Distribution Hand Book
Distribution Hand Book
Interconnection
Handbook
April 2003
Revision 0
Copyright E 2003
by Pacific Gas and Electric Company.
All rights reserved.
Acknowledgements
The working group that wrote the Distribution Interconnection Handbook (DIH) is
comprised of several departments.
Thanks to these team members:
Distribution Planning: Satvir Nagra, Sherry King, Jim Sanborn
Field Metering: Bill Tirona, Young Nguyen
Interconnection Services: John Vardanian (Rule 21), David Ore (ENET),
Art McAuley
Service Planning: Dave Evans
System Operations: Wolfgang Hase, Mike Badet
Technical Support: Jim Sprecher, Jeff Goh, Dan Pearson
Software Support for Interconnection Study: Bob Hartwell
Rate & Tariffs: Jerry Jackson, Dylan Savidge
Communication: Larry Duba
Interconnection ServicesTransmission Handbook: Bill Gravellis
Support: Kris Buchholz
May 1, 2003
ii
May 1, 2003
Table of Contents
Contents
Section 1
Page
General information
2.4.2.
2.5.2.
2.5.3.
May 1, 2003
iii
Contents
Page
2.5.4.
Subdivision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7
2.5.5.
2.5.6.
2.5.7.
2.5.8.
Section 3
3.4.2.
iv
May 1, 2003
Contents
Page
3.5.2.
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-8
3.6.2.
Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-9
3.6.3.
3.6.4.
3.12.2.
3.14.2.
3.14.3.
3.14.4.
3.14.5.
3.14.6.
May 1, 2003
Contents
Page
3.14.6.2. Fuses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-18
3.20.2.
Section 4
4.2.2.
4.2.3.
4.2.4.
4.2.5.
4.2.6.
vi
4.3.1.
4.3.2.
4.3.3.
4.3.4.
Contents
Page
4.3.5.
4.3.6.
4.3.7.
4.3.8.
4.8.2.
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10
4.9.2.
Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-10
4.9.3.
4.9.4.
4.15.2.
4.15.3.
May 1, 2003
vii
Contents
Page
4.17.2.
4.17.3.
4.17.4.
4.17.5.
4.17.6.
4.17.7.
4.17.8.
4.17.9.
May 1, 2003
Contents
Page
4.25.2.
4.25.3.
Section 5
5.4.2.
5.4.3.
May 1, 2003
ix
Contents
Page
5.4.3.6. Make-Before-Break Requirements . . . . . . . . . . . . 5-5
Section 6
6.3.2.
6.7.2.
May 1, 2003
Contents
Page
6.11. Required Tests for the PS Customers Equipment Before Energizing . 6-15
6.11.1.
6.11.2.
6.11.3.
6.11.4.
6.11.5.
Relays/Fuses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-17
Glossary
Attachment 2
Websites Addresses
Attachment 3
Drawings
Figure A3-1
Figure A3-2
Figure A3-3
Figure A3-4
Figure A3-5
Figure A3-6
May 1, 2003
xi
Contents
Page
Document 058779
Document 060559
Document 066195
Attachment 4
Equipment
Rule 21 Process
Rule 21
Rule 21
Attachment 6
Attachment 7
Attachment 8
Attachment 9
xii
May 1, 2003
Contents
Page
Form 62-4527
Form 79-280
Form 79-285
Form 79-756
Form 79-843
Form 79-854
Form 79-973
Form 79-974
Form 79-978
May 1, 2003
xiii
Contents
Page
Form 79-988
Form 79-992
Form 79-944
Form G2-2
Form G5-1
xiv
May 1, 2003
List of Figures
Contents
Page
Section 2
Figure 2-1
Section 3
Figure 3-1
Figure 3-2
Section 4
Figure 4-1
Figure 4-2
Section 5
Figure 5-1
Attachment 3
Drawings
xv
Contents
Page
Document 058779
Document 060559
Document 066195
xvi
May 1, 2003
List of Tables
Contents
Section 1
Table 1-1
Section 2
Page
General information
Interconnection Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
Standard E-NET Interconnection
Table 2-1
Table 2-2
Section 3
Table 3-1
Table 3-2
Table 3-3
Table 3-4
Table 3-5
Section 4
Table 4-1
Table 4-2
Table 4-3
Table 4-4
Table 4-5
Section 6
Table 6-1
Table 6-2
May 1, 2003
xvii
Table 6-3
Table 6-4
xviii
May 1, 2003
Generation
May 1, 2003
xix
Generation
Section 1
General Information
Notice: Document Subject to Change
The information and requirements in this manual are subject to change over time.
The online version of the Distribution Interconnection Handbook, located at
http://www/TechLib/, will be updated as quickly as possible when changes occur.
The bound manual will not be reprinted until the next scheduled print date regardless
of changes in the process or requirements.
1.1.
Purpose
The purpose of this manual is to provide information on how to
interconnect generating facilities or distributed generation (DG) to Pacific
Gas and Electric Companys (PG&Es) electrical distribution lines. This
information is presented by PG&E in an effort to maintain safe, uniform,
and reliable service to generating facilities and customers.
This manual is based on the applicable Federal Energy Regulatory
Commission (FERC) and California Public Utilities Commission (CPUC)
rules and tariffs (e.g., Electric Rules 2, 21, and 22), as well as accepted
industry practices and standards contained within the Applicable
Reliability Criteria.
There are four types of interconnection. They are included in the
following two categories:
Retail
Standard E-NET
Expanded E-NET
Rule 21
Wholesale
1.2.
Standard E-NET
To apply for Standard E-NET interconnection, all of the following
conditions must apply for:
May 1, 2003
1-1
Generation
General Information
Expanded E-NET
To apply for Expanded E-NET interconnection, all of the following
conditions must apply for:
Rule 21
To apply for Rule 21 interconnection, all of the following conditions
must apply for:
1.3.
1-2
May 1, 2003
Generation
General Information
Table 1-1
Interconnection Process
Supplemental
Review
Technology
Initial Review
Standard
E-NET
(Section 2)
PV/wind or
a hybrid of
both
No cost to the
customer for
initial review if
PG&E
determines that
the proposed
project
qualifies as a
simplified
interconnection
No cost to the
customer if
PG&E
determines
that a
supplemental
review is
required.
No cost to the
customer if PG&E
determines that an
additional detailed
study is required.
Expanded
E-NET
(Section 3)
PV/wind or
a hybrid of
both
10 business
days
No fees
collected
10 business
days
No fees
collected
Rule 21
(Section 4)
Any type of
generation
10 Business
Days
$800 fee
collected
10 business
days
$600 fee
collected
1.4.
Detailed Study
Frank Salguero
(8) 2232284
Art McAuley
(8) 2236924
May 1, 2003
1-3
Generation
General Information
1-4
May 1, 2003
Generation
Section 2
Standard E-NET Interconnection
2.1.
Introduction
Standard E-NET is an energy net metering service for customers who
have installed a solar (photo voltaic or PV) or wind turbine generator or a
hybrid of both, with a capacity of 10 kW or less, and have interconnected
the facility to the Pacific Gas and Electric Companys (PG&E) electric
distribution grid system.
Customers who meet the above criteria qualify for Standard E-NET, if
they are:
Residential, or
Purpose
The primary purpose of this generation interconnection service is to allow
customers to offset part or all of their electric loads. These customers may
continue to purchase power from PG&Es electric grid, as well as deliver
incidental power to the grid. This is conforming with CPUC Code 2727.
An E-NET customers electric meter may run forward (to account for
purchases from the grid) and backward (to account for deliveries to the
grid).
2.3.
May 1, 2003
2-1
Generation
Standard E-NET Interconnection
2.4.
2.4.2.2.
2-2
May 1, 2003
Generation
Standard E-NET Interconnection
Signed Agreement
The applicant must provide a signed copy of the
Interconnection Agreement for Net Energy Metering of
Solar or Wind Electric Generating Facilities of 1000 KW
or Less, Other than Residential or Small Commercial
Facilities of 10 KW or Less (Form 79-978, in
Attachment 12).
Please review the agreement checklist, which provides
instructions for completing the agreement.
May 1, 2003
2-3
Generation
Standard E-NET Interconnection
2.4.2.4.
2.4.2.5.
2.4.2.6.
Electric Vehicles
The E-9 rate is mandatory for applicants with electric
vehicles. A completed E-9 Checklist All Customers
Selecting The Schedule E-9 Rate Must Complete the
Following Qualifying Checklist, must be included with
the application. The E-9 Checklist is located in
Attachment 12 of this manual.
2.4.2.7.
Table 2-1
Standard
E-NET
Timeline
Initial Review
PV/wind or
a hybrid of
both
No cost to the
customer for
initial review if
PG&E
determines that
the proposed
project
qualifies as a
simplified
interconnection
Supplemental
Review
No cost to the
customer if
PG&E
determines
that a
supplemental
review is
required.
Detailed Study
No cost to the
customer if PG&E
determines that an
additional detailed
study is required.
Requirements
2.5.1.
Protective Devices
For Standard E-NET, PG&E requires inverters that are certified by
Underwriters Laboratories Standard UL 1741 and listed on the
California Energy Commissioners (CEC) eligible list.
