Unit Commitment Notes
Unit Commitment Notes
5.1 INTRODUCTION
human activity follows cycles, most systems supplying services to a
BecaUSe
electricpower system, the total load on the system will generally be higher
duringthe daytime and early evening when industrial loads are high, lights are
on,and so forth, and lower during the late evening and early morning when
mostof the population is asleep. In addition, the use of electric power has
a weeklycycle, the load being lower over weekend days than weekdays. But why
simplycommit enough units to cover the maximum system load and leave them
canbe saved by turning units off (decommittingthem) when they are not
needed.
EXAMPLE 5A
Unitl:
Min = 150 MW
Max = 600 MW
HI = 510.0+ 7.2P1+
Unit 2:
Min
MBtu/h
100 MW
Max - 400
H2 310.0 + 7.85P2+ 0.00194203MBtu/h
Unit 3:
Min = 50 MW
Max = 000 MW
780+ 7.97P3+ 0.00482P; MBtu/h
132
UNIT COMMITMENT
INTRODUCTION
1200
133
Total
load
- 12
. R/MBtu
Fuel cost3
500
be used to supply this load most economically? To solve this problem, simply
try all combinations of the three units. Some combinations will be infeasibleif
the sum of all maximum MW for the units committed is less than the load
if the sum of all minimum MW for the units committed is greater than the
load. For each feasible combination, the units will be dispatched using the
techniques of Chapter 3. The results are presented in Table 5.1.
Note that the least expensive way to supply the generation is not with all
three units running, or even any combination involving two units. Rather, the
optimum commitment is to only run unit 1, the most economic unit. By only
running the most economic unit, the load can be supplied by that unit Operating
closer to its best efficiency.If another unit is committed, both unit I and the
other unit will be loaded further from their best efficiency points such that the
net cost is greater than unit 1 alone.
Suppose the load follows a simple "peak-valley" pattern as shown in Figure
5.la. If the operation of the system is to be optimized, units must be shut down
as the load goes down and then recommitted as it goes back up. We would
4 AM
4 PM
Time of day
Unit 3
MW
Unit
3
Total
load
Unit 2
Unit 2
Unit I
like to know which units to drop and when. As we will show later, this problem
is far from trivial when real generating units are considered. One approach to
this solution is demonstrated in Example 5B, where a simple priority list scheme
is developed.
4 AM
Time of day
4 PM
EXAMPLE
5B
Suppose
we wish to know which units to drop as a functionof systemload.
Off
Off
Off
Off On
Off
Off
On
On
On
On
200
50
Off
On
Off
On
400
100
600
600
150
150
800
Off
'1000'
On
1200
200
o
250
255
300 267 233
On
Off
Off
On
On
Off
0
550
500
295
Infeasible
Infeasible
Infeasible
400
150
o
50
o
50
0
5389
4911
3760
1658
3418
o
o
o
586
5389
5497
5471
5617
3030 '2440
2787
2244
0
586
INTRODUCTION
134
TABLE 2
for Example 5B
"Shut-down Rule" Derivation
Optimum Combination
Unit I
Load
Unit 2
Unit 3
On
On
On
On
On
On
On
On
On
1200
1150
1100
1050
1000
950
On
On
On
On
On
On
On
On
On
On
On
850
800
750
700
650
On
On
550
On
On
On
On
On
On
On
Off
Off
Off
135
UNIT COMMITMENT
On
On
Off
Off
Off
Off
Off
Off
Off
Off
Off
Off
Off
Figure 5.1bshows the unit commitment schedule derived from this shut-down
rule as applied to the load curve of Figure 5.1a.
So far, we have only obeyed one simple constraint: Enough units will be
committedto supply the load. If this were all that was Involved in the unit
commitmentproblemthat is, just meeting the loadwe could stop here and
state that the problem was "solved." Unfortunately, other constraints and other
phenomena must be taken into account in order to claim an optimum solution.
These constraints will be discussed in the next section, followed by a description
of
drop
Quite simply, if one unit is lost, there in system frequency
c hapter 9). to make up for the
must
loss in a specified be ample reserve
Otherunits must be allocated
timeperiod.
to obey certain
reserve
rules, usually set by
s Pinning
sufficient
having must the reserve be sufficient to make
up for a generation-unit
Notonly
reserves must be- allocated among fast-respondingunits
the
but
and
failure,
units. This allows the automatic generation control system
slow-responding
Chapter9) to restore frequency and interchange quicklyin the event of a
(see
generating-unitoutage.
Beyondspinning reserve, the unit commitment problem may involve various
or "off-line" reserves. These include quick-start
classesof "scheduled reserves"
EXAMPLE 5C
region
Supposea power system consisted of two isolated regions:a western
committed
51.1
Many constraints can be placed on the unit commitment problem. The list
pool, reliability council, and so forth, may impose different rules on the
schedulingof units, dependingon the generation makeup,
load-curve characteristics, and such.
51.2
Spinning Reserve
andan eastern region. Five units, as shown in Figure 5.2,have been tie lines
transmission
to supply 3090 M W. The two regions are separated by
directionThis is
either
in
MW
550
thatcan together transfer a maximum of
of spinning
136
INTRODUCTION
UNIT COMMITMENT
137
constraints: if a plant consists of two
turned on at the same time since or more units, they
cannot
attend both units while starting there are not
enoughcrew
membersto
up
Units
4 and 5
550 raw
maximum
Units
1. 2, and 3
ddltion,
Western region
system.
FIG. 5.2 Two-region
TABLE
Region
Western
Eastern
1000
800
800
Spinning
charw
380
380
1200
1040
310
1350
290
4400
3090
3090
1310
160
compared
where
100
1740
must
Inter.
Reserve
420
420
Total
justmaintain
Regional
Load
and pressure
of the thermal
unit
Eastern region
Figure 5.2
Data for the System in
Regional
GeneraUnit
Unit
tion
Capacity Output
(M W)
Unit
1900
F = fuel cost
160 in
160 out
3090
region.
to this problemis to commitmore units to operate in the eastern
the cost
of hours, the cost of banking will be less than
frequently,due to
Finally,the capacity limits of thermal units may change
the plant; this
maintenanceor unscheduled outages of various equipment in
5.1.4.1 Hydro-Constraints
of
from the scheduling
(or
Unitcommitment cannot be completely separated
scheduling
hydrothermal
problem.
hydro-units.In this text,' we will assume that the
unit commitment
the
will always
COOrdination")problem can be separated from
in this fashion
treatment
We,Ofcourse, cannot assert flatly that our
138
UNIT COMMITMENT
Start-up
cost
Cooling
Banking
Some units are given a must-run status during certain times of the year
reason of voltage support on the transmission network or for such purpo
as supply of steam for uses outside the steam plant itself.
5.1.4.3 Fuel Constraints
We will treat the "fuel scheduling" problem briefly in Chapter 6. A system
which some units have limited fuel, or else have constraints that requireth
to burn a specifiedamount of fuel in a given time, presents a most challeng
unit commitment problem.