Rail Code of Practice
Rail Code of Practice
Category:
Code of Practice
Rail
Section 1
Applicability
ARTC Network wide
Primary Source
Document Status
Version
Date Reviewed
Prepared by
Reviewed by
Endorsed
Approved
3.1
12 Aug 13
Standards
Stakeholders
Manger
Standards
General Manager
Technical Standards
& Environment
16/08/2013
Amendment Record
Version
Date Reviewed
Clause
Description of Amendment
3.0
02 Nov 12
1.1.1(b)(c)(d),
1.4.3, 1.4.12
& Table 1.2A
Reissue of document. Supersedes version 2.8. Significant rewrite due to a change of methodology of managing rail wear
limits. Further updates made following stakeholder consultation.
3.1
12 Aug 13
1.4.13
This ARTC CoP has drawn on the Rail Industry Safety and Standards Board (RISSB) National
Code of Practice Volume 4, Track and Civil Infrastructure, but is not identical. The ARTC CoP has
been subject to Risk Assessment as required by the various State Rail Safety Regulators. The
results of these risk assessments have made it necessary to deviate from the RISSB CoP in
some areas. ARTC maintains traceability of the differences.
Australian Rail Track Corporation Limited 2013
Disclaimer:
This document has been prepared by ARTC for internal use and may not be relied on by any other party without ARTCs prior written consent.
of this document shall be subject to the terms of the relevant contract with ARTC.
Use
ARTC and its employees shall have no liability to unauthorised users of the information for any loss, damage, cost or expense incurred or arising by
reason of an unauthorised user using or relying upon the information in this document, whether caused by error, negligence, omission or
misrepresentation in this document.
Authorised users of this document should visit ARTCs intranet or extranet (www.artc.com.au) to access the latest version of this document.
Contents
Contents
1
Section 1: Rail......................................................................................... 4
1.1
1.2
1.3
Commissioning .................................................................................26
1.4
Version 3.1
Page 2 of 37
Contents
Version 3.1
Page 3 of 37
Contents
Section 1: Rail
1.1
Rail size
The recommended minimum rail sizes are given in Table 1.1A.
Table 1.1A - Rail Size Selection
Existing track
New construction
60
60
47/53/60
[see note 2]
47
40
60
50
40/50
[see note 3]
Notes:
[1]
Rail sizes other than those specified in Table 1.1A may be used subject to demonstration,
through appropriate analysis and/or testing that they are suitable for the operational
task. Rail wear limits for these alternative rail sizes should be determined during this
process.
[2]
Use of 47 kg rail under these operating conditions may require higher levels of
maintenance, particularly where rail and weld geometry are not of good quality.
[3]
Most 40kg rail types have the same foot size as 50kg rail.
[4]
It is normal practice to provide CWR in Heavy Haul and Interstate Lines, and Intrastate
Lines and Relief Lines, but not on Light Weight Intrastate Lines. Loops, refuge sidings and
other tracks may be welded to CWR with the approval of ARTC.
Rail wear
There are generally two rail wear mechanisms, top wear where the rail head is worn or
ground down, and side wear where the rail wears from the gauge face. Top wear is the
dominant wear mechanism for low rails of curves, tangent tracks and curves with radius
greater than about 600m. Side wear is the dominant wear mechanism for the high rail of
curves sharper than about 600m radius.
Rails on main lines and crossing loops are to be examined at the frequency and using
methods described in clause 1.4.3. The gauge face angle of the rails should also be
measured and the actions specified in clause 1.4.11 taken when the limits are exceeded.
The allowable limits for top wear and side wear, at which the capacity of the rail should be
reviewed, are given in Table 1.2A. The limits for rail head wear as detailed in this table are
divided into 2 levels; Risk Control & Condemn.
Version 3.1
Page 4 of 37
Contents
The acceptance limits for worn rails being transposed from curves to straights, beyond
which the rails are not to be reused, are detailed in columns C and D in Table 1.3.
The risk control limits detailed in Table 1.2A are designed to ensure that appropriate risk
based mitigation controls, as detailed in clause 1.4.11, are implemented as the total
percentage head loss passes these limits. These controls are recommended to ensure the
risks due to the higher rail loading forces and general track risk conditions experienced as
the rails wear are reduced to acceptable levels.
