Project Management Plan
Project Management Plan
ASSIGNMENT ON
PROJECT MANAGEMENT PLAN
DISPLAY SUITE FITOUT FOR QUEEN VICTORIA STREET
FREMANTLE APARTMENTS WA
AMD CONSTRUCTION
204 BROKE STREET
SYDNEY, NSW 2000
SUBMITTED BY:
ANH NGUYEN PHAM (S0252679)
BHUWAN GIRI (S0273826)
RAMESH BHATTARAI (S0266380)
SUMAN BALLA (S0276219)
TABLE OF CONTENTS
INTRODUCTION (BHUWAN)
PROJECT MANAGEMENT APPROACH
PROJECT SCOPE
MILESTONE LIST
SCHEDULE BASELINE AND WORK BREAKDOWN STRUCTURE (SUMAN)
CHANGE MANAGEMENT PLAN
COMMUNICATIONS MANAGEMENT PLAN
COST MANAGEMENT PLAN
PROCUREMENT MANAGEMENT PLAN (RAMESH)
PROJECT SCOPE MANAGEMENT PLAN
SCHEDULE MANAGEMENT PLAN
QUALITY MANAGEMENT PLAN
RISK MANAGEMENT PLAN (RAY)
RISK REGISTER
STAFFING MANAGEMENT PLAN
RESOURCE CALENDAR
COST BASELINE
2
QUALITY BASELINE
SPONSOR ACCEPTANCE
1. INTRODUCTION
This project management plan encompasses all the required plans and sub-plans which are
rudimentary for success of a project. This project report includes the total budget and the number
of employees and the equipment required for the execution of the project in a given time frame
for each work. All the information is provide below in the project plan.
1.1 Purpose
The primary purpose of this project, Display suite fit out, includes demolition of existing interior
with construction, furnishing, electrical works, lighting and finally plantation and landscaping on
the basis of detail demolition and construction drawings provided by Hassell Architectural
Design as discussed earlier.
1.1.1 Plan description
It is a commercial suit design for apartment. In fact it is like a dummy so that the
stakeholder can see what the company is going to build in the near future.
1.1.2 Plan pre requisite
Architectural drawing is the first prerequisite for the project, Cost is another factor, working
hour and time also plays important role too.
1.1.3 External Dependencies
Social factor like noise pollution, air pollution may occur during dismantle work, work cannot
commence at night, to reduce sound pollution and complains.
1.1.4 Monitoring and control
Project manager is responsible for the monitoring and control of the whole project. Frequent
monitoring and control is necessary so that the project is completed in right time with
correct budget
1.1.5 Budget
As the project is sponsor by DHA, DHA is paying the money for this project. The budget of
our project is AUD 39,000.00. and the time for the completion is 85 days approx..
1.1.6 Tolerance
There is 10% tolerance in both working time and in budget. It is because any incident can
postpone the work schedule which cause delay in completing the task which ultimately lead
to raise in finance.
3
1.1.7 Schedule
The schedule of our project is shown in Gantt chart which is attached in the appendix.
change in the plan or date should be informed to the team members of the project by the project
manager.
3. PROJECT SCOPE
The scope of this project includes the planning, design, development, testing, and re-construction
of the apartment. This project will meet or exceed organizational standards and additional
requirements established in the project charter. The scope of this project also includes
completion of all documentation, manuals, and training aids to be used side by side with the
demolition and construction process. Project completion will occur when the demolition,
construction and documentation have been successfully executed. All project work will be
performed internally and no portion of this project will be outsourced.
4. MILESTONE LIST
The table given below shows the milestones for the demolition and re-construction of the given
project. This project includes only major milestones of the project and rest of sub-plans are
described in other parts of project plan are described in other sub headings and WBS. If delay
happens during the project execution which may affect the milestone then the manager should be
notified as soon as possible so as to avoid the delays and to provide the delivery on time. Any
change in the plan or date should be informed to the team members of the project by the project
manager.
Milestone
Demolition Floor Work
Description
Date
All equipments and labours are required demolish the 22/02/20
floor. Demolition of tiles, removing skirting,
16
removing carpets
This includes demolition of ceiling tiles, removing
8/03/201
29/04/20
16
brickwork.
This includes re-alignment work of vent and grill,
26/05/20
16
Schedule baseline is the approved project schedule and is part of project plan (PMBOK 2013).
