100% found this document useful (2 votes)
1K views

Salient Features of Mycesmm

The document discusses the salient features of MyCESMM (Malaysian Civil Engineering Standard Method of Measurement), including current issues with existing measurement methods, the framework and structure of MyCESMM, and how it addresses challenges such as defining rock excavation and natural hard materials to reduce disputes between contractors and clients.

Uploaded by

racing.phreak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views

Salient Features of Mycesmm

The document discusses the salient features of MyCESMM (Malaysian Civil Engineering Standard Method of Measurement), including current issues with existing measurement methods, the framework and structure of MyCESMM, and how it addresses challenges such as defining rock excavation and natural hard materials to reduce disputes between contractors and clients.

Uploaded by

racing.phreak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 59

SALIENT FEATURES

OF
MyCESMM

Assoc. Prof. Sr. Sabaria Hassan FRISM, MRICS, MBQSM


Pusat Pengajian Ukur Bahan,
Fakulti Senibina , Perancangan & Ukur
UiTM, Shah Alam
Wednesday, October 15, 2014

INTRODUCTION
CURRENT ISSUES USING SMM

FRAMEWORK OF MyCESMM
Mycesmm
A guide to mycesmm
Standard library of BQ

Wednesday, October 15, 2014

CURRENT PRACTICES IN MSIA |


Building works SMM1 and SMM2 (2000)
Civil engineering works

CESMM3 (UK)

MCESMM (2003)
Ad-hoc basis
Based on Survey done during meet the industry with 147
respondents:
24% use MCESMM,
28% use CESMM (UK) 2nd & 3rd Edition and
48% use other method of measurement.

ISSUES AND CHALLENGES

Wednesday, October 15, 2014

SOME ISSUES IN USING SMM : 1


Piling works

SOME SAY

OTHERS
3m

Pay 10m for supply and


7 m for driving

7m

Pay 7m for supply and


7 m for driving
Who can say exactly what depth
of pile to be driven??

SOME ISSUES IN USING SMM : 2


Trench excavation
Payment
based on this
width??

Or this
width??

If this width,
what angle to
use??

SOME ISSUES IN USING SMM : 3


Rate of Fill
CESMM (UK)
SMM2 (M)

- excavation in stages
eg. excavate from 0m to 1.5m depth
from 1.5m to 3.0m depth a.s.o

MyCESMM

- let the Contractor choose the appropriate method


of construction
- difficulties encountered and loss of productivity
associated with increasing depth of excavation
to be reflect in the builtup rate
- measured whole = max depth
- item description or drawing should indicate the
depth of excavation to facilitate computation of rate
by the contractor (max depth and commencing
surface stated in description) ( as per 5.20)

IMPORTED FILL
Importing fill materials occur, when
CUT (effective) FILL =

-ve

DIPOSAL OF EXCAVATED EARTH

Disposing of excavated materials occur, when


CUT (effective) FILL =

+ve

Class F Earthwork __________________________________________________________________________________

CUT < FILL


Import
2.0

4.0

4.0

Fill
Cut

2.0

4 units 6 units = 2 units imported

CUT > FILL


Dispose

2.0

4.0

6.0

6 units 4 units = 2 units disposed

Fill
Cut

Filling Shrinkage Factor

1.2

1.5

Balance Cut & Fill Situation

6.0

4.8

To Fill 6 units require 7.5 units


Cut
- 6.0 units (4.8 units)
Imported - 1.5 units (1.2 units)

Imported Volume covered in Filling rate

1.2

1.5

Computation of Filling Rate

6.0

4.8

6.0 m3 @ RM5.00 RM30.00


1.5 m3 @ RM10.00 RM15.00
Fill = RM45.00/6 m3 = RM7.50/m3

SOME ISSUES IN USING SMM : 4


Rate for Natural Hard Materials (not rock)
JKR/SPJ/1988
Specification for Roadworks published by Jabatan Kerja Raya,
Malaysia
Rock shall mean material found in ledges or masses in
its original position which would normally have to be
loosened either by blasting or pneumatic tools or, if
excavated by hand, by wedges and sledge hammers.
It shall NOT include material which can be loosened
with a track-type tractor with mounted and drawn
ripper of the following description:

PLANTS USED
Tractor Unit:
Equiptment with a minimum weight of 20 tonnes and
nett horse power rating of 200 brake horse power or
more. The tractor unit is to be in good condition and
operated by experienced personnel skilled in the use
of ripping equipment
Ripping Unit:
The ripper to be attached to the tractor shall be the
most efficient parallelogram type recommended by
the tractor or ripper manufacturer. The ripper shall
have single shank in good working condition with
sharpened cutting point.

