Emergency Generator FMEA Example
Emergency Generator FMEA Example
FMEA Report
Project Title
Client Name
Job No.
Team Leader
Project Analyst (s)
Report Author (s)
ABSTRACT
A Failure Mode & Effects Analysis (FMEA) study was conducted with respect to
the Emergency Generator system of the semi-submersible drilling rig Rig 1. The
FMEA study was conducted at the Company project offices in JSL Shipyard,
Singapore.
FMEA is a methodology used for analyzing potential reliability problems of
systems, with a view to enhancing reliability through design. The FMEA approach
has three basic elements when reviewing potential failure modes. These are the
SEVERITY of the event, the likelihood of OCCURRENCE and the DETECTABILITY
during the design phase of the failure event.
Based on these elements, the FMEA process calculates a Risk Priority Number
(RPN) for each individual Potential Cause of Failure. The aggregate RPN for each
Potential Failure Mode (which may be comprised of a number of individual
Potential Causes of Failure) is then presented in a graphical format for review.
The study team identified 5 subsystems of the Emergency Generator system for
review. These were the starting, fuel, emergency stop, fire damper and
synchronisation / control subsystems. A total of 26 discrete failure modes were
identified and analysed.
Recommendations were developed for the critical and high risk failure modes which, if
implemented, will reduce risk to an acceptable level. Revised RPNs were calculated to
demonstrate the expected reduction in risk for these elements.
Key Words: (e.g. Industry category, study type)
DRILLING, FMEA
Release
Date of Issue
Reviewed by
No.
Draft
Approved by
Client Approval
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY....................................................................4
2. ACRONYMS & GLOSSARY................................................................6
3. DISCUSSION..................................................................................7
4. FMEA STUDY TEAM.........................................................................9
5. FMEA METHODOLOGY...................................................................10
6. DISTRIBUTION.............................................................................13
ATTACHMENTS:
1. FMEA RISK PRIORITY NUMBER (RPN) GRAPH
2. FMEA WORKSHEETS
3. PHOTOGRAPHS
Page 3 of 13
1.
Executive Summary
EXECUTIVE SUMMARY
A Failure Mode & Effects Analysis (FMEA) studies was conducted with respect to
the Emergency Generator system of the semi-submersible drilling rig Rig 1. The
FMEA study was conducted at the Company project offices in JSL Shipyard,
Singapore.
This report covers the Emergency Generator system. Five subsystems of the
Emergency Generator system were identified for review. The identified
subsystems were:
Starting subsystem
Fuel subsystem
Potential failure modes for each subsystem were then identified and the severity,
occurrence and detectability assessed for each potential cause of those failure
modes.
The Fire Damper subsystems were identified as having a significant Risk Priority
Number (RPN) value. The Potential Causes of Failure which resulted in high RPN
values for the Fire Damper subsystem were:
Page 4 of 13
Executive Summary
Potential Failure Modes with an RPN value in excess of 350 have been ranked as
Risk Reduction Measures Required. These can also be viewed as critical risks.
There were two Potential Failure Modes identified by the team as having an RPN
value in excess of 350. Both of these identified items related to the Fire Damper
subsystem.
Potential Failure Modes with an RPN value in excess of 200 but less than 350
have been ranked as Risk Reduction Measures Recommended. That is to say,
these risks were recommended for action but such action was not seen to be
mandatory.
There were two Potential Failure Modes identified by the team as having an RPN
value in excess of 200 but less than 350. Two of these items related to the Fire
Damper subsystem and one item related to the Starting subsystem.
Potential Failure Modes with an RPN value less than 200 have been ranked as
Continuous Improvement. These are items which have no immediate impact
on the operability and safety of the system and thus can be dealt with in due
course, as resources become available to do so.
There were twenty items identified over the range of subsystems which fell into
this category.
Recommendations to mitigate the critical risks were identified by the team. These
recommendations were compiled during the FMEA study and were included in
this report at the Clients request.
For the Fire Damper subsystem the following was recommended to mitigate the
risks to an acceptable level:
Adopt planned maintenance routine to periodically clean and check louvres clean of
debris
Ensure that regular emergency exercises are held and crew are made aware of the
emergency generator room fire damper system limitations.
The study showed that the Emergency Generator system was a fit-for-purpose
design provided that the appropriate asset integrity activity recommendations
such as maintenance, testing and inspection, are carried out during the life of the
system.
Page 5 of 13
2.
ACRONYMS
AC
ALARP
BHPB
FMEA
HAZID
Hp
L
M
N
NDT
Occ
PM
RPN
Sev
SOP
E-Stop
U
Alternating current
As Low As Reasonably Practicable
BHP Billiton
Failure Modes & Effects Analysis
Hazard Identification
Horse Power
Likelihood
Marginal Risk
Negligible Risk
Non Destructive Testing
Occurrence
Preventative Maintenance
Risk Priority Number
Severity
Standard Operating Procedure
Emergency Stop
Unacceptable Risk
Page 6 of 13
3.