2-4
May 1, 2003
Generation
Standard E-NET Interconnection
May 1, 2003
2-5
Generation
Standard E-NET Interconnection
2-6
May 1, 2003
Generation
Standard E-NET Interconnection
To Grid
PG&E
Meter
Lockable Disconnect
Switch (either one of these
locations)
Main
Panel
Transfer or
Bypass Switch
NO
Sub
House
Panel
NC
L2
L1
Invert Unit
(Check UL 1741
Certification)
Wind/Solar Equipment
Figure 2-1
Single-Line Drawing
2.5.4.
Subdivision
Subdivision developers offering solar generating systems must
apply for interconnection for the subdivision as a whole, rather
than submit individual, single-home applications.
To avoid delay, the developer must submit an application form for
the subdivision and a master drawing at least six months before the
requested interconnection.
May 1, 2003
2-7
Generation
Standard E-NET Interconnection
2.5.5.
Metering Requirements
Standard E-NET installations are designed to operate in parallel
with the PG&E system.
The disconnect requirements are specified by PG&E and are listed
in Engineering Document 060559, Disconnect Switches For
Interconnection With Small Power Producers And Cogenerators,
(Attachment 3).
As specified in Rule 21, the generating facility is required to have
an accessible disconnect switch that is lockable in the open
position. The disconnect switch must be located 10 feet or less
from the main utility meter panel and must be observable from the
panel.
Generating facilities under the Standard E-NET program may
deliver minimum power only with rated inverter that is approved
on this application.
In accordance with the CPUC-approved tariff, generators that meet
the following conditions may use a meter without a detent to net
the usage
(net kilowatt hours [kWh] = kWh usage kWh generation):
2-8
May 1, 2003
Generation
Standard E-NET Interconnection
Height Requirement
2.5.6.
Telemetering Requirements
Communication circuits between PG&E and customer generation
facilities may be required for protection, Supervisory Control and
Data Acquisition (SCADA), revenue metering and voice
communications. When external communication circuits are
installed, the responsible party should make sure that the high
voltage protection (HVR) on these circuits meets all applicable
standards.
If the meter is read via a telephone line, the customer is
responsible for installing the line and establishing service. If a land
line is unavailable and cellular signals are acceptable, then a
cellular phone may be used.
If the meters telephone line cannot be dedicated to the meter, the
customer, with approval from PG&Es local metering group, may
arrange to use a line sharing switch.
The telephone-line termination in switchboards, panels,
pole-mounted meters, and pedestals must be located as follows:
May 1, 2003
2-9
Generation
Standard E-NET Interconnection
2.5.7.
Operation Requirements
For PG&Es operating requirements, the customer must ensure that
the PG&E-approved disconnect is accessible at all time to PG&E
employees.
For some PG&E work procedures, such as scheduled maintenance
and outages, PG&E employees may require that this disconnect be
opened and locked for the employees safety.
2.5.8.
2.5.8.1.
Preparallel Inspection
Before giving a final approval for interconnection, PG&E
requires a preparallel inspection.
A PG&E field crew will schedule a date with the customer
or the customers representative to perform the preparallel
inspection. The customer must complete the Preparallel
Inspection Checklist in Attachment 12.
2-10
May 1, 2003
Generation
Section 3
Expanded E-NET Interconnection
3.1.
Introduction
Expanded E-NET is an energy net metering service for customers who
install a photovoltaic (PV) or wind turbine generator or a hybrid of both,
with a capacity above 10 kW and up to 1,000 kW, provided the facility is
interconnected to the Pacific Gas and Electric Companys (PG&E) electric
distribution grid system.
Customers who meet the following criteria will qualify for Expanded
E-NET interconnection:
Residential.
Purpose
The primary purpose of Expanded E-NET interconnection is for
customers to offset part or all of their electric loads. These customers may
continue to purchase power from PG&Es electric grid, as well as deliver
incidental power to the grid.
An Expanded E-NET customers electric meter may run forward (to
account for purchases from the grid) and backward (to account for
deliveries to the grid).
3.3.
May 1, 2003
3-1
Generation
Expanded E-NET Interconnection
3.4.
Application Form/Fees
To apply for Expanded E-NET interconnection, the customer must
submit an E-NET application.
Expanded E-NET applications can be obtained in several ways:
3.4.2.2.
3-2
Generation
Expanded E-NET Interconnection
Signed Agreement
The applicant must provide a signed copy of the
Interconnection Agreement for Net Energy Metering of
Solar or Wind Electric Generating Facilities of 1000 KW
or Less, Other than Residential or Small Commercial
Facilities of 10 KW or Less (Form 79-978, in
Attachment 12).
Please review the agreement checklist, which provides
instructions for completing the agreement.
3.4.2.4.
3.4.2.5.
3.4.2.6.
Electric Vehicles
The E-9 rate is mandatory for applicants with electric
vehicles. A completed E-9 Checklist All Customers
May 1, 2003
3-3
Generation
Expanded E-NET Interconnection
Preparallel Inspection
To ensure that the system has been installed in accordance
with the originally submitted specifications, PG&E must
perform a final inspection of the system before operation
begins.
After a satisfactory inspection, the customer will receive a
written approval from PG&E to operate the system in
parallel with PG&Es grid.
3.4.2.8.
Timeline
There are no review or study fees for Expanded E-NET
interconnection.
Table 3-1
Timeline
10 days
Review
Application Completeness
PG&E must verify that the following items with sufficient
detail are received before conducting the initial review:
The project name and location.
A single-line drawing.
The generating facilities type, size, and data.
A list of protective devices.
The type and mode of a disconnect switch.
Please indicate on the application or drawing any
installed California Energy Commission (CEC)-certified
equipment.
10 days
Initial Review
Engineering review using the Initial Review Process.
Please see Sample of the Initial Review Process, in
Attachment 5.
3-4
Interconnection Study
PG&E will determine the timeline and the cost for an
interconnection study on a case-by-case basis.
May 1, 2003
Generation
Expanded E-NET Interconnection
3.4.2.9.
Application Completeness
Before proceeding with technical evaluation, PG&E has 10
days, from the day of the receipt of the application, to
evaluate if the applicant has provided complete
information.
A completed application must have the following items:
Initial Review
If PG&E deems the application is complete, PG&E has 10
business days to perform the initial review.
At any time that PG&E deems the application is
incomplete, the 10-day clock for the initial review phase
stops. However, as soon as the applicant provides the
missing information and PG&E deems the application is
complete, a new 10-day clock starts.
If PG&E determines that the application qualifies for a
simplified interconnection, PG&E will provide a written
description of the requirements, as well as the agreements
described in Section 4.3. (Rule 21 Agreement).
3.4.2.11.
Supplemental Review
During the initial review, if PG&E determines that the
application does not qualify for a simplified
interconnection, PG&E will perform a supplemental
review.
PG&E will provide one of the following items after the
supplemental review:
May 1, 2003
An interconnection-study schedule.
3-5
Generation
Expanded E-NET Interconnection
Interconnection Study
If an interconnection study is needed, PG&E will
determine the timetable on a case-by-case basis.
3.5.
Requirements
The requirements for Expanded E-NET are based on Rule 21.
This section describes the specific requirements that may be applicable, on
a case-by-case basis, to any retail generators that do not meet one or more
of the simplified interconnection criteria set by the California Energy
Commission (CEC) Rule 21, here referred to as CPUCs Rule
21-Generating Facility Interconnections.
For the complete text of Rule 21 please see:
http://www.pge.com/customer_services/business/tariffs/pdf/ER21.pdf
3.5.1.
Interconnection Requirements
When interconnecting facilities to the PG&E distribution system, it
is important to minimize the potential hazard to life and property.
A basic safety rule requires the automatic detection and isolation
of abnormal system troubles within a reasonable time.
Important system problems are fault conditions, such as a short
circuit.
3.5.2.
3-6
May 1, 2003
Generation
Expanded E-NET Interconnection
The term high-speed, or pilot protection refers to any type of communication-assisted protection, for example,
conventional current-differential protection or direct-transfer trip application.
Please refer to Attachment 6 for the requirements for pilot protection, including the associated transfer trip equipment,
communication circuit monitoring, and the commissioning test.
May 1, 2003
3-7
Generation
Expanded E-NET Interconnection
3.6.
General
The customer must provide and install a manual disconnect switch,
which PG&E will operate, to isolate PG&Es distribution system
from the customers generating facility.
To establish a visually open working clearance in accordance with
PG&Es safety rules and practices, the manual disconnect must be
opened during all maintenance and repair work. For
interconnections of 2.4 kV and above, the disconnect switch must
be located at the point of interconnection with PG&E. The
disconnect switch must be gang-operated, three-pole and lockable.
If the disconnect switch will be located on PG&Es side of the
interconnection point, PG&E must install it at the customers
expense.
If the disconnect switch will be located on the customers side, it
must be furnished and installed by the customer. If the disconnect
device is in the customers substation, it must be located on the
substations dead-end structure and have a PG&E-approved
operating platform. The customer must use only PG&E-approved
devices.
PG&E must inspect and approve the installation before parallel
operation is allowed.
The disconnect switch must not be used to make or break parallels
between the PG&E electric system and the customers generating
3-8
May 1, 2003
Generation
Expanded E-NET Interconnection
Specifications
The manual disconnect switch must meet the following
requirements:
Be gang-operated.
3.6.3.
3.6.4.
May 1, 2003
3-9
Generation
Expanded E-NET Interconnection
3.7.