There are two risk control limits detailed for each rail size based on whether the amount of
side wear loss of width on the gauge face is less or greater than 10mm. Locations where
gauge face wear is lower than 10mm normally align to tangent track or wider radius curves
that are not generally exhibiting high lateral forces and side wear. Once the side wear has
exceeded 10mm, particularly on tighter radius curves, the increased side loading being
experienced by the rail and the reduced rail sectional strength means more conservative
limits are required when extra risk controls become necessary.
Version 3.1
Page 5 of 37
Contents
Loss of
height
(mm)
Remaining
height
(mm)
Loss of
width
(mm)
Remaining
width
(mm)
35%
32%
13
24
15
55
50kg AS
45%
32%
18
21
20
53kg AS
35%
32%
16
23
20
60AS
Standard
40%
34%
18
26
24
46
60AS Head
Hardened
45%
34%
20
24
24
46
47kg AS
(94lb)
(107lb)
50 (46 -
see note 7)
50 (46
see note 7)
Notes:
Version 3.1
[1]
The limits apply to the worst location, and not the average rail wear, for the segment of
track being considered (such as a curve).
[2]
The deciding wear limit is the first exceedance of any of the limits in the table above. The
specified limit action must be taken when the rail wear reaches either the height, width
or head loss %.
[3]
The limits do not apply to combination of defects. Where combined defects occur
assessment by a competent worker is required.
[4]
The limits listed under Limit 1: Risk Control must not be exceeded without first
considering the risk control factors as described within clause 1.4.11.
[5]
All limit dimensions are taken at 16mm from the remaining rail surface either top or side
as described further down within this clause under the heading Rail wear measurement
and calculation summary
[6]
Once the risk control limits are reached, monitoring of rail wear data to identify rail wear
locations that require imminent re-rail, should be performed at no less frequent than
10MGT intervals. This frequency allows preparation for re-rail to occur before condemn
limits are reached or exceeded in practice.
[7]
If it can be shown that all risk control factors in section 1.4.11 are being adequately
controlled, then the extended side wear limits of 46mm can be used on 50kg and 53kg
rails. The extended side wear locations must be ultrasonically tested at no greater than
6MGT intervals. Also noting that at high levels of side wear the rail may be reported as
untestable by the contractor (due to loss of zero probe where rail is worn past the edge
of the web), manual hand testing thus may be required.
Page 6 of 37
Contents
Rail Section
Width of new
rail Head
(mm)
Condemning Worn
remaining width B
(mm)
51
103 AS 1936
70
23
46
45
90 AS 1928, 90 AS 1925
70
24
49
45
90 AS 1916
73
22
52
45
90 J 1913
70
24
48
41
80 ASB 1928
64
23
46
41
70
21
52
41
80 AA 1906
64
25
44
41
80 A 1900
64
24
47
41
80 A(1) 1897
64
28
48
41
80 A(2) 1895
64
28
47
41
80 A(3) 1890
64
32
47
39
78 H 1903
70
21
53
37
75 BHP 1917
62
26
46
36
71 2 D 1875
57
27
43
35
70 AS 1928, 70 AS 1925
64
23
48
35
70 AS 1916
60
25
44
35
70lb 1910
60
25
44
31
60 ASB 1928
64
24
49
31
64
22
52
31
60 ASA 1928, 60 AS
1916
60 BA 1907
58
27
43
31
60 B 1896
58
26
44
31
60 B 1890
57
29
43
Version 3.1
Page 7 of 37
Table 1.3 - Maximum allowable rail wear for all curve worn rail sections to be re-used in tangent track
(transposed/cascaded). Dimensions shown indicate rail head remaining not actual wear
Approx
kg/m
Rail Section
Width of
new rail
Head
(mm)
Combined Wear
Minimum remaining Side
Width C if rail is to be reused on Tangent Track
(mm)
60
70
49
27
60
60 AS 1977 1981
70
49
29
53
53 AS 1977 1981
70
49
26
53
70
49
26
51
103 AS 1936
70
49
26
50
50 AS 1977 1981
70
50
25
50
100 AS 1928
70
52
29
50
100 AS 1916
76
58
26
50
100 C 1907
70
51
26
50
100 C 1901
70
52
27
47
94 AS 1937
70
49
25
45
90 AS 1928, 90 AS 1925
70
52
26
45
90 AS 1916
73
56
24
45
90 J 1913
70
52
27
41
80 ASB 1928
64
49
26
41
70
56
25
41
80 AA 1906
64
48
26
41
80 A 1900
64
51
27
41
80 A(1) 1897
64
50
29
41
80 A(2) 1895
64
49
29
41
80 A(3) 1890
64
49
33
39
78 H 1903
70
55
23
37
75 BHP 1917
62
48
29
36
71 2 D 1875
57
46
30
35
70 AS 1928, 70 AS 1925
64
52
25
35
70 AS 1916
60
48
28
35
70lb 1910
60
48
28
Version 3.1
Page 8 of 37
Table 1.4 gives the area of each rail size in new condition; this figure must be used for
all head loss % calculation methods.