DISCUSSION
3.1.
Background
Discussion
Analysis
The results of this FMEA are supported by industry data. The DNV Offshore Reliability Data
handbook provides specific data relating to reliability of emergency generator systems. The
following empirical data with respect to worldwide experience of emergency generator
reliability was extracted as part of the FMEA study:
Number of degrading events per 1 x 106 hours of operation includes the following:
-
In line with the above reliability data, the FMEA study for the Emergency Generator on Rig 1
resulted in high RPN levels for the following Potential Failure Modes:
Failure to start
3.3.
Recommendations
The analysis showed that the Fire Damper posed significant risks. In this failure
mode one casual mode was identified as significantly high; debris jammed in
the louvres.
Recommendations to mitigate the risk were identified by the team.
Recommendations were compiled during the FMEA study and were included in
this report at the Clients request. For the Fire Damper subsystem the following
was recommended to mitigate the risk to an acceptable level:
Ref: S1266 Rev 1
Page 7 of 13
Discussion
Adopt planned maintenance routine to periodically clean and check louvres clean of
debris
Ensure that regular emergency exercises are held and crew are made aware of the
emergency generator room fire damper system limitations.
Page 8 of 13
4.
For the purposes of this FMEA study, Contractor utilised the following personnel:
Table 4.1: FMEA Team Members
Name
Company
Page 9 of 13
5.
FMEA Methodology
FMEA METHODOLOGY
Identify the Potential Effects of Failure for each Potential Failure Mode
Assess and rank the severity criteria of each Potential Effect of Failure
Identify the Potential Causes of Failure for each of the Potential Effects
of Failure
Assess and rank the Occurrence and Detectability criteria levels for
each Potential Cause of Failure
Quantify the risk by generating a Risk Priority Number (RPN) for each
Potential Cause of Failure.
of
the
study
with
appropriate
The aggregate RPN for each Potential Failure Mode is presented in a graphical
format for review and serves to allow a prioritisation of response to the findings
of the FMEA study.
Page 10 of 13
FMEA Methodology
The following tables provide the criteria used to ranking the elements of
Severity, Occurrence and Detectability during the FMEA study:
Severity
1
2
None
Very Slight
3
4
Slight
Minor
Moderate
Moderately High
High
Very High
Extremely High
10
Maximum
Occurrence
1
2
3
4
5
6
7
8
9
10
Extremely Unlikely
Remote
Very Low
Low
Moderately Low
Medium
Moderately High
High
Very High
Extremely Likely
Page 11 of 13
FMEA Methodology
Very High
High
Moderately High
Moderate
Low
Very Low
Remote
Very Remote
Absolute
Uncertainty
Ranking
1
2
3
4
5
6
7
8
9
10
FMEA Worksheets
Following is an example of a completed worksheet from the FMEA study. The Risk Priority
number is used to prioritise the process of addressing the findings of the FMEA study.
Table 5.2 FMEA Worksheet Example
Potential
Failure Mode
1. Start motor
failure
Potential
Effects of
Failure
1. Generator
does not start
upon receiving
start signal
Severity
Occurrence
Detectability
during
design
process
Risk
Priority
Number
1. Age of motor
2. Ingress of moisture to
motor winding
42
3. Low voltage/high
amperage starts
42
4. Excessive number of
starts (short cycling of
engine)
28
Potential Causes of
Failure
Ranking
Page 12 of 13
6.
Distribution
DISTRIBUTION
Owner
Paper
CD
Contractor Library System
Page 13 of 13
ATTACHMENT 1
Page 1 of 1
ATTACHMENT 2
FMEA Worksheets
7.
FMEA WORKSHEETS
2. Start power
failure
(battery/air
failure)
Potential Effects of
Failure
1. Generator does not
start upon receiving start
signal
Sev
2. Battery explosion
3. Fire
Occ
Detectability
during design
process
RPN
1. Age of motor
2.
Ingress
of
moisture to motor
air/electric
42
3. Low voltage/high
amperage starts
42
4.
Excessive
number of starts
(short cycling of
engine)
28
5.
Incorrect
application of motor
1.
Lack
maintenance
batteries)
56
42
1.
Shorting
terminals
of
2.
Insufficient
insulation
3. Cable damage
Potential Causes of
Failure
of
(dry
16
cell
24
2. Excessive current
delivery
24
1.