Have met all the criteria set by the CEC Rule 21, Section J, as
tested by a nationally recognized testing laboratory (NRTL)
acceptable to PG&E and the test reports must have been approved
by PG&E.
PG&E requires additional testing for multiple units unless the generator
has received an earlier approval.
Separate single-unit or multiple-unit inverters that do not meet
Underwriters Laboratories Standard UL1741 or have not been adequately
tested will not be granted commercial operation status and the customer is
not permitted to interconnect to the system.
PG&E reserves the right to disconnect previously certified interconnected
units when Underwriters Laboratories (UL) decertifies the units. PG&E
may implement an acceptable mitigation procedure for recertification at
the customers expense.
3-10
May 1, 2003
Generation
Expanded E-NET Interconnection
Machine-Based Generation
In addition to customer-owned generator protection (such as voltage and
frequency relays), the following equipment may be required for
machine-based generating facilities:
The power quality requirement (see Attachment 10, Rule 2) may also
apply to machine-based generating facilities.
Notes
1. A reverse-power function is unacceptable as a substitute for fault
detection. An under-power function may be a viable substitute for
some fault-detection schemes. A utility-grade device with three,
independent, current-measuring elements may be required for the
generator.
2. An under-power function cannot be applied when inadvertent
export is a possibility.
3.10.
May 1, 2003
3-11
Generation
Expanded E-NET Interconnection
3.12.
Relay Grades
Two categories of relays are commonly used for interconnection
protection:
3.12.1.
Industrial-Grade Relays
Industrial-grade relays may be used for projects not exceeding
1,000 kW.
3-12
May 1, 2003
Generation
Expanded E-NET Interconnection
3.12.2.
Utility-Grade Relays
Utility-grade relays are more costly than industrial-grade relays.
For more information on utility-grade relays, please refer to
Section 4, Rule 21 Generating Facility Interconnection.
3.13.
A dedicated cable.
A microwave.
May 1, 2003
3-13
Generation
Expanded E-NET Interconnection
The addition of any new generation facility to the PG&E electric system
must not degrade the existing protection and control schemes or lower the
levels of safety and/or reliability for existing PG&E customers. For more
information on Rule 2 Description of Service, please refer to:
http://www.pge.com/customer_services/business/tariffs/pdf/ER2.pdf or
Attachment 10.
Many parts of the PG&E electric system have provisions for an alternate
feed. However, due to protection problems, there are some locations
where PG&E does not allow generation to be online while being fed from
an alternate source.
Whenever possible, PG&E provides the owner of the generating facility
with the option of not paying for upgrades. If the owner of the generating
facility pays for the upgrades, the owners facility may stay online while
being transferred to the alternate source. However, if the owner of the
generating facility does not pay for the upgrades, PG&E has the option of
shutting down the facility while it is being transferred to an alternate
source.
3.14.
Telephone interference.
3-14
May 1, 2003
Generation
Expanded E-NET Interconnection
Table 3-2
Generator-Protection Devices
Device
Number1
40 kW
or
Less
50/51
X2
X2
59
27
X3
Overfrequency
81O
Underfrequency
81U
X
X
Generator-Protection Device
Phase Overcurrent
Overvoltage
Undervoltage
41 kW 401 kW
to
and
400 kW Larger
51N
X4
51V
51C
X5
Reverse-Power Relay
32
X6
X6
X6
Direct-Transfer Trip
TT
X7
X7
X7
Notes
1. Please refer to Table 3-3, Standard Device Numbers, on Page 3-20
for device numbers, definitions, and functions.
2. When fault-detection is required, per CPUC Rule 21, the phase
overcurrent protection must be able to detect all line-end phase and
phase-fault conditions.
The generator must be equipped with a phase
instantaneous-overcurrent relay that can detect a line fault under
subtransient conditions.
The generator does not have to be equipped with a phase
instantaneous-overcurrent relay if the generator uses a 51V or 51C
relay. PG&E determines if a 51V or a 51C relay is better suited for the
specific project.
3. For generators rated at 40 kW or less, installing a contactor
undervoltage release may meet the undervoltage protection
requirement.
4. When fault detection is required, per CPUC Rule 21, a group of
generators, each of which is rated at less than 400 kW but whose
aggregate capacity is 400 kW or greater, must have an overcurrent
relay with voltage restraint (or voltage control, if determined by
PG&E) installed on each generator greater than 100 kW.
5. Depending on PG&Es circuit configuration and loading, PG&E will
determine if a generator must be equipped with a transfer trip on the
distribution-level interconnections.
6. A transfer trip must be installed if PG&E determines that there is
either one of the following conditions:
May 1, 2003
Generation
Expanded E-NET Interconnection
The following sections describe the protective and control devices that
must be installed on generators:
3.14.1.
Phase Overcurrent
Please see Table 3-3, Standard Device Numbers, on Page 3-20
(Device 50/51) for the definition and function of phase-overcurrent
relays.
3.14.2.
Over/Undervoltage Relay
The over/undervoltage relay is used to trip the generators circuit
breaker when the voltage is above or below PG&Es normal
operating level.
In the event that the generator carries load that is isolated from
PG&Es electric system, the over/undervoltage relay is used for
the generator and backup protection.
For all distribution interconnections, the undervoltage relay is set
at 88 % of the nominal voltage (106 V on the 120 V base).
The overvoltage relay is set at 110 % of the nominal voltage (132
V on the 120 V base).
3.14.3.
Over/Underfrequency Relay
The over/underfrequency relay is used to trip the generators
circuit breaker when the frequency is above or below PG&Es
normal operating level. It is used for the backup protection and
generator or turbine protection.
To maintain generation online during system disturbances, the
customer must coordinate the generators underfrequency relay
settings with those of other utilities in the Western Electricity
Coordinating Council (WECC). For more information about the
WECC, please refer to http://www.wecc.biz/main.html.
For all distribution interconnections, the underfrequency relay is
set at 58 Hz with a time delay of 30 seconds. The overfrequency
relay is set at 61 Hz with a time delay of 15 cycles (0.25 second).
3.14.4.
Ground-Fault-Sensing Scheme
The ground-fault-sensing scheme detects PG&Es power-system
ground faults and trips the generator breaker or the generators
main circuit breaker, preventing the generator from continuously
contributing to the ground fault.
The ground-fault-sensing scheme must be able to detect faults
between the PG&E systems side of the dedicated transformer and
the end of PG&Es distribution circuit.
3-16
May 1, 2003
Generation
Expanded E-NET Interconnection
PG&E will determine the suitability of installing a relay with a voltage restraint (Device 51V) or a voltage control (Device
51C) on a case-by-cases basis, depending on the system characteristics for the specific interconnection project.
May 1, 2003
3-17
Generation
Expanded E-NET Interconnection
3.14.6.
Fault-Interrupting Devices
PG&E must review and approve all customer-selected
fault-interrupting devices.
There are two basic types of fault-interrupting devices for
distribution interconnections:
Circuit Breakers
Fuses
3.14.6.1.
Circuit Breakers
A three-phase circuit breaker is the required
fault-interruption device at the point of interconnection due
to its simultaneous three-phase operation and its ability to
coordinate with PG&E line-side devices. The three-phase
circuit breaker is able to automatically separate the
generator from PG&Es electric system upon detection of a
circuit fault.
The customer may install additional circuit breakers and
protective relays, which are not required for
interconnection, in the generation facilities.
The interconnection circuit breaker must have sufficient
capacity to interrupt the maximum available fault current it
may experience and must be equipped with accessories to
perform the following functions:
3.14.6.2.
Fuses
Fuses are single-phase, direct-acting sacrificial links that
melt to interrupt fault current and protect equipment.
The customer must replace blown fuses manually after
each fault before the facility may be returned to service.
3-18
May 1, 2003
Generation
Expanded E-NET Interconnection
May 1, 2003
3-19
Generation
Expanded E-NET Interconnection
Table 3-3
Device
Number
Device
Number
15
A speed-of-frequency
matching device functions to
match and hold the speed or
the frequency of a machine or
of a system equal to, or
approximately equal to, that of
another machine, source, or
system.
50
An instantaneous overcurrent
or rate-of-rise relay indicates a
fault in the apparatus or circuit
that is being protected, when
there is an excessive value of
current, or an excessive rate of
current rise.
21
51
25
Synchronizing and
synchronism-check devices
permit two alternating current
(ac) circuits to be paralleled
when they are within the
desired limits of frequency,
phase angle, and voltage.
52
27
An undervoltage relay
functions on a given value of
undervoltage.
59
32
A reverse-power relay
functions on a reverse-power
flow at a given set point.
60
A voltage-balance relay
operates on a given difference
in voltage between two circuits.
46
A reverse-phase or
phase-balance current relay
functions when the polyphase
currents are of reverse-phase
sequence, or when the
polyphase currents are
unbalanced or contain negative
phase-sequence components
exceeding a given amount.
61
A current-balance relay
operates on a given difference
in the current input or output of
two circuits.
47
A phase-sequence voltage
relay functions on a
predetermined value of
polyphase voltage in the
desired phase sequence.
62
A time-delay stopping, or
opening, relay delays a
shutdown, stopping, or opening
operation in an automatic
sequence initiated by another
device.
3-20
May 1, 2003
Generation
Expanded E-NET Interconnection
Table 3-3
Device
Number
Device
Number
67
An ac directional-overcurrent
relay functions on a desired
value of ac overcurrent flowing
in a predetermined direction.