Measurements should be taken to an accuracy of 0.5mm, with the gauge face angle
measured to an accuracy of 2 degrees. The head area loss should be measured to an
accuracy of 2%.
All measurements of head width and head depth are taken 16mm below or 16mm in
the rail head as shown below. Measurements are taken from running faces.
The condemn limits for worn height are designed to target solely tangent (top) wear.
In cases where excessive side wear has occurred, it may not be possible to measure
the top wear at 16mm from the remaining gauge face edge otherwise invalid
measurements can be obtained. In such cases where this 16mm measure point is not
representative of the true top wear (due to the strong gauge face wear), the worn
height may be measured 16mm in from the field side of the rail head as an alternative.
Table 1.4 Rail Size new head area to be used for head loss % calculations
Version 3.1
Rail type
47AS
2548
50AS
2729
53AS
2710
60AS Standard
3018
3018
Page 9 of 37
Joints shall have adequate strength and the rail shall be adequately restrained. The
centre portion of long lengths may need to be treated as CWR.
Aluminothermic
(ii) Flashbutt
b) Rail surface repair weld process
Recommended types of weld processes for rail surface repair include:
(i)
Aluminothermic.
Version 3.1
Page 10 of 37
Joints on opposite rail legs may be adjacent to each other (i.e. square). Where
staggered joints are used the effect on vehicle resonances should be taken into
consideration.
Joints should be centrally suspended between sleepers.
Fish plated rail joint components should be manufactured to conform to the
appropriate Australian Standard [see Note 2] as follows:
Fishplates
AS 1085.2
AS 1085.4
Spring washers
AS 1085.7
Notes:
[1]
6 hole/4 bolt joints should only be used where it is intended to weld the track. The "two
centre bolts not used" refers to the bolt on either side of, or closest to the interface of the
two rails.
[2]
These standards generally define the materials, material tests, manufacture, design and
specification of the component, and component testing and compliance.
(ii) Other Joints
Expansion switches, junctions and other permanent joints not covered by AS 1085
shall be supplied in compliance with the specified design.
Pre-assembled glued insulated joints should incorporate swage lock fastenings. In general
insulating materials that encapsulate fishplates are unsuitable for swage lock fastenings
without the application load spreading plates.
d) Pre-assembled glued insulated joints containing rails heavier than 47 kg/m rail shall be
manufactured from head hardened rail. Standard joint lengths are 3.43 and 4.47 m with
the standard versine range specified in ARTC specifications for use in curved tracks.
e)
Rail ends shall be angle cut as provided for in AS1085.12. Where angle cutting is required it
should be at 15 degrees to a line square across the rail head.
f)
The insulated joint is to be centrally suspended between sleepers and located within 700
mm of its design location. When placed on curves pre-assembled glued insulated joints
must be pre-curved to suit the radius of the track.
Page 11 of 37
Each joint of the Double insulated joint must be new and shall conform in all respects to the
requirements of ARTC Standard ETA-01-01 Manufacture and testing of Pre-Assembled
Glued Insulated Rail Joints except when stated in this Section. Second hand joints may not
be reused.
The double block joints shall consist of 2 glued insulated joints at 2.325m apart. The length
of the double block joint is 5.765 m and is composed of three lengths of rail (1.720m,
2.325m and 1.720m) rigidly joined by a pair of fishplates at each joint, adhesive insulating
material and high strength bolts with nuts and washers.