Internal
collapse
Recommendations
Sev
Occ
Detectability
RPN
%
Reducti
on
Page 1 of 14
4. Solenoid
failure
5. Flywheel burr
6. Automatic
controller failure
Potential Effects of
Failure
1. Generator does not
start upon receiving start
signal
Sev
Occ
Detectability
during design
process
RPN
1. Lack of
maintenance
21
2. Poor installation
3. Choice of material
4. Moisture
28
1. Excessive
number of starts
(short cycling of
engine)
14
2. Low voltage/high
amperage starts
14
1. Damage during
commissioning
21
2. Control system
errors causing start
signals while engine
running
42
Potential Causes of
Failure
2. Emergency generator
downtime
1. Inability to start
due to flywheel
excessively
burred/damaged.
1. Poor terminal
connections
42
2. Maintenance
personnel not
resetting controller
14
3. Drift of control
parameters
21
Recommendations
Sev
Occ
Detectability
RPN
%
Reducti
on
Page 2 of 14
7. Manual
override not
deactivated
9. Fire dampers
closed
10. Fuel
inventory (day
Potential Effects of
Failure
Sev
Occ
Detectability
during design
process
RPN
4. Failure of
monitoring circuit
14
1. Maintenance
personnel not
resetting controller
21
2. Wiring errors
14
Potential Causes of
Failure
2. Emergency generator
does not receive start
signal
1. Switch left in
manual position
10
28
2. Fuel starvation,
requiring re-bleed of
systems and downtime
1. Engine starting
with fuel valve
closed
14
14
2. Inadvertent
operation of damper
14
3. Compressed air
system failures
42
1. Emergency generator
overheats
2. Oxygen starvation to
emergency generator
1. Operating
engines whilst fire
dampers closed
12
21
Recommendations
Sev
Occ
Detectability
RPN
%
Reducti
on
Page 3 of 14
Potential Effects of
Failure
Sev
tank empty or
contaminated)
11. Battery
charger failure
Occ
Detectability
during design
process
RPN
2. Shipyard blasting
grit
49
1. Clogged filters
12
2. Air in system
Potential Causes of
Failure
2. Fuel starvation,
requiring re-bleed of
systems and downtime
3. Premature shutdown
12
42
2. Maintenance
check failures
14
3. PM system does
not cover monitoring
of charging amps
1. Extended non
charging periods
24
2. Excessive
number of starts
(short cycling of
engine)
12
3. Faulty battery
4. Poor battery
maintenance
72
1. Poor quality
battery
2. Flat batteries
Sev
Occ
Detectability
RPN
%
Reducti
on
2. Periodic maintenance of
the main, auxiliary and
emergency switchboards.
21
50.00
3. Include periodic
maintenance of
emergency starting
batteries in planned
maintenance program.
48
33.33
Recommendations
Page 4 of 14
Potential Effects of
Failure
4. Reduced cranking
amp availability
12. Alarm
malfunction
Sev
Occ
Detectability
during design
process
RPN
2. Poor battery
maintenance
36
3. Excessive
number of starts
(short cycling of
engine)
4. Insufficient design
charging current
1. Poor quality
battery
2. Poor battery
maintenance
18
3. Excessive
number of starts
(short cycling of
engine)
4. Insufficient design
charging current
Potential Causes of
Failure
1. Alarm state
inhibits start signal
2. Alarm flooding
1. Poor design of
alarm systems
3. False alarms
1. Poor maintenance
3. Inadequate alarm
check procedures
1. False alarm
4. Premature shutdown
Recommendations
Sev
Occ
Detectability
RPN
%
Reducti
on
Page 5 of 14
Potential Effects of
Failure
5. Failure to shutdown
Sev
Potential Causes of
Failure
1. Failure to
recognize alarm
state
Occ
Detectability
during design
process
RPN
Recommendations
Sev
Occ
Detectability
RPN
%
Reducti
on
Potential Effects of
Failure
1. Hose/fuel line
failure
2. Fire
Sev
Occ
Detectability
during design
process
RPN
1. Leaking
connection
20
2. Fractured pipe
1. Contact with
exhaust - leak
14
2. Fuel leak
contacting turbo
charger
14
Potential Causes of
Failure
3. Premature shutdown
1. Fuel starvation
84
2. Fuel filter
blockage
1. Premature shutdown
1. Fuel starvation
84
3. Fuel quality
1. Covered under
starting system
4. Fuel inventory
inadequate
1. Covered under
starting system
5. Fuel pump
failure
1. Mechanical
breakdown
14
2. Poor maintenance
28
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 6 of 14
Potential Effects of
Failure
2. Premature shutdown
Sev
Occ
Detectability
during design
process
RPN
3. Inadequate
design
1. Fuel starvation
28
Occ
Detectability
during design
process
RPN
1. Sabotage
32
2. Unprotected
Estop buttons
16
Potential Causes of
Failure
Recommendations
Sev
Occ
Detectability
%
Reductio
n
RPN
2. Failure To
Operate
Potential Effects of
Failure
Sev
Potential Causes of
Failure
1. Unwarranted
emergency stop