87
A differential-protective relay
functions on a percentage of
the phase angle or other
quantitative difference between
two currents or by other
electrical quantities.
79
90
81
94
Table 3-4
Square D
PRS 250
Synchronizing
Relays
(25)
Undervoltage
Relay
(27)
Basler Electric
6-327
BE4-27
PR-201-UV
BE4-51
Nondirectional
Overcurrent Relay
(50/51)
Overvoltage Relay
(59)
6-327
BE4-59
PR-101-OV
Frequency Relay
(Under/Over)
( 81U/O)
6-328
BE4-81-O/U
R-101-OUF
Overcurrent Relay
(51N,V,C)
1
For utility-grade relays, please see Table 6-3, Utility-Grade Relays for Generation Application, on
Page 6-9.
May 1, 2003
3-21
Generation
Expanded E-NET Interconnection
Notes
1. Customers may install industrial-grade relays only on projects that are
greater than 10 kW or less than or equal to 1 MW and are
interconnected to distribution circuits.
2. Relays used in a ground fault-detection scheme must be utility grade.
3. The above table contains information regarding products,
manufacturers, and representatives. This table is not all-inclusive. The
inclusion or omission of a product, manufacturer, or representative is
not meant to be an indication of the quality or reliability of a product
or service. No endorsements or warranties are implied.
Other types of relays may be acceptable, but PG&E must review and
approve the certified test results performed by an independent party
acceptable to PG&E before the facility may be installed and released
for commercial operation.
Contact PG&Es System Protection department for the test
specifications for each relay.
3-22
May 1, 2003
Generation
Expanded E-NET Interconnection
3-Wire Systems, Service Transformer Connected Wye on 12 kV Side
Service Transformer
Generator
12 kV-240 V
59
N
13
Service Transformer
Generator
3 PTs
12 kV-240 V
R
13
59
N
Figure 3-1
Recommended Ground Detection Schemes
12 kV Distribution Circuits
May 1, 2003
3-23
Generation
Expanded E-NET Interconnection
4-Wire System, Service Transformer Connected Ground Wye on 21 kV Side
21 kV
Service Transformer
Generator
Neutral
51
G
Service Transformer
Generator
Neutral
Ground Bank*
51
G
Figure 3-2
Recommended Ground Detection Schemes
21 kV Distribution Circuits
3.16.
Metering Requirements
E-NET installations are generally designed to operate in parallel with the
PG&E system.
The disconnect requirements are specified by PG&E. Please see
Engineering Document 060559, Disconnect Switches For
Interconnection With Small Power Producers And Cogenerators, located
in Attachment 3.
3-24
May 1, 2003
Generation
Expanded E-NET Interconnection
May 1, 2003
3-25
Generation
Expanded E-NET Interconnection
Table 3-5
Height Requirement
Telemetering Requirements
If the meter is read via a telephone line, the customer is responsible for
installing the line and establishing service. If a land line is unavailable and
cellular signals are acceptable, a cellular phone may be used.
If the meters telephone line cannot be dedicated to the meter, the
customer, with approval from PG&Es local metering group, may arrange
to use a line sharing switch.
The telephone-line termination in switchboards, panels, pole-mounted
meters, and pedestals must be located as follows:
When cellular phones are used, the same location requirements apply to
the power supply when measured from the load side of the meter and
located outside PG&Es sealable section.
3-26
May 1, 2003
Generation
Expanded E-NET Interconnection
3.18.
3.19.
Communication
PG&E may require that communication circuits be installed to provide
protection, Supervisory Control & Data Acquisition (SCADA), and voice
communications between PG&E and the customers generation facilities.
The customer is responsible for the monthly costs and the costs associated
with the installation of EMS, SCADA and protection circuits. In addition,
the customer is responsible for the costs incurred by PG&E personnel
while involved in assisting the telephone company personnel in making
repairs to the leased circuits.
When external communication circuits are installed, the responsible party
must ensure that the high-voltage protection (HVP) on these circuits and
related equipment meets all the applicable standards.
3.20.
Operation Requirements
If the unit is equipped with a disconnect switch, that switch must be
accessible to PG&Es employees. When maintenance or other work
procedures are scheduled, this disconnect switch may have to be opened
and locked for the protection of PG&E employees.
3.20.1.
May 1, 2003
3-27
Generation
Expanded E-NET Interconnection
3-28
May 1, 2003
Generation
Section 4
Rule 21 Generating Facility Interconnection
4.1.
Introduction
Rule 21, Generating Facility Interconnections, describes the
interconnection, operating, and metering requirements for retail customers
who want to connect their generating facilities to PG&Es distribution
system, which is under the jurisdiction of the California Public Utilities
Commission (CPUC).
PG&E allows interconnection of generating facilities with its distribution
system if the customer meets all the requirements of Rule 21.
Rule 21-Generating Facility Interconnections, which can be found at:
http://www.pge.com/customer_services/business/tariffs/pdf/ER21.pdf or
in Attachement 11, defines the interconnection process for customers who
install generators, including solar, wind, or conventional gas-fired
generators, on their premises to offset their loads.
Rule 21-type generators operate in parallel with PG&Es electric
distribution grid system.
The cost of interconnecting a generating facility with PG&Es system can
be affected by variables such as the circuit loading, the location, and the
size and type of the generating facility.
For more information on Rule 21 generators and the interconnection
process, please refer to PG&Es website
http://www.pge.com/002_biz_svc/gen/retail_gen_rule_21.shtml.
4.2.
Application Form/Fees
Customers who want to interconnect under the provisions of Rule
21 must fill out a Generating Facility Interconnection
Application (Form No. 79-974 in Attachment 12), and follow the
process set forth in the form.
The application must include the following.
May 1, 2003
4-1
Generation
Rule 21 Generating Facility Interconnection
Application Completeness
PG&E has 10 days, from the day of the receipt of the application,
to check if the applicant has provided complete information.
A completed application includes the following:
Initial Review
If PG&E deems that the application is complete, PG&E has 10
business days to perform the initial review.
At any time that PG&E deems the application incomplete, the
10-day clock for the initial review phase stops. However, as soon
as the applicant provides the missing information and PG&E
deems the application complete, a new 10-day clock starts.
If PG&E determines that the application qualifies for a simplified
interconnection, PG&E will provide a written description of the
requirements, as well as the agreements described in Section 4.3.
(Rule 21 Agreement on Page 4-4).
4.2.4.
Supplemental Review
During the initial review, if PG&E determines that the application
does not qualify for a simplified interconnection, PG&E will
perform a supplemental review.
PG&E will provide one of the following items after the
supplemental review:
4-2
Generation
Rule 21 Generating Facility Interconnection
Interconnection Study
After the initial or supplemental review, if PG&E determines that a
detailed interconnection study is necessary, PG&E will offer an
agreement that sets forth the following:
This agreement will provide cost estimates for the fixed price or
actual cost billing options.
4.2.6.
May 1, 2003
4-3
Generation
Rule 21 Generating Facility Interconnection
Rule 21 Agreement
Generator interconnection projects under the provisions of Rule 21
generally require one or more of the following agreements. Copies of
these forms can be found in Attachment 12.
4.3.1.
4.3.2.
4.3.3.
4-4
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
4.3.5.
4.3.6.
4.3.7.
Other Agreements
The following are other agreements that may be applicable:
May 1, 2003
4-5
Generation
Rule 21 Generating Facility Interconnection
4.4.
4.5.
Preparallel Inspection
PG&E will perform a final inspection of the system before operation. This
allows PG&E to ensure that the system has been installed in accordance
with the originally submitted specifications.
After the inspection, the customer will receive written approval from
PG&E to operate the system in parallel with PG&Es grid.
Note: The system must not be operated until the customer
has received a written approval from PG&E.
4-6
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
4.6.
Timeline
Table 4-1 below outlines the time frames of the review and approval
process:
Table 4-1
Timeline
10 days
Review
Application Completeness
PG&E must verify that the following items are received
before conducting the initial review:
$800 initial review fee
The following information is provided with sufficient
detail:
The project name and location.
A single-line drawing.
The generator type, size, and data.
A list of protective devices.
The type and mode of a disconnect switch.
10 days
Initial Review
Engineering review using the Initial Review Process.
Please see Sample of the Initial Review Process, in
Attachment 5.
4.7.
Interconnection Study
PG&E will determine the timeline and the cost for an
interconnection study on a case-by-case basis.
Fees/Charges
The following fees are charged for reviews:
Please note that up to $5,000 of the review and/or study fees will be
waived for solar-generating facilities up to 1 MW that do not export
power to the grid.
May 1, 2003
4-7
Generation
Rule 21 Generating Facility Interconnection
4.8.
Technical Requirements
The specific requirements of this section apply on a case-by-case basis to
any retail generation customers who do not meet one or more of the
simplified interconnections criteria set by the California Energy
Commission (CEC) Rule 21, here referred to as CPUC Rule
21-Generating Facility Interconnections. See Attachment 11.
4.8.1.
Interconnection Requirements
When interconnecting facilities to the PG&E distribution system, it
is important to minimize the potential hazard to life and property.
A basic safety rule requires automatic detection and isolation of
abnormal system troubles within a reasonable time.
Important system troubles are fault conditions, such as a short
circuit.
4.8.2.