The lubricating system shall comply with relevant environmental statutory requirements for
the control of excess lubricant and friction modifiers.
d) A register shall be established and maintained which specifies where rail lubricators are to
be used and the method of application.
The top of the guard rail shall be at the level of the adjacent running rail surface, or below
it by no more than 50 mm.
d) The working face of the guard rail that comes into contact with derailed wheels shall be a
minimum of 200mm and a maximum of 380mm from the gauge face of the running rail,
and be located to keep derailed wheels on sleeper ends and avoid rolling stock impacts with
structures. The maximum clearance is preferable and if a smaller clearance is adopted an
effective maintenance regime must be in place for replacing the guard rails, when tamping
ballast top bridges, and the rails at the bridge ends.
e)
The working face of the splay rail which comes into contact with the derailed wheels should
start approximately 600mm from the gauge face of the running rail and be angled towards
the running rails to ensure derailed wheels pass the correct side of the guard rail end or
vee.
f)
g) Splay rail sleepers should be fully supported for their entire length.
h) Guard rails shall extend past the end of structure or other hazard being protected.
i)
Guard rails and guard rail ends shall be fastened to every sleeper. They may be connected
directly to timber sleepers with no plates.
j)
Guard rail lengths shall be joined using four-hole fish plated joints as a minimum or their
equivalent with at least two bolts on each side. No joints are permitted in the vee.
k)
Version 3.1
Page 12 of 37
(ii) be vee shaped where there are pairs of guard rails between the running rails and
extend a minimum 3.6m beyond the abutment on the train approach side of the
bridge.
(iii) extend parallel for a minimum of 3m beyond the abutment on the departure side of
the bridge
(iv) Installed at both ends of the bridge where traffic is bi-directional.
l)
Where transoms are bolted to girders the spikes are to be adjacent to the rail flange.
m) When transoms are clipped to girders the spikes are to be installed through holes drilled in
the guard rail flange.
n) Block out holes for guard rail fastenings in concrete sleepers shall be grouted with an
approved high strength grout.
o) Suitable isolation arrangements are to be made where required in track circuit areas.
p) For fixing details, dimensional set-outs and componentry detail and sizes, Standard Guard
Rail drawings are available.
q) For special installations, such as where noise and vibration limiting track fixings are used or
where expansion joints exist, specific design details of guard rail installations to suit will be
required. Approved track fixings are to be used. The design is to be certified by a
competent design engineer.
1.2
e)
f)
53 kg rail cross section should comply with the superseded AS 1085.1 (1980). All
other properties should comply with AS 1085.1
(ii) 50 kg and 60 kg rail and should comply with AS 1085.1 or equivalent standard.
Rail purchased for use in CWR track should be obtained in lengths as long as possible so as
to minimise the number of welds in track.
b) Closure rails
In addition to the requirements of Table 1.5 closure rails should conform to the following
criteria:
(iii) Longer lengths are often used to improve the track geometric quality and reduce
track maintenance;
(iv) The closure rail head profile shall comply with Table 1.10 and be compatible with the
rail head profile of the rail to be removed such that rail misalignments are not
introduced into the track.
Version 3.1
Page 13 of 37
c)
Version 3.1
Page 14 of 37
Factor
Specification
Method of Test
Frequency / Timing
of Test
Method of
Assessment
Ultrasonic testing as
required by Figure 1.1
Wear limits
Gauge or measurement
of wear
Metallurgical properties
N/A
N/A
N/A
Applicable Australian
and International
Standards
Review by metallurgist
competent in rail
examination/testing/
evaluation
Direct measurement
Version 3.1
Chemical composition
Inclusions
Impact resistance
Hardness
Microstructure
Comments
Page 15 of 37
Factor
Specification
Method of Test
Frequency / Timing
of Test
Method of
Assessment
Comments
Adjacent welds
Direct measurement
Direct measurement
Direct measurement
Version 3.1
Rail Twist
Discontinuities
Page 16 of 37
Factor
Specification
Method of Test
Frequency / Timing
of Test
Method of
Assessment
Comments
Check branding
Gauge or profile
measurement
Direct measurement
Matching profiles
Direct measurement
Version 3.1
Page 17 of 37
Factor
Specification
Method of Test
Welding practices
Welding current
Upset displacement
Welding time
Frequency / Timing
of test
Method of
Assessment
Against specification
Visual observation of
welding process.
