Microsoft Project Quick Reference Guide
Microsoft Project Quick Reference Guide
Project 2013
TABS
View Bar
TIP!
1 A New Project
Set Project Defaults
TIP!
Create a task list that breaks the project into Summary Tasks
and tasks. This hierarchical list is also known as a Work
Breakdown Structure (WBS).
2 Build a Schedule
Indent &
Outdent
Tasks
TIP!
Add or
Remove Task
Relationships
Click to insert
on the Task list
ide
ine
he
Format the
Task List
Use a different
color for
critical tasks
3 Manage Resources
Create a Split View
1. Select Gantt Chart from the View Bar.
2. On the VIEW tab check the box for
Details (this splits the view into an
upper pane Gantt Chart and a lower
pane Task Form).
Assign Resources to
Tasks in a Split View
After adding resources to the Resource
Sheet, assign resources to tasks using
the Split View of Details.
1. In the upper pane Gantt Chart view,
select the task by clicking the Task ID
to select the task row to assign the
resource.
Task Type
If Duration is Changed
If Work is Changed
Fixed Units
Duration is recalculated
Work is recalculated
Duration is recalculated
Fixed Work
Duration is recalculated
Duration is recalculated
Fixed Duration
Work is recalculated
Work is recalculated
Track Schedule
Progress Against
a Baseline
The Baseline saves a copy of
current cost and schedule.
Capture the baseline when the
plan is complete and before
beginning to update status.
Save the current baseline:
1. On the PROJECT tab, in the
Schedule group, click Set Baseline and select
Set Baseline to open the dialog.
2. In the Set Baseline dialog, select Baseline
Options and click OK.
View the schedule baseline on the Gantt Chart view:
1. Select the FORMAT tab.
2. In the Bar Styles group, click Baseline and select
the Baseline to display.
TIP!
TIP!