4-8
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
May 1, 2003
4-9
Generation
Rule 21 Generating Facility Interconnection
4.9.
General
A generator must be equipped with a manual disconnect switch.
As a means of electrically isolating PG&Es electric system from
the customers systems, the customer must provide a
PG&E-operated disconnect device. To establish a visually open
working clearance, in accordance with PG&Es safety rules and
practices, the manual disconnect must be opened during all
maintenance and repair work.
For interconnections of 2.4 kV and above, the disconnect switch
must be located at the point of interconnection with PG&E. The
disconnect switch must be gang-operated, three-pole, and lockable.
If the disconnect switch will be located on PG&Es side of the
interconnection point, PG&E must install it at the customers
expense.
If the disconnect switch will be located on the customers side, it
must be furnished and installed by the customer. If the disconnect
device is in the customers substation, it must be located on the
substations dead-end structure and have a PG&E-approved
operating platform. The customer must use only PG&E-approved
devices.
PG&E must inspect and approve the installation before parallel
operation is allowed.
The disconnect switch must not be used to make or break parallels
between PG&Es electric system and the customers power system.
The devices enclosure and operating handle (when present) must
be locked at all times, using PG&Es padlocks.
The disconnect switch must be visible and easily accessible to
PG&E employees. When installed on the customers side of the
interconnection, the switch must be installed close to the metering.
It must be identified with a PG&E-designated switch-number
plate.
4.9.2.
Specifications
The manual disconnect switch must meet the following
requirements:
4-10
Be gang-operated.
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
4.9.3.
4.9.4.
4.10.
May 1, 2003
4-11
Generation
Rule 21 Generating Facility Interconnection
Have met all the criteria set by the CEC Rule 21, Section J, as
tested by a nationally recognized testing laboratory (NRTL)
acceptable to PG&E and the test reports must have been approved
by PG&E.
PG&E requires additional testing for multiple units unless the generator
has received an earlier approval.
Separate single-unit or multiple-unit inverters that do not meet
Underwriters Laboratories Standard UL1741 or have not been adequately
tested will not be granted commercial operation status and the customer is
not permitted to interconnect to the system.
PG&E reserves the right to disconnect previously certified interconnected
units when Underwriters Laboratories (UL) decertifies the units. PG&E
may implement an acceptable mitigation procedure for recertification at
the customers expense.
Therefore, it is critical that the interconnecting applicant understands all
of PG&Es technical requirements before the applicant does an
engineering design or procures material.
At PG&Es discretion, noncertified inverters may be interconnected if the
applicant meets the additional requirements. The additional requirements
may include, but are not limited to, those listed in Table 3-3, Standard
Device Numbers, on Page 3-20.
4.12.
Machine-Based Generation
In addition to the standard generator protection (such as voltage and
frequency relays), the following equipment may be required for
machine-based generating facilities.
The power quality requirement (see Attachment 10, Rule 2) may also
apply to machine-based generating facilities.
4-12
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
Notes
1. A reverse-power function is unacceptable as a substitute for fault
detection. An under-power function may be a viable substitute for
some fault-detection schemes. A utility-grade device with three,
independent, current-measuring elements may be required for the
generator.
2. An under-power function cannot be applied when inadvertent
export is a possibility.
4.13.
4.14.
May 1, 2003
4-13
Generation
Rule 21 Generating Facility Interconnection
Relay Grades
Two categories of relays commonly used for interconnection protection
are:
Industrial-grade relays.
Utility-grade relays.
4.15.1.
Industrial-Grade Relays
Industrial-grade relays are less reliable than utility-grade relays
and may be installed only in projects up to 1,000 kW (aggregate
nameplate) that are interconnected to distribution circuits. (Please
see Table 4-4, Industrial-Grade Relays for Generation
Application, on Page 4-30.)
Please refer to the following sections for the protection
requirements for units with an individual output capacity of 100
kW and a total aggregate generation of 400 kW or larger:
4.15.2.
Utility-Grade Relays
Utility-grade relays, used by electric utilities, have much higher
reliability and accuracy than industrial-grade relays (please see
Table 6-3 Utility-Grade Relays for Generation Application, on
Page 6-9).
These devices typically have draw-out cases and indicating targets.
In addition, to facilitate testing and troubleshooting, these devices
are equipped with better recording capability than industrial-grade
relays.
Utility-grade relays must be installed in the following
circumstances:
4-14
Generation
Rule 21 Generating Facility Interconnection
4.15.3.
May 1, 2003
4-15
Generation
Rule 21 Generating Facility Interconnection
4.16.
A dedicated cable.
4-16
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
The addition of any new generation facility to the PG&E electric system
must not degrade the existing protection and control schemes or lower the
levels of safety and/or reliability for existing PG&E customers. For more
information, please refer to Rule 2 Description of Service at:
http://www.pge.com/customer_services/business/tariffs/pdf/ER2.pdf or
Attachement 10.
Many parts of the PG&E electric system have provisions for an alternate
feed. However, due to protection problems, there are some locations
where PG&E does not allow generation to be online while being fed from
an alternate source.
Whenever possible, PG&E provides the customer with the option of not
paying for upgrades. If the customer pays for the required upgrades, the
customers facility may stay online while being transferred to the alternate
source. However, if the customer does not pay for the upgrades, PG&E
has the option of shutting down the facility instead of transferring it to an
alternate source.
4.17.
Telephone interference.
May 1, 2003
4-17
Generation
Rule 21 Generating Facility Interconnection
Table 4-2
Generator-Protection Devices
Device1
Number
40 kW
or
Less
50/51
X2
X2
59
27
X3
Overfrequency
81O
Underfrequency
81U
51N
X4
51V
51C
X5
Generator-Protection Device
Phase Overcurrent
Overvoltage
Undervoltage
41 kW 401 kW
to
and
400 kW Larger
Reverse-Power Relay
32
X6
X6
X6
Direct-Transfer Trip
TT
X7
X7
X7
Notes
1. Please refer to Table 4-3, Standard Device Numbers, on Page 4-29
for device numbers, definitions, and functions.
2. When fault-detection is required, per CPUC Rule 21, the phase
overcurrent protection must be able to detect all line-end phase and
phase-fault conditions.
The generator must be equipped with a phase
instantaneous-overcurrent relay that can detect a line fault under
subtransient conditions.
The generator does not have to be equipped with a phase
instantaneous-overcurrent relay if the generator uses a 51V or 51C
relay. PG&E determines if a 51V or a 51C relay is better suited for the
specific project.
3. For generators rated at 40 kW or less, installing a contactor
undervoltage release may meet the undervoltage protection
requirement.
4. If CPUC Rule 21 requires fault protection, the ground-fault detection
is required for any noncertified inverter-based, induction, or
synchronous generating facility.
Synchronous generators with an aggregate generation over 40 kW and
induction generators with an aggregate generation over 100 kW
require ground-fault detection.
5. When CPUC Rule 21 requires fault protection, a group of generators,
each less than 400 kW but whose aggregate capacity is 400 kW or
greater, must have an overcurrent-relay with voltage restraint (or
voltage control, if determined by PG&E) installed on each generator
rated greater than 100 kW.
4-18
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
Phase Overcurrent
Please see Table 4-3, Standard Device Numbers, on Page 4-29
(Device 50/51) for the definition and function of the
phase-overcurrent relays.
4.17.2.
Over/Undervoltage Relay
The over/undervoltage relay is used to trip the interrupting device
when the voltage is above or below PG&Es normal operating
level.
In the event that the generator carries load that is isolated from
PG&Es electric system, the over/undervoltage relay is used for
generator and backup protection.
For all distribution interconnections, the undervoltage relay is set
for 88% of the nominal voltage (106 V on the 120 V base) unless
system conditions require otherwise.
The overvoltage relay is set for 110% of the nominal voltage (132
V on the 120 V base).
4.17.3.
Over/Underfrequency Relay
The over/underfrequency relay is used to trip the interrupting
device when the frequency is above or below PG&Es normal
May 1, 2003
4-19
Generation
Rule 21 Generating Facility Interconnection
Ground-Fault-Sensing Scheme
4.17.4.1.
General
The ground-fault-sensing scheme detects PG&Es
power-system ground faults and trips the generators
circuit breaker or the main circuit breaker, preventing the
generator from continuously contributing to a ground fault.
The ground-fault-sensing scheme is able to detect faults
between the PG&E systems side of the dedicated
transformer and the end of PG&Es distribution circuit.
The following types of transformer connections, provided
with the appropriate relaying equipment, are commonly
used to detect system ground faults:
4.17.4.2.
Distribution Interconnections
For a transformer connected in a delta configuration to the
distribution system with a delta connection on the system
side, PG&E recommends a separate grounding
transformer, in addition to the appropriate relaying
equipment.
For a transformer connected in a grounded-wye
configuration to the 3-wire distribution system with a
grounded wye on the system side, the generator must have
a single-phase potential transformer between the neutral
and ground connection, in addition to the appropriate
relaying equipment.
For the typical, distribution-level interconnection schemes,
please see the following drawings:
4-20
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
PG&E will determine the suitability of a voltage restraint (device 51V) or a voltage control (device 51C) relay on a
case-by-cases basis and depending on the system characteristics for the specific interconnecting project.