Check graph or meter
Actions
When a process non-conformance is
identified possible corrective actions
include:
Stop welding
Reassess process
Readjust settings
Rework
Audit of welder
competency.
Visual: Weld
certification that the
weld has been visually
inspected and no
recordable defects have
been found
As specified in Clauses
1.4.8 and 1.2.4
As specified in Clause
1.4.8
[see note 1]
Note [1]:ARTC may specify strength testing and macroscopic testing of welds following welding machine malfunction, overhaul, change of rail
section or work shift.
Version 3.1
Page 18 of 37
Factor
Specification
Method of test
Welding practices
Frequency / Timing
of test
Method of
assessment
Against specification
Visual observation of
welding process.
Worker competency and
training
Version 3.1
Corrective actions
When a process non-conformance is
identified possible corrective actions
include:
Stop welding
Reassess process
Rework
Audit of welder
competency
Visual: Weld
certification that the
weld has been visually
inspected and no
recordable defects have
been found
As specified in Clauses
1.4.8 and 1.2.4
Welds to be tested
ultrasonically within the
timeframe specified in
ARTC standard ETE-01-03
As specified in Clause
1.4.8
Page 19 of 37
Factor
Specification
Method of test
Frequency / Timing
of test
Method of
assessment
Actions
Materials
Prior to use
As necessary
Welding practices
Against specification
Audit of welder
competency
Welds to be tested
ultrasonically within the
timeframe specified in
ARTC standard ETE-01-03
Version 3.1
Reassess Process.
As specified in Clause
1.4.8
Page 20 of 37
START
NO
YES
NO
YES
YES
OK, no test required
Version 3.1
NO
Test rail prior to unrestricted
traffic
Page 21 of 37
DEFECT [2]
COMMENT ON ACTIONS
Bolt hole
(crack, elongation or non
conforming)
Defects shall be cut out and replaced by a closure rail. The closure rail may be welded
at both ends provided specified rail lengths are not exceeded.
Broken foot
Broken rail
Defects should be cut out and the rail welded (subject to compliance with guidelines
for distances to bolt holes) or replaced by a closure rail.
Corroded rail
Repairs shall be carried out by replacing the complete rail between welds unless the
rail has been examined in detail by manual ultrasonic examination.
Horizontal split
(head or web)
Repairs shall be carried out by replacing the complete rail between welds, unless the
rail has been examined in detail by manual ultrasonic examination.
Mechanical joint
Mill defect
Repair is not normally required until growth is detected. The defect should then be
reclassified according to the nature of propagation or failure.
Multiple transverse
defects
Repairs shall be carried out by replacing the complete rail between welds, unless the
rail has been inspected in detail by manual ultrasonic examination. The rail removed
should be immediately rendered unsuitable for reuse.
Notches
Defects shall be cut out and the rail welded or replaced by a closure rail.
Unclassified Defect
Piped Rail
Repairs shall be carried out by replacing the complete rail between welds, unless the
rail has been examined in detail by manual ultrasonic examination. The rail removed
should be immediately rendered unsuitable for reuse.
Shatter Crack
Repairs shall be carried out by replacing the complete rail between welds, unless the
rail has been inspected in detail by manual ultrasonic examination. The rail removed
should be immediately rendered unsuitable for reuse.
Transverse Defect
(including those from
shells or wheel burns)
Vertical Split
(head or web)
Repairs shall be carried out by replacing the complete rail between welds, unless the
rail has been examined in detail by manual ultrasonic examination. The rail removed
should be immediately rendered unsuitable for reuse.
Weld defect
(head, web or foot)
Repairs shall be carried out by removing the weld and replaced by a closure rail, or by
the use of wide gap welds if no bolt holes exist.
Repairs shall be carried out by removing the weld and replacement with a closure rail,
or by the use of wide gap welds if no bolt holes exist.
Ultrasonic defects that occur are to be found in other defect classifications. Alignment
defects may be corrected by grinding, surface repair or replacement with a closure
rail.
Version 3.1
Page 22 of 37
DEFECT [2]
COMMENT ON ACTIONS
Wheel burn
Note:
[1]
All repairs shall meet the rail surface guidelines defined in Clause 1.2.4.
Insertion rail welds into track including those for closure rails.