ROCK CLASSIFICATION

EARTH (Grade V & VI)

Totally weathered

ROCK (Grade III & IV)

Cracks and fissures,


partially weathered

ROCK (Grade I & II)

Fresh, monolithic, no fractures


or cracks

THE PROBLEM

EARTH (Grade V & VI)

SEDIMENTARY HARD MATERIAL


ROCK (Grade I & II)

Class F Earthwork ____________________________________________________________________________

THE PROBLEM

On Site:
In between the two extreme material on site
(earth and rock) we have HARD MATERIAL

which is not been clearly defined


not included in the scope of specification
which the Contractor has to excavate but not
priced accordingly
the current practice, it is usually been paid
under normal excavation i.e. excavation in
earth

Resulting in:
Claim by the Contractor due to low productivity for
excavation in natural hard material (get paid for earth
excavation instead of excavation in rock)
Class F Earthwork ____________________________________________________________________________

MyCESMM SOLUTION

REDEFINE ROCK
ROCK or ARTIFICIAL HARD MATERIAL shall be
material that requires the use of either hydraulic
rock breaker, pneumatic tools or explosives.
..(MyCESMM)
DEFINE NATURAL HARD MATERIAL

NATURAL HARD MATERIAL shall be material other


than ROCK and ARTIFICIAL HARD MATERIAL
that requires ripping and other specialised
equipment. . (MyCESMM)

The Contractor gets paid


For what he Did
Class F Earthwork __________________________________________________________________________

HARD MATERIAL/ROCK EXCAVATION


shall required one or a combination of the following
methods:

Excavation using track excavator exceeding a mass


of 44 tones and 321 BHP rating
Ripping using a tractor unit of minimum weight of 37
tones and 305 BHP rating and a ripper attached
Excavation using pneumatic tools
Open blasting
Controlled blasting

- Hard Material & Rock will have a common rate -

Class F Earthwork __________________________________________________________________________

SOME ISSUES IN USING SMM : 5

Conditions of contract

JKR 203A (Rev. 10/83)


Clause 26(b) BQ for Building Works based on SMM2
prepared by Institute of Surveyors, Malaysia

JKR 203A (2007)


Clause 26.4 BQ allowed to be based on CESMM 3 by ICE or
any Method

When disputes arise say concrete works which SMMs


governs?
Wednesday, October 15, 2014

20

SOME ISSUES IN USING SMM: 6

Too many SMMs, JKR 203A-2007 allows it but is it


practical?
Eg:
Under 1 Item - Supply, lay, including excavation, valves, thrust
blocks, etc (CESMM3)
Under 4 Items - Excavation (I), Supply & Lay including joints (2),
Valve (3), Thrust blocks (4) (Own Method)
Under 7 Items - Excavation (I), Supply (2), Lay (3), Cutting of Pipes
(4), Joints (5), Valve (6), Thrust blocks (7) (Own Method)

Wednesday, October 15, 2014

21

A Guide to
MyCESMM

Malaysian Civil
Engineering Standard
Method of Measurement
(MyCESMM)

Library of Standard
BQ Descriptions for
MyCESMM

2011
Wednesday, October 15, 2014

22

FRAMEWORK OF
MyCESMM

Wednesday, October 15, 2014

23

Malaysian Standard Method of


Measurement (MyCESMM)

Wednesday, October 15, 2014

24

CONTENT
Section 1. Definition
Section 2. General Principle
Section 3.Application Of the Work Classification
Section 4.Coding and Numbering of Items
Section 5.Preparation of the Bill of Quantities
Section 6.Completion, pricing and use of the Bill of Quantities
Section 7.Method Related Charges

Section 8.Work Classification: Class A Class T

Wednesday, October 15, 2014

25

Section 1: Definitions
1.1

MyCESMM, BQ, Specification, COC etc.


1.2 condition of contract
1.3 refer 1.1
1.4 ref to section and paragraph
1.5- Work =everything that the contractor has
to do including liabilities, obligations and risks.
1.6 - site

Wednesday, October 15, 2014

26

Section 1: Definitions (contd)


1.7

expressedly required = stated


1.8 BQ
1.9 Daywork
1.10 work classification
1.11 original surface/ original grd level

Wednesday, October 15, 2014

27

Section 1: Definitions (contd)

1.12 final surface


1.13- commencing surface
1.14 excavated surface
1.15 hyphen
1.16 JKR
1.17 LLM
1.18 DOE
1.19 BS and MS
1.20 singular / plural

Wednesday, October 15, 2014

28

Section 2 : General Principles


The application and extent of MyCESMM
Objective of MyCESMM
Objectives of the Bill of Quantities

Wednesday, October 15, 2014

29

Section 2 : General Principles (contd)


CLIENT
Idea, concept
Functional, size, material
confirmation

Estimated cost (range)


Time

CONSULTANT

CONTRACTOR

- conceptual design
- detailed design
- Specification (work & material)
- Bill of Quantities
- Estimated Cost

COST &
TIME

Section 2 : General Principles (contd)


ENGINEER(DESIGNER)

CONTRACTOR
WORK
What ?