May 1, 2003
4-21
Generation
Rule 21 Generating Facility Interconnection
Reverse-Power Relay
Please see Table 4-2, Generator-Protection Devices, on Page
4-18 (Device #32) for the definition and function of a
reverse-power relay.
4.17.7.
Fault-Interrupting Devices
PG&E must review and approve all customer-selected
fault-interrupting devices.
There are two basic types of fault-interrupting devices for
distribution interconnections:
Circuit Breakers
Fuses
4.17.7.1.
Circuit Breakers
A three-phase circuit breaker is the required
fault-interrupting device at the point of interconnection,
due to its simultaneous three-phase operation and its ability
to coordinate with PG&E line-side devices. The
three-phase circuit breaker is able to automatically separate
the generator from PG&Es electric system upon detection
of a circuit fault.
The customer may install additional circuit breakers and
protective relays, which are not required for
interconnection, in the generation facilities.
The interconnection circuit breaker must have sufficient
capacity to interrupt the maximum fault current it may
experience and must be equipped with accessories to
perform the following functions:
4-22
Generation
Rule 21 Generating Facility Interconnection
4.17.7.2.
Fuses
Fuses are single-phase, direct-acting sacrificial links that
melt to interrupt fault current and protect the equipment.
The customer must replace blown fuses manually after
each fault before the facility may be returned to service.
Only trained personnel may replace overhead primary
fuses.
Fuses cannot be used as the primary protection for
three-phase generation facilities because fuses:
Synchronous Generators
The customer must ensure that the generating unit meets all the
applicable standards of the:
May 1, 2003
4-23
Generation
Rule 21 Generating Facility Interconnection
The prime mover and the generator must be able to operate within
the full range of voltage and frequency excursions that may exist
on PG&Es electric system without damaging the generator.
4.17.9.
Synchronizing Relays
The purpose of synchronizing devices is to ensure that a
synchronous generator parallels with PG&Es electric system
without causing disturbance to other customers and facilities
(present and in the future) that are connected to the same system.
Synchronizing devices also ensure that the generator will not be
damaged due to an improper parallel action. Please refer to
Attachment 8, Generator Automatic Synchronizers for Generation
Entities, for additional information and requirements.
Synchronous generators and other generators with stand-alone
capability must use one of the methods in the following sections to
synchronize with PG&Es electric system.
4.17.9.1.
4.17.9.2.
4-24
Generation
Rule 21 Generating Facility Interconnection
4.17.9.3.
4.17.9.4.
4-25
Generation
Rule 21 Generating Facility Interconnection
4.18.
Induction Generators
Induction generators and other generators with no inherent var (reactive
power) control capability must be able to provide an amount of reactive
power equivalent to that required for a synchronous generator.
4-26
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
4.20.
May 1, 2003
4-27
Generation
Rule 21 Generating Facility Interconnection
4-28
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
Table 4-3
Device
Number
Device
Number
15
A speed-of-frequency
matching device functions to
match and hold the speed or
the frequency of a machine or
of a system equal to, or
approximately equal to, that of
another machine, source, or
system.
50
21
51
25
Synchronizing and
synchronism-check devices
permit two alternating current
(ac) circuits to be paralleled
when they are within the
desired limits of frequency,
phase angle, and voltage.
52
27
An undervoltage relay
functions on a given value of
undervoltage.
59
An overvoltage relay
functions on a given value of
overvoltage.
32
A reverse-power relay
functions on a reverse-power
flow at a given set point.
60
A voltage-balance relay
operates on a given difference
in voltage between two
circuits.
46
A reverse-phase or
phase-balance current relay
functions when the polyphase
currents are of reverse-phase
sequence, or when the
polyphase currents are
unbalanced or contain
negative phase-sequence
components exceeding a
given amount.
61
A current-balance relay
operates on a given difference
in the current input or output
of two circuits.
47
A phase-sequence voltage
relay functions on a
predetermined value of
polyphase voltage in the
desired phase sequence.
62
A time-delay stopping, or
opening, relay delays a
shutdown, stopping, or
opening operation in an
automatic sequence initiated
by another device.
May 1, 2003
4-29
Generation
Rule 21 Generating Facility Interconnection
Table 4-3
Device
Number
Device
Number
67
An ac
directional-overcurrent relay
functions on a desired value of
ac overcurrent flowing in a
predetermined direction.
87
A differential-protective relay
functions on a percentage of
the phase angle or other
quantitative difference between
two currents or by other
electrical quantities.
79
90
81
94
Table 4-4
Square D
PRS 250
Synchronizing
Relays
(25)
Undervoltage
Relay
(27)
Basler Electric
6-327
BE4-27
PR-201-UV
BE4-51
Nondirectional
Overcurrent Relay
(50/51)
Overvoltage Relay
(59)
6-327
BE4-59
PR-101-OV
Frequency Relay
(Under/Over)
( 81U/O)
6-328
BE4-81-O/U
R-101-OUF
Overcurrent Relay
(51N,V,C)
1
For utility-grade relays, please see Table 6-3, Utility-Grade Relays for Generation Application, on
Page 6-9.
4-30
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
Notes
1. Customers may install industrial-grade relays only on projects that are
greater than 10 kW or less than or equal to 1 MW and are
interconnected to distribution circuits.
2. Relays used in a ground fault-detection scheme must be utility grade.
3. The above table contains information regarding products,
manufacturers, and representatives. This table is not all-inclusive. The
inclusion or omission of a product, manufacturer, or representative is
not meant to be an indication of the quality or reliability of a product
or service. No endorsements or warranties are implied.
Other types of relays may be acceptable, but PG&E must review and
approve the certified test results performed by an independent party
acceptable to PG&E before the facility may be installed and released
for commercial operation.
Contact PG&Es System Protection department for the test
specifications for each relay.
May 1, 2003
4-31
Generation
Rule 21 Generating Facility Interconnection
3-Wire Systems, Service Transformer Connected Wye on 12 kV Side
Connect a 12 kV-240 V distribution transformer (or a 12 kV-120 V PT) between the neutral and
ground; load the secondary with a 13 resistor, and an overvoltage relay.
For 12 kV-240 V:
Turns ratio, N = 12,000 = 50
240
Maximum secondary voltage, V3 = 12,000 = 138.5 V
3 (50)
Short time ratings for resistor and transformer:
V2 = 138.52 = 1,477 W (or VA)
R
13
12 kV
Service Transformer
Generator
12 kV-240 V
59
N
13
Service Transformer
Generator
3 PTs
12 kV-240 V
R
13
59
N
Figure 4-1
Recommended Ground Detection Schemes
12 kV Distribution Circuits
4-32
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
4-Wire System, Service Transformer Connected Ground Wye on 21 kV Side
21 kV
Service Transformer
Generator
Neutral
51
G
Service Transformer
Generator
Neutral
Ground Bank*
51
G
Figure 4-2
Recommended Ground Detection Schemes
21 kV Distribution Circuits
4.22.
Metering Requirements
Rule 21 installations are generally designed to operate in parallel with the
PG&E system.
The disconnect requirements are specified by PG&E and listed in the
Engineering Document 060559, Disconnect Switches for Interconnection
with Small Power Producers and Cogenerators. (See Attachment 3)
May 1, 2003
4-33
Generation
Rule 21 Generating Facility Interconnection
Height Requirement
4.23.
Telemetering Requirements
If the meter is read via a telephone line, the customer is responsible for
installing the line and establishing service. If a land line is unavailable,
and cellular signals are acceptable, a cellular phone may be used.
4-34
May 1, 2003
Generation
Rule 21 Generating Facility Interconnection
When cellular telephones are used, the same location requirements apply
to the power supply when measured from the load side of the meter and
located outside PG&Es sealable section.
4.24.
Communication
PG&E may require that communication circuits be installed to provide
protection, Supervisory Control & Data Acquisition (SCADA), and voice
communication between PG&E and the customers generation facilities.
The customer is responsible for the monthly costs and the costs associated
with the installation of EMS, SCADA and protection circuits. In addition,
the customer is responsible for the costs incurred by PG&E personnel
while involved in assisting the telephone company personnel in making
repairs to the leased circuits.
When external communication circuits are installed, the responsible party
must ensure that the high-voltage protection (HVP) on these circuits and
related equipment meets all the applicable standards.
4.25.
Operation Requirements
If the unit is equipped with a disconnect switch, the switch must be
accessible to PG&E employees. When maintenance or other work
procedures are scheduled, this disconnect switch may have to be opened
and locked for the protection of PG&E employees.
4.25.1.
May 1, 2003
4-35
Generation
Rule 21 Generating Facility Interconnection
Other Requirements
The maximum capacity for single-phase generating facilities
connected to a shared, single-phase secondary must not exceed 20
kVA.
Customers must install a 240 V service for generating facilities
with a center-tap neutral so that no more than 6 kVA of imbalance
capacity exists between the two sides of the 240 V service.
4.25.3.
System Upgrades
After PG&Es engineering departments review, PG&E may
require system upgrades so that the system is able to accommodate
the interconnection of the distribution generation (DG) system.
4-36
May 1, 2003
Generation
Section 5
Portable, Emergency, Standby Generators Interconnection
5.1.
Introduction
During a power outage, customers can use an electric generator as a
standby system to keep lights and appliances running until service is
restored.
A generator can power the refrigerators, freezers and other essential
equipment during a prolonged outage. However, generators are expensive
and noisy, and can pose serious safety hazards. Therefore, customers must
follow all the manufacturers safety instructions.
