Salient Features of Mycesmm
Salient Features of Mycesmm
OF
MyCESMM
INTRODUCTION
CURRENT ISSUES USING SMM
FRAMEWORK OF MyCESMM
Mycesmm
A guide to mycesmm
Standard library of BQ
CESMM3 (UK)
MCESMM (2003)
Ad-hoc basis
Based on Survey done during meet the industry with 147
respondents:
24% use MCESMM,
28% use CESMM (UK) 2nd & 3rd Edition and
48% use other method of measurement.
SOME SAY
OTHERS
3m
7m
Or this
width??
If this width,
what angle to
use??
- excavation in stages
eg. excavate from 0m to 1.5m depth
from 1.5m to 3.0m depth a.s.o
MyCESMM
IMPORTED FILL
Importing fill materials occur, when
CUT (effective) FILL =
-ve
+ve
4.0
4.0
Fill
Cut
2.0
2.0
4.0
6.0
Fill
Cut
1.2
1.5
6.0
4.8
1.2
1.5
6.0
4.8
PLANTS USED
Tractor Unit:
Equiptment with a minimum weight of 20 tonnes and
nett horse power rating of 200 brake horse power or
more. The tractor unit is to be in good condition and
operated by experienced personnel skilled in the use
of ripping equipment
Ripping Unit:
The ripper to be attached to the tractor shall be the
most efficient parallelogram type recommended by
the tractor or ripper manufacturer. The ripper shall
have single shank in good working condition with
sharpened cutting point.
ROCK CLASSIFICATION
Totally weathered
THE PROBLEM
THE PROBLEM
On Site:
In between the two extreme material on site
(earth and rock) we have HARD MATERIAL
Resulting in:
Claim by the Contractor due to low productivity for
excavation in natural hard material (get paid for earth
excavation instead of excavation in rock)
Class F Earthwork ____________________________________________________________________________
MyCESMM SOLUTION
REDEFINE ROCK
ROCK or ARTIFICIAL HARD MATERIAL shall be
material that requires the use of either hydraulic
rock breaker, pneumatic tools or explosives.
..(MyCESMM)
DEFINE NATURAL HARD MATERIAL
Conditions of contract
20
21
A Guide to
MyCESMM
Malaysian Civil
Engineering Standard
Method of Measurement
(MyCESMM)
Library of Standard
BQ Descriptions for
MyCESMM
2011
Wednesday, October 15, 2014
22
FRAMEWORK OF
MyCESMM
23
24
CONTENT
Section 1. Definition
Section 2. General Principle
Section 3.Application Of the Work Classification
Section 4.Coding and Numbering of Items
Section 5.Preparation of the Bill of Quantities
Section 6.Completion, pricing and use of the Bill of Quantities
Section 7.Method Related Charges
25
Section 1: Definitions
1.1
26
27
28
29
CONSULTANT
CONTRACTOR
- conceptual design
- detailed design
- Specification (work & material)
- Bill of Quantities
- Estimated Cost
COST &
TIME
CONTRACTOR
WORK
What ?
Quantity ?
Coverage Rules ?
Size (dimension) ?
Where ?
When/Duration/Interval ?
Additional Descripion
Rule
Material Specification ?
MyCESMM_________________________________________________________________________________________________
Units of meas.
32
SECOND DIVISION
1
2
3
THIRD DIVISION
Unit
sum
sum
sum
1
2
3
4
5
6
7
8
9
10
pH
Total Suspended Solid (TSS)
Biochemical Oxygen Demand (BOD)
Chemical Oxygen Demand (COD)
Dissolved Oxygen (DO)
Escherichia Coli (E.coli)
Ammoniacal nitrogen
Oil and grease
Manganese
Iron
nr
nr
nr
nr
nr
nr
nr
nr
not as:
MyCESMM_________________________________________________________________________________________________
Rules to measurements
35
DEFINITION RULES
COVERAGE RULES
38
Piles
SECOND DIVISION
1
2
Bored piles
Driven cast in-situ concrete
piles
THIRD DIVISION
1
2
m
m
Permanent casings
Reinforcement straight bars nom
dia :
not exceeding 20mm
exceeding 20mm
Reinforcement helical bars
concreted length
Cut-off piles
1
2
3
4
5
Class of
Works
Unit
t
t
t
m
nr
H223
Wednesday, October 15, 2014
39
Quantities
- BQ quantity as a basis for estimating the rate
- Final quantity to be re-measured
MyCESMM_________________________________________________________________________________________________
SECTION
PREAMBLE
WORKS ITEMS
Part 1 General Items
Part 2 Bridge No.1
Part 3 Bridge No.2
Part 4 Roadwork
Part 5 Tunnel
Part 6 Rest areas complex
C
D
DAYWORK SCHEDULE
GRAND SUMMARY
Wednesday, October 15, 2014
41
42
43
44
MRC
15/10/2014
46
7.4- Description
fully described extent of work covered (temporary/permanent)
Identify resources to be used
47
A General Items
B Environmental Protection and Enhancement
C Traffic Management and Control
D Site Investigation Work
E Demolition and Site Clearance
F Earthworks
G Geotechnical Work
H Piling Work
I Concrete Work
J Brickwork, Blockwork and Masonry
K Timber Work
L Metalwork
M Building Work
N Painting Work
O Pipeworks
P Drainage Work
Q Roads and Pavings
R Tunnel Work
S Rail Tracks
T Miscellaneous Work
MCESMM
A General Items
P Environmental Protection and enhancement
Q Traffic Management and Control
B Soil Investigation Works
D Demolition and Site Clearance
E Earthworks
C Slope Stabilisation and Ground Treatment
J Piling Works
F Concrete Works
K Brickwork, Blockwork and Masonry
L Timber Works
M Metalwork
N Painting Works
I Pipeworks
H Drainage Works
G Roadwork
O Rail Tracks
R Miscellaneous Works
48
Wednesday, October 15, 2014
A Guide to MyCESMM
49
50
51
52
WHAT?
53
WHAT?
54
WHERE
55
56
Library of Standard BQ
Descriptions based on
MyCESMM
57
58
THANK YOU.
READY TO APPLY MyCESMM? |
59