- Item Ref. / Description

Quantity ?
Coverage Rules ?
Size (dimension) ?
Where ?
When/Duration/Interval ?

Additional Descripion
Rule

Material Specification ?
MyCESMM_________________________________________________________________________________________________

Section 3 : Application of the Work Classification

Item description - Work classification


-20 main classes; Class A- Class T

Each class comprises up to 3 division which


classify work at successive level of detail 8
descriptive features of work.

Units of meas.

Wednesday, October 15, 2014

32

DESCRIPTIONS FROM MyCESMM


FIRST DIVISION
3

Water quality control and monitoring

SECOND DIVISION
1
2
3

Skid tank bund


Water treatment facilities
Sewage treatment facilities

Water quality sampling and in-situ


testing
Water quality sampling and laboratory
testing

Each division only 8 items (max), WHY???


3 digit code number, B358, B3510???
B359.1 Manganese, B359.2 - Iron

THIRD DIVISION

Unit
sum
sum
sum

1
2
3
4
5
6
7
8
9
10

pH
Total Suspended Solid (TSS)
Biochemical Oxygen Demand (BOD)
Chemical Oxygen Demand (COD)
Dissolved Oxygen (DO)
Escherichia Coli (E.coli)
Ammoniacal nitrogen
Oil and grease
Manganese
Iron

nr
nr
nr
nr
nr
nr
nr
nr

Section 3 : Application of the Work Classification


(contd)
- Describes briefly the WORK component (not the TASK i.e.
how
the Work should be done) to be executed by the Contractor
- (the details of work will be described in the Tender
Drawing and coverage rule in the Preamble to BQ
and
the MoM)
e.g:

not as:

- Excavate in cut to dispose unsuitable material below


embankment max depth.
- Mild steel bar of nominal diameter 20mm

Supply, deliver, cut, bent and fix mild steel bar of


diameter 20mm

MyCESMM_________________________________________________________________________________________________

Section 3 : Application of Work Classification


(contd)

Rules to measurements

Each class work contains


Measurements Rules,
Definitions Rules,
Coverage Rules,
Additional rules

Application of rule horizontal line

Wednesday, October 15, 2014

35

Section 3 : Application of Work Classification


(contd)
MEASUREMENT RULES

M1 The depth of boring, drilling,


sampling and testing shall be
measured form the
Commencing Surface as
a) not exceeding 10m
b) 10 - 20m
c) 20 - 30m
d) 30 - 40m
e) 40 - 50m
f) stated exceeding 50m

DEFINITION RULES

COVERAGE RULES

ADDITIONAL DESCRIPTION RULES

D1 Plant movement is shifting C1 Item for plant movement


A1 Item description for water
of plant or equipment from
shall be deemed to include
sample shall state the
one borehole / test position to
dismantling from one position
volume.
the next position.
and erecting at another
A2 Item descriptions for
D2 Hillslopes is more than 25
C2 Sampling shall be deemed to
disturbed sample shall state
degrees.
include transportation and
the weight of samples.
protection.
D3 Small disturbed samples is
A3 Item descriptions for block
less than 5kg.
C3 All field exploration and tests
sample shall state the size of
shall be deemed to include
sample.
logging of daily field records.

Application of rule horizontal line

Section 3 : Application of Work Classification


(contd)
- Coverage Rule (preambles) briefly identify what
to be included in the pricing eg : excavation in cut
e.g: a. Items for excavation to include disposal of
excavated material, unless otherwise stated.
b. Items classified as excavate in cut to
include transportation from source to place of fill or
disposal
c. Items classified as excavation in cut to
include the trimming and preparation of excavated
surface.

Section 4 : Coding & Numbering of Items


One alphabet and not more than three digits.

E.g. Code I310 identifies an item as


Class
I
Concrete Works
1st Division
3
precast concrete
2nd Division 2
beams
3rd Division 0
Description: I310 - Precast concrete, in beams
*
9
0
Additional description

Wednesday, October 15, 2014

38

MyCESMM Coding structure


FIRST DIVISION
2

Piles

SECOND DIVISION
1
2

Bored piles
Driven cast in-situ concrete
piles

THIRD DIVISION
1
2

Depth bored or driven


Boring through rock

m
m

Permanent casings
Reinforcement straight bars nom
dia :
not exceeding 20mm
exceeding 20mm
Reinforcement helical bars
concreted length
Cut-off piles

1
2
3
4
5

Class of
Works

Unit

t
t
t
m
nr

H223
Wednesday, October 15, 2014

39

Section 5: Preparations of the Bill of Quantities


Bill of quantities = List of items with brief descriptions and
estimated quantities
-(the details of work described in the Tender Drawings,
- coverage rule in the Preamble to BQ
- and the MoM)
e.g:

Excavate cut to dispose unsuitable material below


embankment max depth----.