According to the law, customers are not allowed to connect a
permanently-installed or portable generator to another power source, such
as PG&Es power lines.
Owners and operators of generators are responsible for ensuring that the
generators are used correctly, and that the electricity from the unit does
not backfeed, i.e., flow into PG&Es power lines. If the generator is not
used correctly, it may endanger lives and damage property.
5.2.
Portable Generators
Customers must follow the safety requirements listed below:
Ensure that the total electric load on the generator does not exceed
the manufacturers rating.
Use the lowest wattage of light bulbs that can still provide a
safe level of light.
Remember that the greater the load on the generator, the more fuel it will
use.
Keep cords out of the way so that they will not be a tripping hazard,
especially in dimly lit doorways or halls. Customers must never run
cords under rugs or carpets where heat may build up or damage to a
cord may not be noticed.
May 1, 2003
5-1
Generation
Portable, Emergency, Standby Generators Interconnection
5.3.
Standby Generators
Only a qualified professional, such as a licensed electric contractor, may
install a permanent standby generator.
When a generator is permanently connected to a customers electric
system, it energizes the buildings wiring. This type of installation
requires a device that prevents the generator from being connected to
PG&Es power lines.
PG&E recommends using a double-pole, double-throw transfer switch to
keep the generator from backfeeding into PG&Es system.
(To see a diagram of a transfer switch, please refer to Figure 5-1 below or
http://www.pge.com/004_safety/images/transfer_large.gif)
To Meter
To Main
Fuse Box
To Generator
Figure 5-1
Transfer Switch
5-2
Generation
Portable, Emergency, Standby Generators Interconnection
5.3.1.
5.4.
Safety Requirements
Emergency Generators
There are two methods of transferring an electric power supply between
the PG&E source and the emergency generator system:
5.4.1.
5.4.2.
May 1, 2003
5-3
Generation
Portable, Emergency, Standby Generators Interconnection
The transfer of load from PG&E to the emergency source and back
to PG&E can be done without causing the customer to experience
an outage.
5.4.3.
Interconnection Requirements
The list below gives the requirements for interconnecting
emergency generators that use open or closed transfer schemes.
5.4.3.1.
Interconnection Study
A study is not required if the applicant meets the
requirements outlined in this section and submits the
required reports and drawings for review and approval.
5.4.3.2.
Transfer Switch
The transfer switch must be rated for the maximum
possible load current.
5.4.3.3.
Operation/Clearance
For the purposes of any clearance or line work, the
customer must consider the emergency generator as a
power source.
Before a customer may perform any load transfers by the
make-before-break transfer method, the customer must
notify the responsible operation center of the intent to
transfer load to the emergency generator and back to the
5-4
May 1, 2003
Generation
Portable, Emergency, Standby Generators Interconnection
5.4.3.6.
Make-Before-Break Requirements
5.4.3.6.1.
Transfer Switch
In the event that the transfer switch closes into a
fault condition, the transfer switch must be rated
for the level of fault possible in the system.
In the event that the transfer switch fails, the
customer must ensure that there is an interlock
that will trip either the main or the generators
circuit breaker, so that the unit will not remain
paralleled to PG&Es electric system.
The controls for the transfer switch must prevent
parallel operation of the customers generator and
PG&Es electric system for an extended period of
time.
Customers who have systems that allow parallel
conditions to exist for more than 0.5 seconds (30
cycles) on the transmission system and more than
1 second (60 cycles) on the distribution system
must meet an additional set of requirements
outlined in Section 4, Rule 21 Generating
Facility Interconnection, of this manual.
5.4.3.6.2.
Manual Disconnect
The customer must provide a manual disconnect,
located at the point of interconnection, that may
be used to establish a visually open safety
clearance to protect PG&Es employees working
on PG&Es electric system.
The manual disconnect must be:
May 1, 2003
Operated by PG&E.
5-5
Generation
Portable, Emergency, Standby Generators Interconnection
5.4.3.6.3.
Synchronizing Function
The customer must do the following to ensure that
the load is transferred safely and smoothly:
5.4.3.6.4.
Protection
The emergency generators are paralleled with
PG&Es electric system. Therefore, in the event of
a fault on the system during a load transition, the
customer must have protective devices to prevent
the customers generator from remaining
connected to PG&Es electric system.
It is important to prevent damages on the
customers equipment, PG&Es electric system,
and other PG&E customers equipment caused by
possible back-feeding of the customers power to
the PG&E system.
In most installations, the customer installs a
reverse-power relay to meet this protection
requirement.
The customer must install this relay on the
customers side of the service transformer that is
connected to PG&Es electric system.
To ensure that reverse power flow is detected
before it actually enters PG&Es electric system
5-6
May 1, 2003
Generation
Portable, Emergency, Standby Generators Interconnection
Dedicated Transformer
Due to the fact that the emergency generator may
be connected in parallel with PG&Es electric
system, all transfer schemes of the
make-before-break type must have a dedicated
transformer.
The use of dedicated transformers makes it less
likely that other PG&E customers will be affected
by transfer activities. In addition, customers need
a dedicated transformer to install the
reverse-power relay scheme.
May 1, 2003
5-7
Generation
Portable, Emergency, Standby Generators Interconnection
5-8
May 1, 2003
Load
Section 6
Technical Requirements for Load Entities
6.1.
Purpose
This section specifies the technical requirements for electric load
customers interconnecting to the Pacific Gas and Electric Companys
(PG&E) primary distribution system. It applies to all existing, as well as
all new, primary service (PS) customers.
If the interconnection involves load and generation, the information in the
following generation sections applies:
6.2.
Applicability
The applicable protection standards of this section apply to all PS
customers interconnecting to any part of PG&Es primary distribution
system.
To ensure consistency with the applicable reliability criteria, PG&E has
developed protection standards to govern the design, inspection, and
testing of the protective devices.
6.3.
May 1, 2003
6-1
Load
Technical Requirements for Load Entities
These facilities, in addition to other protection facilities, are termed system protection facilities.
6-2
May 1, 2003
Load
Technical Requirements for Load Entities
Facilities that fail to meet the above testing requirements are subject to
either a delay in service or disconnection from the PG&E power system.
6.3.1.
May 1, 2003
6-3
Load
Technical Requirements for Load Entities
Single-line diagrams.
Control diagrams.
Manufacturer
Style
Types
Ranges
Settings
Power factor.
Load factor.
Starting currents.
6-4
Load
Technical Requirements for Load Entities
6.3.2.
6.4.
May 1, 2003
6-5
Load
Technical Requirements for Load Entities
Request that the PS customer supply test and supporting data from
the manufacturer. Such tests must be performed at the PS customers
expense and before PG&Es approval of the relay for
interconnection use2.
The PG&E-required relays must be able to detect all phase and ground
faults and coordinate with the appropriate PG&E line equipment.
Table 6-1
Protection Device
Device10 Number
34.5 kV or less
50/51
50/51N
Device Number
50
51
6.4.1.
Fault-Interrupting Devices
For each particular application, PG&E must review and approve
the fault-interrupting devices that the PS customer selects.
There are two basic types of fault-interrupting devices available
for distribution systems:
Circuit breakers
Fuses
There are additional system tests associated with communication-assisted protection. These tests (also referred to as end-to-end satellite tests) require all terminals of a transmission line be tested as a system and
include the protection, communication equipment and medium between the interconnected terminals.
Please refer to Attachment 6 for more information.
6-6
May 1, 2003
Load
Technical Requirements for Load Entities
6.4.1.1.
Circuit Breakers
When a circuit fault is detected, a three-phase circuit
breaker at the point of interconnection automatically
separates the PS customers equipment from PG&Es
system.
The PS customer may install additional circuit breakers for
operating and protecting the facility. However, PG&E does
not require that the PS customer install these additional
circuit breakers.
The interconnection circuit breaker must have sufficient
capacity to interrupt the maximum available fault current
at its location. It must be equipped with accessories to
perform the following functions:
Fuses
PG&E may approve the use of fuses for load-only
facilities, if the fuses coordinate with the PG&E line-side
devices for both phase and ground faults. If PG&E
approves the fuses, the PS customer should consider
installing a negative-sequence relay and/or other devices to
protect its facility against single-phase conditions.
Fuses are single-phase, direct-acting, sacrificial links that
melt to interrupt fault current and protect the equipment.
The PS customer must replace the blown fuses manually
after each fault before the facility can return to service.
Only trained, qualified personnel can replace the overhead
primary fuses.
Since fuses are single-phase devices, they may not all melt
during a fault and may not separate the PS customers
system automatically from PG&E.
Large primary fuses that do not coordinate with PG&Es
source-side protective phase and ground relays are not
allowed. These fuses may cause all the customers on the
May 1, 2003
6-7
Load
Technical Requirements for Load Entities
Standby/Backup Source
6.5.1.
Standby Source
When the PS customers load requires a high level of reliability,
the PS customer may request to have either a transmission source
installed or a backup distribution and transmission source installed
at the PS customers expense.
When the PS customers load is transferred from the primary
source to the standby source or vice versa, a momentary outage
(drop-and-pickup operation) occurs.