Table 1.10 - Welded Rail Discontinuities (New Welds)
Factor
Recommended
limits (see Note 5)
Method of test
Corrective action
to achieve
tolerances
1 m reference and
height difference
measure (2)
Remove or grind
Nil
1 m reference and
height difference
measure
Remove or lift
0.5 mm over 1 m
1 m reference and
height difference
measure
Remove or bend
0.5 mm over 1 m
1 m reference and
height difference
measure
Remove or grind
Remove or grind
Remove or grind
Remove or grind
Notes:
Version 3.1
[1]
[2]
[3]
Tolerances are applied only to areas of the rail where wheel contact may occur
[4]
The critical factor in the rail surface limits is the ramp angle measured with a dipped weld
gauge (P1) over 50mm over the full extent of grinding of the weld.
[5]
The minimum standard for new welds should be as per the column titled recommended
limits.
Date of last revision: 12 Aug 13
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Page 23 of 37
Flame cutting shall not be used in preparing rail ends for installation of a permanent nonwelded rail joint.
Both ends of the rail to be welded must be of the same type i.e. either both flame cut or both
sawn.
Other than when used during the welding process as specified above flame cut rail ends under
traffic are only permitted in emergency conditions and shall be plated as a temporary joint,
have a speed restriction of 20 km/h or less (dependent on the joint design) imposed and be
kept under close observation. Under no circumstances are trains permitted to proceed over
these rails at normal speeds. The flame cut rail end must be replaced as soon as possible by
welding in a new section or replacing the affected rail with a saw cut rail.
Page 24 of 37
Measurement of the length between the two reference points shall be made
a) prior to cutting the rail; and
b) after the rail has been welded into track.
Comparison of these two measurements shall be within 2 mm.
If the results of the measurements indicate that the rail adjustment is out of tolerance then
either
i.
ii.
buckles;
break-aways / pull-aparts;
CWR that is being stress adjusted by rattling the rail on sleepers or when using
rollers that only act under the foot of the rail, should be subject to the following:
The maximum adjustment length should not exceed:
Curve Radius
500 metres
300 metres
150 metres
Actual adjustment length will depend on equipment and practices used to ensure an
even distribution of the adjustment over the adjustment length.
CWR on concrete sleepered track, that is being stress adjusted with rollers that lift
under the head of the rail (and in accordance with approved Work Instructions) can be
stressed in lengths of up to 900 metres in one direction. For stressing near the mid
point, this can be in both directions to give total stressing length of up to 1800 metres.
(ii) Finished stress free temperature should be within 5o C from the design neutral
temperature. Adequate records are to be kept to clearly demonstrate this has been
achieved.
Version 3.1
Page 25 of 37
c)
Commissioning
(ii) Establish isolation points so that rail outside the length will not be affected by the
process.
(iii) After cutting the rail, establish the stress free condition between the isolation points
by releasing the rail from the fastening system and vibrating it, for example by '
rattling' the rail.
(iv) Measure the shade rail temperature.
(v) Determine the extension or rail gap by the following equation (see Note 1):
E = 1000.L.X.T
where:
E
extension in millimetres
0.0000115
difference between the shade rail temperature (actual) and the design
neutral temperature in degrees Celsius
cutting the rails to achieve the necessary stress free gap (i.e. plus the weld gap);
stretching the rails to close the gap to the necessary weld gap, see Note 2.
1.3
[1]
If the rails are to be welded ensure that the weld gap is taken into account in
determining the stress free gap.
[2]
Assumes the rail is to be welded by the aluminothermic welding process. In the case of
other welding processes the stress free gap will need to be specified.
Commissioning
*** To Be Determined (to be addressed in RISSB Standards) ***
1.4
Version 3.1
Page 26 of 37
for all new welds (see Tables 1.6, 1.7 and 1.8); and
(ii) where the response following detection of a rail or weld defect is 'observe'.
c)
Detailed inspection
Detailed inspection should be carried out as follows:
(i)
Probe configurations shall be carefully selected for the defect being examined. As a
basis the following standards shall be used to derive the work instructions:
Version 3.1
Page 27 of 37
Other detailed inspections may be used in conjunction with ultrasonic detection, for
example magnetic particle, dye penetrant, X-ray, eddy current and magnetic
induction.
