Method Statement River Crossing

This document outlines the method statement for building a cable tray river crossing for a solar power plant in Gorontalo. It involves installing pile foundations using a diesel pile hammer and crane truck. The pad footings will be constructed by excavating, laying concrete, placing reinforcement cages, and pouring and compacting more concrete to form the foundation base. Next, the superstructure will be placed using a roller launch method where the bridge is constructed in situ and then jacked across the span using rollers and cantilever technique. Finally, the cable tray will be placed on the bridge and safety risk assessments will be conducted for the initial site setup and various construction activities.

Uploaded by

Deny Cahyo N
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
1K views2 pages

Method Statement River Crossing

This document outlines the method statement for building a cable tray river crossing for a solar power plant in Gorontalo. It involves installing pile foundations using a diesel pile hammer and crane truck. The pad footings will be constructed by excavating, laying concrete, placing reinforcement cages, and pouring and compacting more concrete to form the foundation base. Next, the superstructure will be placed using a roller launch method where the bridge is constructed in situ and then jacked across the span using rollers and cantilever technique. Finally, the cable tray will be placed on the bridge and safety risk assessments will be conducted for the initial site setup and various construction activities.

Uploaded by

Deny Cahyo N
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

METHOD STATEMENT FOR CABLE TRAY RIVER CROSSING

1. GENERAL

River crossing work procedure of building for Gorontalo Solar Power


Plant is to demonstrate the process of making bridge for cable tray.
2. Equipment
- Diesel Pile Hammer
- Crane Truck
- Theodolite
- Survey Equipment
- Automatic Level
3. Bridge Construction Sequence
Foundation are required for abutments. Foundations can be either
concrete pad pile.
1. Instal Pile Foundation
2. Pad footings are generally constructed as follows:

excavation to a depth of approximately 2.5 metres below


formation level

laying a concrete layer

fabricating cages of steel reinforcement, which is done on site,


with bars protruding vertically to required level

Placing formwork for the foundation slab.

Transporting concrete to the site and pouring and compacting


the concrete, by vibration to required level

Leaving the concrete for a period of time to enable it to cure


before stripping the formwork to from foundation base

3. Supper Structure Placement


Roller launch method. The bridge is constructed in situ and then
jacked across the span using rollers and cantilever technique.

4. Placement Cable Tray


4. Safety
The following Safety Risk Assessments are relevant to the works and will be
produced by competent persons and attached to the detailed Method Statement
in accordance with the Construction Phase Plan:

Initial site setup

Manual Handling

Working at Height

Slips, trips and falls

Power tools

Working near mobile plant and plant movement

Lift Plans

Surfacing works