The project Display suite fitout for Queen Victoria Street consists of work packages which are
more than 8 hours to but do not cross 56 hours of work. The project work packages were
formulated with sound collaboration among the team personnels and inputs from various sources
from the past were too incorporated. All work packages are defined in the WBS Dictionary for
this refurbishment project which include all tasks, resources, and deliverables. Every work
package in the WBS is defined in the WBS Dictionary and will aid in resource planning, task
completion, and ensuring deliverables meet project requirements.
All team individuals contributed for this project and the schedules were taken from WBS and
ProjectCharter. Only after the approval of project sponsor, the project got base-lined. Further
schedule are to be updated with Ms Project by the Project Manager. If there are to be any
proposed changes to the current schedule, it will follow control process. With the combined
consensus of project manager and team, the determination of the effects on the change on
schedule, resources, cost and risks will be carried out.If there is to be changes, it should be
approved by the Project Sponsor which will then be incorporated by Project Manager in all
stages.
The Project Schedule Baseline and Work Breakdown Structure are provided in Appendix A,
Project Schedule and Appendix B, Work Breakdown Structure.
The communication matrix of project team presented below encompases the communications
requirements. It will be a guideline for information communication.
Name
Title
Jarvis John
Project Sponsor
Richard
Mac
Project Manager
Cullum
Kenya
Kent
Smith
Young
Civil
Engineer
Tek Karki
Supplier
Quality
Specialist
Suman Bang
Foreman
E mail
Office Phone
[email protected]
om
richardmc@gmail.
com
KenyaKent@gmail
.com
smithyoung@gmai
l.com
sumanban@gmail.
com
[email protected]
0436988948
0436599944
0436598912
0436598458
0436597895
043654548
Cell
Communication
Phone
preference
043659894 Collaborative
7
043659894
6
043959894
5
046329894
5
043458945
043779894
5
Environment
Email
Cell Phone
Schedule
Office Phone
Cell Phone
Civil engineer:
Civil engineer sees if the site works are running according to planned drawings
Foreman:
Foreman guides the general labor in carrying out laboring works
7.2 Communication method and technologies:
A common method of communication is to be established for communication. Google
Drive can be incorporated to share data and files among the team members. All team members
should possess basic understanding of MS project and ability to develop, maintain and
communicate schedule. Further, every team member is given with a personal profile with own
username and password to access their portals online in a common platform or company
website.
SN
Description
Order Date
10
Received Date
Remarks
Bricks
Sand
Cement
Nails, Glue,
Tiles
Furniture works
1 Refurnishing an apartment
1.3 Finishing
worksceiling works
1.4Floor
Finishing
11
WBS Name:
Work Package?
1.1
WBS Predecessor(s):
Yes / No
None
Must-Start Date:
02/02/2016
Must-Finish Date:
03/02/2016
WBS Estimated Effort:
2 days
Assigned to:
Team Leader: Michael
Robert (Phone:
0449133556)
Project manager: James
Smith (Phone:
0424445667)
Technical information: Workers try to avoid break the concrete and the finishes of the
internal and external brick wall nearby to prevent the cost to fix that place, and must be
follow the safety instruction during performing task
Quality requirement: After completion, the quality must be checked by expert and project
manager, and the following task can be conducted conveniently.
12
Acceptance criteria: Tasks are met the expectations of the expert and done on schedule of
the project. There is no risk occur in the next following task
In our project we have different WBS dictionary. As we can see it has all the points that easily
describes the Project scope management plan. We have attached the other WBS dictionary at the
end.
Costs of quality
Duration Estimating
Straightforward approach to the estimation of activity durations is to keep historical records of
particular activities and rely on the average durations from this experience in making new
duration estimates. Since the scope of activities are unlikely to be identical between different
projects, unit productivity rates are typically employed for this purpose. For example, the
duration of an activity Dij such as concrete formwork assembly might be estimated as:
ID
Descrip
Name
tion
Predecessor
ID Relations
3
4
5
6
7
8
9
10
11
3
3
3
6
7
8
9
10
hip
FS
SS
FS+1day
SS
FS
FS
FS
FS
13
14
15
15
16
11
13
14
15
16
FS+2days
FS
FS+1day
FS
FS+1day
20
Brickwork
19
SS
14
Successor
Relati
ID
onship
21
22
23
24
25
26
27
28
29
31
32
33
34
Tile Works
Doors and Windows
Water supply
Sanitary works
Sanitary and CP Fixtures
Electrical Works
Electrical Fixtures
Furniture Work
Internal Painting work
Re Alignment works of vent and grill
Tile works
Fiber cement works
Roof and external Painting works
20
20,2
20,2
23
24
23
26
27
28
29
31
32
33
FS
20SS
20FS
FS
FS+1day
FS
FS+1day
FS
FS
FS+2days
FS
FS
FS
15
16
14.RISK REGISTER
Existing controls described &
Evaluation
evaluated
form of Risk
Reschedule or take
Over costing more
than budget allocated
Machinery break
down
a bank loans
(L, M, H or
ENTITY>.