New welds shall be checked for alignment and meet the requirements of Table 1.10.
d) Documentation
The following documentation relating to rail and weld defects shall be maintained:
(i)
Page 28 of 37
(i)
Detailed inspection
A detailed inspection shall be carried out when a joint is suspected to contain additional
defects that cannot be detected by visual inspection.
d) Documentation
Documentation of track sections with non-welded rail joints should be maintained.
(ii) Other unusual and obvious wear patterns and defects indicating for example poor
vehicle tracking, sharp points in curves or excess/deficiency in track superelevation.
(iii) High levels of rail wear approaching wear limits, particularly on curves.
(iv) Excessive rail gauge face angle.
(v) Locations of wheel burns and corrugations and any other deformation of the rail head
Inspections may be carried out from an on-rail vehicle travelling at a speed consistent with
the scope of the inspection, or by walking.
b) General inspection
The amount of rail wear on all main lines and crossing loops shall be measured and
recorded at a period no longer than 6 months apart on Heavy Haul Lines and 12 months
apart on all other lines. The measurement of rail head profile wear may be done by
mechanical non-contact means such as by the AK Car, or other approved track
measurement vehicle. Measurement of wear by non-contact mechanical means such as
hand-held Railmate, Miniprof etc are also acceptable. Measurements shall be taken at
intervals of maximum 10m apart when using the AK car and also when visually inspecting
throughout the affected area (which has been identified as having the most severe example
of wear recorded).
c)
The location of rail wear in excess of the condemn limits detailed in Table 1.2A shall be
recorded together with the location and details of the deformations in (i), (ii), (iv) and (v)
above.
d) Rail in tunnels
In addition to the above requirements, rails in tunnels and wet locations shall be examined
for corrosions during track patrols. The examination should preferably be carried out on a
wet day to confirm the location of water ingress into the tunnel.
The examination requires the removal of any debris and ballast from the rail sections and
particularly from the foot and web area to determine where:
Version 3.1
Page 29 of 37
Where there is a reduction in rail size in the foot or web measurements should be taken at a
maximum spacing of 20 metres with the results reported on the appropriate form. The
original and allowable limits for 53kg/m and 60 kg/m are shown on the form. Care should
be taken to ensure the worst dimensions in the area are recorded.
Once reduction in size is noted a copy of the report is to be retained by the Length
inspector/examiner for reference at the next examination.
The maximum allowable loss of web and foot size is 3mm at which stage the rail should be
replaced.
Carry of lubrication.
Level of lubrication
The level of lubrication can be detected or measured by the following:
(i)
Visual inspection.
(ii) Tribometer.
(iii) Gauge.
Version 3.1
Page 30 of 37
Notes:
[1]
This includes excess lubricant on the gauge side or lubricant being transferred to the top
of the rail head (where it is not intended to be applied).
[2]
Instances where one rail is well lubricated and the other is dry may contribute to high
lateral forces being imposed on the rails and its supporting system. In severe situations
this has contributed to the derailment of trains.
General inspections should look for those conditions inspected for in Patrol
Inspections in addition to damaged and defective components (e.g. mechanical joints
where used).
Version 3.1
Failure of glue in glued joint, particularly between the end post and the first bolt hole and
beyond;
Loose, bent or broken bolts with joint pulling apart or closing up;
Pumping joint;
Page 31 of 37
Ineffective drainage;
Metal conductors across the joint which could short circuit the insulation.
Factor
Optimum maintenance
limit
Normal maintenance
limit
Column 1
Column 2
See note 4
See note 5
1mm over 1 m
2 mm over 1 m
0.5 mm over 1 m
2 mm over 1 m
0.5 mm over 1 m
2 mm over 1 m
0.5mm over 1 m
2 mm over 1 m
8 milliradians
10 milliradians
1 mm over 100mm
2 mm over 100 mm
1 mm over 100mm
2 mm over 100 mm
Notes:
Version 3.1
[1]
Guidelines for rail with non-welded rail joints are not specified.
[2]
Linear measurements taken with a 1 metre straightedge and feeler or taper gauge
[3]
Vertical deviations in rail running surface should be measured with a dipped weld gauge.
[4]
Column 1 gives limits for best practice that have been shown to give optimal
maintenance results in ARTC. No action is required
[5]
When the discontinuities of the magnitudes shown in column 2 are left in track, problems
with track geometry deterioration and high impact causing track component deterioration
can be expected.
