Performance Measurement of R&D Projects in A Multi Project Concurrent Engineering Environment
Performance Measurement of R&D Projects in A Multi Project Concurrent Engineering Environment
www.elsevier.com/locate/ijproman
Defence Research & Development Organisation, 117C, B Wing, Sena Bhavan, New Delhi - 110 0011, India
b
Management Faculty, University of Pune, India
c
Indian Institute of Cost and Management Studies & Research, 85/1, Chiplunkar Road, Erandavane, Pune - 411 004, India
d
Defence Research & Development Organisation, 117D, B Wing, Sena Bhavan, New Delhi - 110 0011, India
Abstract
An R&D Project can be characterized by its life cycle with three phases of evolution, viz., Project Selection Phase (Screening,
Evaluation, Selection), Project Execution Phase (Technology Development, Product Development, Performance Demonstration)
and Implementation Phase (Production, Marketing, Sales). The traditional approach of performance measurement deals with each
of these phases in isolation. As a result, the evaluation models and performance measurement criteria are separate for each phase.
Once a project is selected, all attention is focused on its completion within the stipulated time and cost, without much consideration
to either the assumptions made at the time of project selection or the requirements of the implementation phase. As a result, performance measurement system for project execution phase is totally independent of other phases. In an R&D environment with
high uncertainty and complexity, coupled with multiple projects competing for limited common resources, use of dierent models
of evaluation at dierent phases may lead to incorrect assessment and poor overall performance. This paper addresses this important issue and suggests a framework for an Integrated Performance Index encompassing the entire lifecycle of R&D projects. The
framework identies the key factors in each phase of the project lifecycle and integrates them through a formula to derive an
Integrated Performance Index that can be used to measure the overall performance of a project at any point of time during its life
cycle. # 2001 Elsevier Science Ltd. All rights reserved.
Keywords: Integrated performance measurement; Multi-project environment; Concurrent engineering; Project management
1. Introduction
Performance measurement plays an important role in
ensuring the project success and its subsequent usefulness to the sponsoring organization. In a controlled
environment, the organizational and project performance is known to be sensitive to the metrics of measurement. Hence it is very important to devise
appropriate performance measurement system to suite
the project and organizational environment. The notion
of performance measurement generally implies identication of certain performance metrics and criteria for
their computation. Several metrics have been developed
to evaluate R&D projects during the selection phase
[123]. Similarly there are well developed metrics for
166
167
168
169
Fig. 2. Conceptual model of an R&D environment with integrated performance measurement system.
170
n
X
Wi Si
i1
Z 1
171
Several methods of risk assessment have been reported in the literature [20,21]. As in the case of merit
ranking, for the risk ranking also there is no universally
acceptable measure evolved so far. Traditionally the risk
is expressed with the help of probability measures such
as the probability of technical success, probability of
commercial success, etc., and the overall risk is computed
through some formula. In most cases the risk assessment is not easily amenable for quantication. Keeping
these factors in view the new model proposes a risk
ranking methodology based on subjective estimates.
The sponsors are expected to provide a list of risk
parameters q1, q2,. . .,qn which in their view represents
the risk at dierent stages of the project. These parameters are selected in such a way that they are independent of each other and occur in a sequential manner
during the life cycle of the project. For example the
technical risk (the probability of not being able to meet
the technical specications), economic risk (probability
of not being able to produce the required quantity at the
required cost), commercial risk (probability of not being
able to attain the required sales volume) fall into this
category. Based on the perceived risk of each factor, a
score is assigned against each risk factor and the overall
risk rank of the project is computed as a product of
these scores. The overall risk of the project can be the
product of these individual risk factors.
n
172
Fig. 3. Graphic tool to determine progress and cost deviation of an R&D project (From Pillai and Rao [23]).
Quadrant 4 can be obtained by transforming corresponding points from Quadrants 1 and 3 (by projecting
the time intercepts of the progress and cost graphs into
Quadrant 4). From the cost vs. progress graphs, the deviations of the cost and progress can be directly measured.
The underlying principle of the four-quadrant graph
is better than the earned value analysis and provides an
integrated costprogresstime analysis. The earned value
analysis uses three elements, viz., the budgeted cost of
work scheduled (BCWS), the actual cost of work performed (ACWP), and the budgeted cost of work performed (BCWP) or the earned value. The cost variance
is given by BCWP
ACWP, which gives a true variance in cost. But the schedule variance is given by
BCWS BCWP which is an interpretation of the schedule variance in terms of cost, which roughly means
that a behind schedule condition requires a variance
amount of cost to get back to schedule. Accurate analysis of schedule condition in terms of time requires utilisation of network or milestone schedule.
In Fig. 3, P gives the ACWP and Q gives the BCWP.
Hence the cost variance computation using the four
quadrant graph is the same as with earned value analysis. R in Fig. 3 represents progress that should have
been made for the actual cost, that is the work scheduled for actual cost (WSAC), while the x co-ordinate of
point P gives the actual progress for actual cost. The
dierence between the x co-ordinates of R and P will
directly give the progress deviation. Further to this, additional schedule/cost information can be directly derived
from Quadrants 3 and 1 and the progresscost interrelationship is more clearly understood from this graph.
It is known that the delays and cost overruns have
adverse eect on the project and for the success of a
project both the progress and cost deviations should
remain as close to the zero as possible throughout the
project execution phase. Keeping this in view, the status
parameters may be related to the project performance in
the following manner:
Z 1=1 pd 1 ce fother factors
9.5. Decision eectiveness and the project performance
Decision eectiveness represents the eectiveness of
the existing project management system in ensuring the
success of the project. The decision eectiveness will
have a positive inuence on the project performance
and the relationship with the project performance may
be specied as follows.
Z 1 decision effectivenessf fother factors
Decision eectiveness can be computed as a weighted
sum of number of factors that contribute towards a
173
n
X
Wi Si
i1
174
n
X
Wi S i
i1
n
X
Wi S i
i1
n
X
Wi S i
i1
175
176
[11]
[12]
[13]
References
[1] Chang Zeph Yun, Yong Kit Chin. Dimensions and indices for
performance evaluation of a product development project. International Journal of Technology Management 1991;6(1/2):15567.
[2] Schmidt RL, Freeland JR. Recent progress in modelling R&D
project selection process. IEEE Transactions on Engineering
Management 1992;39(2):189201.
[3] Martino JP. R&D project selection. USA: John Wiley, 1995.
[4] Meyer MH, Tertzakian P, Utterback JM. Metrics for managing
research and development in the context of the product family.
Management Science 1997;43(1):88111.
[5] Cordero R. The measurement of innovation performance in the
rm: an overview. Research Policy 1990;19:18592.
[6] Foster RN, Linden LH, Whiteley RL, Kantrow AM. Improving
the return on R&DII. Research Technology Management
1985;MarchApril:1322.
[7] Patterson WC. Evaluating R&D performance at Alcoa Laboratories. Research Management 1983;MarchApril:237.
[8] Porter Jr. JG. Post audits an aid to research planning.
Research Management:2830
[9] Batson RG. Characteristics of R&D management which inuence information needs. IEEE Transactions on Engineering
Management 1987;EM-34(3):17883.
[10] Krogh LC, Prager JH, Sorensen DP, Tomlinson JD. How 3M
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21]
[22]
[23]
177