What we will do
Effectively assign
P
Yes
Get in agreement
delay in tasks
Assign the task
effectively to
No
avoiding delay or
assign more
completion day
workers to do the
Hire another
delayed tasks
have a technicians
machines or need
the assist of
technical expert
17
VH - see Sheet 1)
VULNERABLE
risk.
(L, M, H or VH - see
<INSERT
(A, B, C, D or E -
in/to/on/for/of
(1, 2, 3, 4, or 5 - see
IMPACT>
to manage this
Current Effectiveness
will <INSERT
What we do now
Sheet 1)
<INSERT EVENT>
Sheet 1)
see Sheet 1)
For example,
Statements(s) below.
Further Actions
Risk level
Likelihood
Consequence
Identified Risks
Risk Description
Analysis &
No
shortage materials
good security
N
No
Material shortage
workers to
perform task on
construction site or
No
always follow
employees'
schedule
seek another
engagement
have agreement
reliable suppliers
with a few
hire additional
Employee turnover
system at the
No
suppliers to
prevent shortage of
Political issue
materials
conduct project
when satisfying
No
political conditions
as approval of
Competition
government
have good
management
to compete with
system to improve
other competitors
Yes
performance that
can produce the
Yes
fluctuation of the
changing of the
prices of materials
agreement with
to avoid loss
stakeholder
regarding the
18
changing of price
Team leaders (3 positions): who are responsible for each specific tasks such as, brickwork,
finishes, plumbing, and electrical work
THE PROJECT MANAGER WILL NEGOTIATE WITH ALL NECESSARY TSI FUNCTIONAL
MANAGERS IN ORDER TO DETERMINE AND ALLOCATE RESOURCES FOR THE
DISPLAY SUITE
FOR THIS PROJECT AND ALL RESOURCES WILL REMAIN IN THEIR CURRENT WORKSPACE.
16.RESOURCE CALENDAR
The Display Suite Fitout Queen Victoria Street, Fremantle Apartments WA Project will require
all project team members for the entire duration of the project although levels of effort will vary
as the project progresses. Project team is required to work 40 hour work weeks. If a project
team member is not required for a full 40 hour work week at any point during the project, their
efforts outside of the Display Suite Fitout Queen Victoria Street, Fremantle Apartments WA
will be at the discretion of different functional work. The following graph below show the total
effort hours of project team on different main tasks monthly.
200
180
160
140
120
hours 100
demolition ceiling
80
60
finished work on
ceiling
40
20
0
February March
April
May
Month
20
17.COST BASELINE
The cost baseline for the Display Suite Fitout for Queen Victoria Street, Fremantle Apartments
WA project includes all budgeted costs for the successful completion of the project.