Quantities
- BQ quantity as a basis for estimating the rate
- Final quantity to be re-measured

MyCESMM_________________________________________________________________________________________________

Section 5: Preparations of the Bill of Quantities

5.2 5.7 - Sections of BQ

SECTION

PREAMBLE

WORKS ITEMS
Part 1 General Items
Part 2 Bridge No.1
Part 3 Bridge No.2
Part 4 Roadwork
Part 5 Tunnel
Part 6 Rest areas complex

C
D

DAYWORK SCHEDULE
GRAND SUMMARY
Wednesday, October 15, 2014

41

Section 5: Preparations of the BQ (contd)


5.8 - Headings and Sub heading

5.9 - Extent of itemisation and descriptions follow work


classification BUT can further be itemized due to special
method of construction or cost

5.10 5.12 Descriptions dwgs, specs. , conditions of


contract read in conjunction with the work classification

5.11 detail from work classification may be omitted provided a


reference is given eg. Drawing, specification, MS, BS etc.

5.12 additional description may be given where appropriate.

Wednesday, October 15, 2014

42

Section 5: Preparations of the BQ (contd)

5.13 ranges of dimensions


5.14 Prime cost sum
5.15 Provisional Sum
5.17 Quantities nett , round up/down
5.18 Units of measurement
5.19 work affected by water
5.20 state commencing surface and state the
maximum depth for boring, excavation or driving.

Wednesday, October 15, 2014

43

Section 6 : Completion, Pricing and Use of the BQ

6.1 - Rates and prices shall be inserted in the


rate column in Ringgit Malaysia with Sen inserted
as decimal fractions of one Ringgit.

6.2 - Each part of the BQ shall be total and


carried to the Grand Summary

Wednesday, October 15, 2014

44

Section 7: Method-Related Charges

MRC

15/10/2014

JKR Seminar 28-29 August 2013

Section 7: Method-Related Charges (contd)

7.1- Definition: the sum for an item inserted in the BQ


by a tenderer.
Time-related charges the cost is to be considered
as proportional to the length of time taken to execute
the work
Fixed charge- charges which is not a time related
charge.

7.2- to cover items of works relating to:


his intended method of executing the works,
the cost of which are not to be considered as
proportional to the quantities of the other items and
for which he has not allowed in the rates and prices for
the other items.
Wednesday, October 15, 2014

46

Section 7: Method-Related Charges (contd)

7.3- Itemisation follow Class A

7.4- Description
fully described extent of work covered (temporary/permanent)
Identify resources to be used

7.5 Contractor shall not be bound by the method


7.6 not subjected to re-measurement but shall be
deemed to be priced for the purposes of valuation of
variation
7.7 payment interim certificate
7.8 contractor shall not be bound to adopt method
paid in full. Can only change when V.O exist.

Wednesday, October 15, 2014

47

Section 8: Work Classifications


MyCESMM

A General Items
B Environmental Protection and Enhancement
C Traffic Management and Control
D Site Investigation Work
E Demolition and Site Clearance
F Earthworks
G Geotechnical Work
H Piling Work
I Concrete Work
J Brickwork, Blockwork and Masonry
K Timber Work
L Metalwork
M Building Work
N Painting Work
O Pipeworks
P Drainage Work
Q Roads and Pavings
R Tunnel Work
S Rail Tracks
T Miscellaneous Work

MCESMM
A General Items
P Environmental Protection and enhancement
Q Traffic Management and Control
B Soil Investigation Works
D Demolition and Site Clearance
E Earthworks
C Slope Stabilisation and Ground Treatment
J Piling Works
F Concrete Works
K Brickwork, Blockwork and Masonry
L Timber Works
M Metalwork
N Painting Works
I Pipeworks
H Drainage Works
G Roadwork
O Rail Tracks
R Miscellaneous Works

48
Wednesday, October 15, 2014

A Guide to MyCESMM

Wednesday, October 15, 2014

49

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

50

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

51

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

52

WHAT?

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

53

WHAT?

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

54

WHERE

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

55

WHERE & WHAT

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

56

Library of Standard BQ
Descriptions based on
MyCESMM

Wednesday, October 15, 2014

57

Wednesday, October 15, 2014

MyCESMM- JKR 28-29 July 2013

58

THANK YOU.
READY TO APPLY MyCESMM? |

Wednesday, October 15, 2014

59

You might also like