Sample Test Summary Report by SoftwareTestingHelp
Sample Test Summary Report by SoftwareTestingHelp
http://SoftwareTestingHelp.com
Contents
1.
Purpose ................................................................................................................................................. 2
2.
3.
4.
Metrics .................................................................................................................................................. 3
5.
6.
7.
Lessons Learnt....................................................................................................................................... 6
8.
Recommendations ................................................................................................................................ 6
9.
10.
Exit Criteria........................................................................................................................................ 7
11.
Conclusion/Sign Off........................................................................................................................... 7
12.
1. Purpose
This document explains the various activities performed as part of Testing of ABCD
transport system application.
2. Application Overview
ABCD transport system is a web based Bus ticket booking application. Tickets for
various buses can be booked using the online facilities. Real time passenger information
is received from a Central repository system, which will be referred before booking is
confirmed. There are several modules like Registration, Booking, Payment and Reports
which are integrated to fulfill the purpose.
3. Testing Scope
<This section explains about the functions/modules in scope & out of scope for testing;
Any items which are not tested due to any constraints/dependencies/restrictions.
Example: A functionality verification which needs connectivity to a third party
application cannot be tested, as the connectivity could not be established due to some
technical limitations. This section should be clearly documented, else it will be assumed
that Testing covered all areas of the application>
a) In Scope
Functional Testing for the following modules are in Scope of Testing
Registration
Booking
Payment
b) Out of Scope
Performance Testing was not done for this application.
c) Items not tested
Verification of connectivity with the third party system Central
repository system was not tested, as the connectivity could not be
established due to some technical limitations. This can be verified during
UAT (User Acceptance Testing) where the connectivity is available or can
be established.
4. Metrics
<Metrics will help to understand the test execution results, status of test cases & defects
etc. Required Metrics can be added as necessary. Example: Defect Summary-Severity
wise; Defect Distribution-Function/Module wise; Defect Ageing etc.. Charts/Graphs can
be attached for better visual representation>
d) No. of test cases planned vs executed
e) No. of test cases passed/failed
Test cases
planned
80
Test cases
executed
75
TCs
Pass
70
Tcs
Failed
5
Critical
25
0
Major
15
0
Medium Cosmetic
20
0
0
5
Total
60
5
65
Reports
7
4
4
1
16
Total
25
15
20
5
65
http://abcd.2345.com
192.168.xxx.22
Oracle 12g
192.168.xxx.22
7. Lessons Learnt
<This section is used to describe the critical issues faced and their solutions (how they
were solved during the Testing). Lessons learnt will help to make proactive decisions
during the next Testing engagement, by avoiding these mistakes or finding a suitable
workaround >
S. No
Issues faced
Smoke testing test cases
required to be executed
manually each time.
Solutions
Smoke test cases were automated
and the scripts were run, which ran
fast and saved time.
8. Recommendations
<Any workaround or suggestions can be mentioned here.>
Admin control for defect management tool can be given to Offshore Test
lead/manager for providing access to Testing team.
Each time the onsite Admin need not be contacted for requests whenever they
arise, thereby saving time due to the geographical time zone difference.
9. Best Practices
<There will be lot of activities done by the Testing team during the project. Some of them
could have saved time, some proved to be a good & efficient way to work, etc. These can
be documented as a Value Add to show case to the Stakeholders.
Example: A repetitive task done manually every time was time consuming. This task was
automated by creating scripts and run each time, which saved time and resources.
Smoke test cases were automated and the scripts were run, which ran fast and
saved time.
Automation scripts were prepared to create new customers, where lot of
records need to be created for Testing.
Business critical scenarios are separately tested on the entire application which
are vital to certify they works fine.
10.
Exit Criteria
11.
Conclusion/Sign Off
<This section will mention whether the Testing team agrees and gives a Green signal for
the application to Go Live or not, after the Exit Criteria was met. If the application does
not meet the Exit Criteria, then it can be mentioned as The application is not
suggested to Go Live. In this scenario, It will be left with the decision of Senior
Management and Client and other Stakeholders involved to take the call on whether the
application can Go Live or not.>
As the Exit criteria was met and satisfied as mentioned in Section 10, this application is
suggested to Go Live by the Testing team. Appropriate User/Business acceptance
testing should be performed before Go Live.
12.
<This section mentions the meanings of Abbreviated terms used in this document and
any other new definitions>
**********
Sample Test Summary Report Created and published by:
http://SoftwareTestingHelp.com