Project Manager:
Project Name:
Apartments WA
To complete the
Project
demolition and
Project Sponsor:
Objective:
DHA
of display suite
Date prepared:
Prepared by:
Submitted to:
Total Cost
AMD Constructions
DHA
12/01/2016
$39,600
Date: 01/02/2016
Authorization:
Expense
Labor
In-house
General Labor
Day
Hr
No. of
Tota
worker
Hrs
96
Uni
t
Total
Cum
Cos
Cost
Cost
$2,400
$2,400
purpose
source
t
$25
Laying
Raised from
protection,
investor
Removal of
rubbish from
demolition,
data, skirting,
21
funding
GPOs,
protection
works and
cleaning on
regular basis
Demolition of
Skilled Labor
(demolishers)
12
192
$25
$4,800
$7,200
carpet tiles,
Raised from
walls, ceiling
investor
tiles, grids
Removal of
lights and
electric
Electrician
13
208
$25
$5,200
$12,40
0
fittings before
demolition
and
Raised from
investor
installation of
new lights and
data points
Painting of
Painter
96
$25
$2,400
$14,80
walls, doors,
Raised from
frame and
investor
ceiling
$25
$25
Contract
Brick Worker
56
$25
$1,400
$16,20
Completion of
brick works
Removal of
windows and
Carpenter
112
$25
$2,800
$19,00
installation of
Raised from
investor
other furniture
Tile Layer
96
$25
22
$2,400
$21,40
works
Laying of tiles Raised from
on floor and
ceiling
Laying and
investor
fixing of Hot
Plumber
112
$25
$2,800
$24,20
pipes, sanitary
investor
works,
fixtures
Administrative
material
supplies( brick
s, tiles
zyprock,
ceiling tiles,
electrical
Supplies
$8,000
$32,20
fixtures and
Raised from
points,
investor
sanitary and
water supply
pipes and
fixtures,
cement,
paints)
Equipment
$2,900
Refreshments
$1,000
Travel
$1,000
Technology
$2,500
$39,60
TOTAL
0
23
$35,10
0
$36,10
Raised from
0
$37,10
investor
Raised from
0
$39,60
investor
Raised from
investor
18.QUALITY BASELINE
The Display Suite Fitout for Queen Victoria Street, Fremantle Apartments WA Project must meet
the quality standards established in the quality baseline. The quality baseline is the baseline
which provides the acceptable quality levels of the project. The deliverables must meet or
exceed the quality baseline values in order to meet the satisfaction of stakeholders.
Item
Brickwork
Acceptable Level
Sound structure and nice
Finished job
outlook, sustainable
Nice interface, durable at less
Display job
3 years
Meet the drawing
Tiles work
requirements,
Smooth interface, nice look
Electrical work
and sustainable
Durable, working well, well-
Demolition job
organized display
Not occurring risk for next
Plumbing job
task
Well-organized and durable
pipes system, sustainable for 1
year
24
25
Appendix A
Project Schedule
26
Appendix C
WBS Dictionary
WBS Number:
WBS Name:
Work Package?
Yes / No
skirting
WBS Description:
None
Must-Start Date:
02/02/2016
Must-Finish Date:
09/02/2016
WBS Estimated Effort:
5 days
Assigned to:
Team Leader: Robert
Lavender (Phone:
0449123456)
Project manager: James
Smith (Phone:
0424445667)
27
Technical information: Avoiding workers occupying same work room can prevent task delay,
and have to be follow the safety instruction during performing task
Quality requirement: After completion, the quality must be checked by expert and project
manager, and the following task can be conducted conveniently.
Acceptance criteria: Tasks are met the expectations of the expert and done on schedule of the
project. There is no risk occur in the next following task
28
WBS Number:
WBS Name:
Work Package?
Remove lighting,
Relocate
existing lights
grid, ceiling
and electrical
tiles
Yes / No
1.2.2
1.2.1
WBS Predecessor(s):
WBS Description:
1.2.1
1.1.3
Must-Start Date:
electrical
ceiling
tiles and grids
Resources: Labor, equipment,
Resources: Labor, equipment,
07/03/16
02/02/2016
Must-Finish Date:
08/03/16
03/02/2016
WBS Estimated Effort:
52 days
Assigned to:
Team Leader: Alice
Jordan
Hens
(Phone: 0449133559)
0449133556)
Project manager: James
Smith (Phone:
0424445667)
Technical information: There
To perform
is needthis
of work
properpackage,
and experienced
there is amanpower
use of various
as it is ceiling
work, Need tomaterials
construction
considerand
about
tools
thesuch
safety
as drill,
of workers.
hammer,
At and
firstlifter
electrical
if necessary.
lights are
There
removed
is need
and
all proper
of
wires are
andremoved
experienced
and then
manpower
only we
ascan
it isrelocate
ceiling work,
the grid
Need
work.
to consider about the safety
Quality
requirement: After completion, the quality must be checked by expert and project
of
workers.
manager,requirement:
Quality
and the following
After task
completion,
can be conducted
the qualityconveniently.
must be checked
Especially
by expert
the and
circuit
project
work,
cable, lighting
manager,
Especially
fixture,
theAlso
circuit
the work
tile works
and the
as ittile
is works
ceilingasworks
it is ceiling
and may
works
haveand
chance
may of
have
leakage.of leakage and slope maintain in the ceiling.
chance
Acceptance criteria: Tasks are met the expectations of the expert and done on schedule of
the project. There is no risk occur in the next following task
29