Date of last revision: 12 Aug 13
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Page 32 of 37
[6]
Gap < 30 mm
Stop traffic
1.4.10
Imperfections that may have damaged rollingstock should be advised to the train
operator.
Component
Parameter
40/40
Fishplates
60/65
80/90
100/115
115/160
[1]
Visual cracks
1 or both plates
A6
A6
A6
A6
A6
A6
Complete failure
1 fishplate
A4
A4
A4
A4
A4
A4
Both fishplates
A1
A1
A1
A1
A1
A1
Fishbolts
Effective
[2]
A7
A7
A7
A7
A7
A7
A6
A6
A6
A6
A6
A6
A2
A2
A2
A2
A2
A2
A1
A1
A1
A1
A1
A1
Defective
A6
A6
A6
A6
A6
A6
4mm
A7
A7
A7
A7
A7
A7
< 4mm
A6
A6
A6
A6
A6
A6
Rail Ends
Batter
A6
A6
A6
A6
A6
A6
20mm
A7
A7
A7
A7
A7
A7
21mm to 30mm
A6
A6
A6
A6
A6
A6
Version 3.1
Page 33 of 37
A3
A3
A3
A3
A3
A3
A2
A2
A2
A2
A2
A2
Rail
defects
misalignment
Surface or internal
defects
Notes
[1]
[2]
Effective means able to maintain satisfactory vertical and horizontal alignment of rail
ends under traffic. Ineffective bolts may be missing, broken, or loose (depending on
condition of other bolts and operating environment). Effective bolts may be tight, or
loose (depending on condition of other bolts and operating environment).
[3]
Default speed restriction may be increased after risk assessment of rail end pull-apart
potential, and potential for the unacceptable alignment of rail ends.
[4]
It is an assumption that electrical failure of an insulated joint causes the signalling to fail
safe. i.e. it is a track reliability issue and not a track safety issue.
[5]
Default speed restriction may be increased after risk assessment of rail end gap growth
potential, and wheel climb potential.
Table 1.16A Definition of Response Codes
[2]
Response Code
Description
A1
[1]
A2
[1]
A3
[1]
A4
[1]
A5
[1]
A6
A7
Routine Inspection
[2]
[4]
Notes:
Version 3.1
[1]
[2]
[3]
If repairs cannot be made prior to the passage of the next train, the speed restriction
should be implemented along with an appropriate increase in the monitoring [see Note 2]
until actions are taken to restore the track.
[4]
[5]
If the cause of a defect is known and it is known that it will not deteriorate into an unsafe
condition an alternate response to that shown in table1.16A is permitted with appropriate
documentation and approval by the Civil Engineering Representative or nominate
representative..
Page 34 of 37
1.4.11
Version 3.1
Page 35 of 37
The risk controls listed above are recommended to ensure the likelihood of broken rails is
reduced to acceptable risk levels. Each individual high wear location must be treated as a
unique situation and numerous variables should be considered when assessing the risks
involved, example factors include; curvature, MGT, axle loads, track speeds, ambient
temperature differential, grade, rail type/age, typical rolling stock condition (wheel flats),
track geometry, sleeper conditions, and drainage/mud holes.
As the rail wear approaches the final condemn limit dimensions, clearly the risk levels and
associated control actions need to be reviewed and potentially made more stringent. Lines
with very high traffic (MGT) rates may need special wear management regimes to give
early prediction of risk control or re-rail locations so they are identified in time to enable
the specified actions within this clause. Curves with tight radius approximately <300m may
also require re-rail planning much earlier than the specified condemn limits due to very fast
rates of wear.
1.4.12
1.4.13
Response time
Action
[1]
No action
13 Weeks
13 Weeks
Component Damage
Version 3.1
Page 36 of 37
Response time
Action
13 Weeks
13 Weeks
Note [1] These defect sizes and responses apply to all configurations of guard rail fasteners.
1.5
Amount of wear
b) Quarantine
Where rail requires further classification they should be quarantined from reusable rail to
prevent its use back in track.
c)
Disposal
All non-reusable rail components should be clearly marked and disposed of as soon as
practicable after release from the track.
Version 3.1
Page 37 of 37