Jan08 Q&A 4
Jan08 Q&A 4
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Aruna Perera
----- Original Message ----From: Wael Guirges Tawfik
To: [email protected]
Date: Thu, 06 Mar 2008 13:01:51 +0400
Subject: Questions
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Many thanks,
----- Original Message ----From: Ashlyn Almeida
To: " Prof. Sam " <[email protected]>
Date: Wed, 05 Mar 2008 17:16:13 +0400
Subject: Re: Summer 2007 Q&A
Dear Dr Sam
Your Q&A session is proving to be quite valuable. Thank you for the effort.
In a recently signed contract the contractor needed to comply with 110 V for construction work in force in a
JAFZA area which has become regulation. Normal requirement on a DM site being 220V. The contract does
state that the contractor must comply with local regulations etc. During the tender clarification we asked the
contractor to confirm if he would comply with JAFZA Health safety document which clearly spells out this
requirement. He gave a letter confirming compliance not realizing this was a requirement.
Now post award he insists for a variation. Is it a variation ? If the 110V requirement was an existing JAFZA
requirement prior to the tender was submitted and if the tender documents clearly required C to comply with
JAFZA requirements, then it is not a Variation. Otherwise it is a Variation. Also if the area was previously
under DM jurisdiction and later (i.e.after the Tender), came under JAFZA jurisdiction, then it is a variation.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
regards
Ashlyn
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Hello Professor,
My name is Ahmed, working in one of the leading interior fit-out company in Dubai. Sir, I have a
question, request you to kindly resolve this issue mentioned below.
During the awarding of contract to one of our subcontractor, the rates of certain items were not
scrutinized by our QS due to lack of time. Now after completing the project when I observed these
rates, they are very high when compared with average rates. The contract is re-measurable &
having Back to Back term. Kindly advise if,
1. I can ask him to provide me a break down of these items. Yes, if you need to use them as a
basis for valuing variations.
2. Ask him for discount in these items. Yes you can ask, but he does not have an obligation
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
If you are capable of proving your entitlement, then you should pursue the dispute
resolution mechanism in the contract.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Nafeesa Sayad
Senior Quantity Surveyor