2. Degradation
engine/electrical system
1. Short cycling
(loading and
unloading of system)
3. Loss of emergency
power systems
1. Emergency
generator shutdown
54
1. Damage to generator
electrical systems
1. Incorrect voltage
12
2. Loss of control
3. Overload
12
4. Poor maintenance
1. Incorrect voltage
2. Overload
3. Asynchronous
operation
2. Damage to bus
electrical systems
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 7 of 14
Potential Effects of
Failure
3. Damage to motor
3. Incorrect
operation
Sev
Occ
Detectability
during design
process
RPN
1. Overspeed
2. Overload
1. Circuit breaker
failure
24
2. Poor design of
Estop system
24
1. Poor design of
Estop system
12
2. Mechanical failure
of air intake
1. Poor design of
Estop system
18
2. Poor maintenance
18
Potential Causes of
Failure
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 8 of 14
2. Failure to
reset (open)
3. Failure to seal
upon closure
Potential Effects of
Failure
1. Non extinguishing of
fire
Sev
Occ
Detectability
during design
process
RPN
Recommendations
1. Debris jammed in
louvre
343
2. Seizure due to
lack of maintenance
21
42
Potential Causes of
Failure
2. Escalation of fire
1. Non exclusion of
air
42
1. Inability to operate
emergency generator
2. Lack of
maintenance
14
3. Lack of
awareness of
procedure
175
42
1. Debris jammed in
louvre
343
1. Non extinguishing of
fire
Sev
Occ
Detectability
RPN
%
Reductio
n
1. Adopt planned
maintenance routine
to periodically check
louvres are clean of
debris.
63
81.63
4. Ensure that
regular emergency
exercises are held
and crew are made
aware of the
emergency
generator room fire
damper system
limitations.
63
64.00
1. Adopt planned
maintenance routine
to periodically clean
and check louvres
clean of debris
63
81.63
Page 9 of 14
4. Inadvertent
operation
Potential Effects of
Failure
Sev
Occ
Detectability
during design
process
RPN
2. Lack of
maintenance
14
3. Poor design of
damper
Potential Causes of
Failure
2. Escalation of fire
1. Non exclusion of
air
42
1. Unplanned shutdown
of generator
1. Loss of
Emergency Power
98
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 10 of 14
Potential Effects of
Failure
Sev
1. Fails to
synchronize to
main bus (if
applicable)
1. Inability to return to
main power without
power interruption
2. Fails to reach
synchronize
speed
1. Inability to
synchronize to main bus
2. Voltage/frequency
dependant loads
receiving incorrect
power supply (EG AC
motors)
3. Generator
attempts
asynchronous
closure
1. Circuit breaker
damage
2. Explosion/fire
Occ
Detectability
during design
process
RPN
1. Design of control
system
2. Control system
component failure
16
1. Design of control
system
2. Control system
component failure
20
3. Problems with
main bus (e.g. main
bus voltage
incompatible)
80
1. Generator
damage
36
2. Fuel system
impairment
24
3. Control system
component failure
24
4. Fire damper
malfunction
54
1. Control system
component failure
28
2. Personnel
attempting manual
closure of circuit
breaker
147
1. Circuit breaker
recoil on attempted
closure to main bus
14
Potential Causes of
Failure
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 11 of 14
Potential Effects of
Failure
3. Blackout
4. Generator damage
4. Unstable
voltage/frequenc
y
Sev
Occ
Detectability
during design
process
RPN
1. Main bus
protection operates
in reaction to
attempted
emergency
generator circuit
breaker closure
40
2. Emergency
generator protection
operates
40
1. Inadequate
protective systems
2. Extreme overload
35
Potential Causes of
Failure
5. Unplanned shutdown
1. Generator
protective devices
operate
32
6. Loss of emergency
power systems
1. Emergency
generator shutdown
20
1. Voltage/frequency
dependent loads
receiving incorrect
power supply (EG AC
motors)
1. Generator
damage
18
2. Fuel system
impairment
24
3. Control system
component failure
24
2. Inability to
synchronize to main bus
1. Inappropriate
voltage/frequency
parameters
3. Generator damage
1. Inadequate
protective systems
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 12 of 14
Potential Effects of
Failure
Sev
Potential Causes of
Failure
Occ
Detectability
during design
process
RPN
4. Unplanned shutdown
1. Emergency
generator protection
operates
48
5. Loss of emergency
power systems
1. Emergency
generator shutdown
20
Recommendations
Sev
Occ
Detectability
RPN
%
Reductio
n
Page 13 of 14
ATTACHMENT 3
Photographs
Page 1 of 1
8.
Attachment 3: Photographs
PHOTOGRAPHS
Attachment 3: Photographs
Attachment 3: Photographs