50 V
50 V
50 V
50 V
(+)
8
50 V
9
50 V
10
50 V
(-)
000040AG
- 99 -
Maintenance
FV
(+)
IG
(-)
Once the short-circuit has been made, measure the insulation resistance (Riso) using a megohmmeter positioned between the two shorted
poles and ground (of the inverter).
FV
(+)
IG
(-)
Mega
Inverter
If the Riso is less than 1 MOhm, the inverter does not connect to the grid
because of low insulation of the PV generator to ground.
000043AG
- 100 -
Maintenance
000039AG