When the PS customers equipment is being fed from the backup
source and the PS customer wants to transfer the load back to the
primary source with a parallel operation (make-before-break
method), the PS customer must ensure that the following
requirements are met:
6-8
May 1, 2003
Load
Technical Requirements for Load Entities
Table 6-3
Manufacturer
ABB
(ASEA)
(Westinghouse)
Nondirectional Overcurrent
Relay
50/51
Nondirectional Overcurrent
Relay Ground
51N
CO
DPU-2000R
Microshield
(MSOC)
RXIDF
CO
DPU-2000R
ALSTOM
MCGG
MCGG
Basler Electric
BE1-51
BE1-51
Beckwith Electric
M-0420
M-3410
M-3420
M-3430
M-3520
M-0420
M-3410
M-3425
M-3520
IFC
IFC
SR-489
SR-745
L-90, T-60
SR-735
SR-737
SR-489
SR-745
L-90, T-60
SR-735
SR-737
SEL-251
SEL-311C
SEL-321
SEL-351
SEL-501
SEL-387
SEL-387E
SEL-587
SEL-251
SEL-321
SEL-351
SEL-501
RXIDF
Brush Electric
General Electric
Schweitzer
Woodward
1
2
All the relays specified in this table imply three single-phase relays.
All microprocessor-based relays that are used as a multifunctional protective device must have backup
relays.
May 1, 2003
6-9
Load
Technical Requirements for Load Entities
6.6.
Metering Requirements
This section addresses direct access (DA) and bundled-service PS
customers, who are connected at distribution voltages (34.5 kV and
below), as described in Rule 2, Section 13, Service Delivery Voltages.
(See Attachment 10.)
Customers connected at the available service voltages must satisfy
PG&Es revenue-metering requirements and those of other applicable
governing authorities (i.e., California Public Utilities Commission
[CPUC], California Independent System Operator [CAISO], etc.).
For customers exporting power, loads connected at distribution voltages
must satisfy the metering protocols established by PG&E and CAISO.
Exceptions will be handled on a case-by-case basis with approval from
PG&Es Customer Metering Services in close coordination with Field
Metering Services.
Other arrangements that affect the required metering installation may also
require a Generation Special Facilities Agreement. (See Attachment
12.)
6.7.
Wholesale
6.7.1.
Wholesale Service
For wholesale-service interconnections, the PS customers must
provide, install, own, and maintain all revenue-metering-related
equipment, including all the items provided and maintained by
PG&E or a Meter Service Provider (MSP) listed under Retail
Service below.
PS customers who are interested in wholesale service must meet
the following criteria:
PG&Es requirements.
6-10
May 1, 2003
Load
Technical Requirements for Load Entities
6.7.2.1.
Bundled Services
For bundled (full-service) utility services, PG&E, in most
cases, continues to provide the following services:
May 1, 2003
Load
Technical Requirements for Load Entities
6.7.2.3.
6.7.2.4.
6.7.2.5.
Customer Responsibilities
The customer (end-user) maintains the following:
6.7.2.5.1.
6-12
May 1, 2003
Load
Technical Requirements for Load Entities
An overhead light.
6.7.2.5.3.
6.7.2.5.4.
May 1, 2003
6-13
Load
Technical Requirements for Load Entities
6.9.
Communications Circuits
PG&E may require communications circuits between PG&E and the
customers generation facilities for the following purposes:
Protection
Voice communications
Preparallel Inspection
In order for PG&E to provide the PS customer with a timely
pre-energization service, it is important to meet all the deadlines stated in
this section.
6-14
May 1, 2003
Load
Technical Requirements for Load Entities
Ensure that the equipment completes and passes all the tests outlined
in the sections below.
Ensure that all the test reports identify the equipment in their header
information and that the identification matches the single-line or
three-line diagrams.
The customer must meet all the above requirements and ensure that the
test reports are approved at least 3 working days before the requested
energization date.
6.11.1.
Proving Insulation
A 2,500 volt (V) dc megger or a 1,000 V high-pot test is preferred
for any of the insulation tests below, but a 1,000 V megger test is
acceptable.
May 1, 2003
6-15
Load
Technical Requirements for Load Entities
Table 6-4
6.11.2.
Proving Ratios
The main transformer(s) ratio(s) must be proven by one of the
following methods:
6.11.3.
Circuit Breakers
The following are the requirements for circuit breakers:
6.11.4.
6-16
May 1, 2003
Load
Technical Requirements for Load Entities
Check the CTs for the proper polarity whenever they feed
PG&E equipment.
6.11.5.
Megger the total circuit with the ground wire lifted, to prove
that only one ground exists.
Relays/Fuses
The following are the requirements for relays/fuses:
May 1, 2003
6-17
Load
Technical Requirements for Load Entities
6.12.
10 %
0.05 %
0.05 Hz
Energizing
Customers must meet the following requirements before PG&E can begin
the energizing process:
6.13.
General Notes
6-18
May 1, 2003
Load
Technical Requirements for Load Entities
May 1, 2003
6-19
Load
Technical Requirements for Load Entities
6-20
May 1, 2003
Attachments
Attachment 1
Glossary
This glossary can also be found online at
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/gloss.pdf
May 1, 2003
A1-1
Attachments
A1-2
May 1, 2003
Attachments
Attachment 2
Website Addresses
To Locate
Website Link
Section 2 Standard E-NET Interconnection
Tariff Book
http://www.pge.com/customer_services/business/tariffs/
California Public
Utilities Code
http://www.leginfo.ca.gov/cgibin/calawquery?codesection=puc
&codebody=&hits=20
Singleline diagram
http://www.pge.com/002_biz_svc/gen/enet_diagram.gif
http://www.consumerenergycenter.org/buydown/eligible_invert
ers.html
http://www.pge.com/customer_services/business/tariffs/pdf/E
R2.pdf
UL1741 Certification
http://ulstandardsinfonet.ul.com/scopes/1741.html
http://www.consumerenergycenter.org/buydown/eligible_invert
ers.html
http://www.pge.com/customer_services/business/tariffs/pdf/E
R2.pdf
Western Electricity
Coordinating Council
(WECC)
http://www.wecc.biz/main.html
Information on
Expanded E-NET
Generator
Interconnection on
PG&E website
http://www.pge.com/002_biz_svc/gen/expanded_enet.shtml
California Public
Utilities Code
http://www.leginfo.ca.gov/cgibin/calawquery?codesection=puc
&codebody=&hits=20
Tariff Book
http://www.pge.com/customer_services/business/tariffs/
Rule 21 Generating
Facility
Interconnections
http://www.pge.com/customer_services/business/tariffs/pdf/E
R21.pdf
UL1741 Certification
http://ulstandardsinfonet.ul.com/scopes/1741.html
Interconnection
Agreement for Net
Energy Metering of
Solar or Wind Electric
Generating Facilities
Residential or Small
Commercial Facilities
of 10kW or Less
http://www.pge.com/002_biz_svc/pdf/enet_interconnection_a
greement.pdf
Rule 2Description of
Service
http://www.pge.com/tariffs/doc/ER2.doc
Appendix J
Generation Operating
Agreement
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/app_j.
pdf
May 1, 2003
A2-1
Attachments
To Locate
Website Link
http://www.pge.com/002_biz_svc/gen/retail_gen_rule_21.shtm
l
Western Electricity
Coordinating Council
(WECC)
http://www.wecc.biz/main.html
American National
Standards Institute
(ANSI)
www.ansi.org
Institute of Electrical
and Electronic
Engineers (IEEE)
www.standards.ieee.org
California Public
Utilities Code
http://www.leginfo.ca.gov/cgibin/calawquery?codesection=puc
&codebody=&hits=20
Tariff Book
http://www.pge.com/customer_services/business/tariffs/
UL1741 Certification
http://ulstandardsinfonet.ul.com/scopes/1741.html
Interconnection
Agreement for Net
Energy Metering of
Solar or Wind Electric
Generating Facilities
Residential or Small
Commercial Facilities
of 10kW or Less
http://www.pge.com/002_biz_svc/pdf/enet_interconnection_a
greement.pdf
Rule 2Description of
Service
http://www.pge.com/tariffs/doc/ER2.doc
Appendix E
Substation Grounding
Requirements
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/app_e
.pdf
Appendix L
Generation Special
Facilities Agreement
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/app_l.
pdf
Appendix Q
Generator Automatic
Sychronizers
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/app_q
.pdf
Appendix R
Generator Protective
Relay Requirements
http://www.pge.com/002_biz_svc/gen/pdf/wi_handbook/app_r.
pdf
A2-2
May 1, 2003
Attachments
Attachment 3
Drawings
Figure A3-1
Figure A3-2
Figure A3-3
Figure A3-4
Figure A3-5
Figure A3-6
Document 058779
Document 060559
Document 066195
May 1, 2003
A3-1
Attachments
A3-2
May 1, 2003
Distribution
Attachments
Customers
Termination Facility
Point of Service
Protection and Metering
Customer provides protective device
PG&E approves settings
Underground
Street
Customers Conduit
and Conductor
Figure A3-1
Underground Primary Service from Underground Distribution
Preferred Service Arrangement
Customers Termination Facility 3 500 Feet From PG&E Splice Box
May 1, 2003
A3-3
Distribution
Attachments
Underground
Street
Customers
Termination Facility
Metering
Point of Service
S Customer provides protective device
S PG&E approves settings
Conduit owned and maintained by customer
Conductor and Splices by PG&E
Notes:
1. PG&E will install a protective device under a special
facilities agreement if there are extenuating
circumstances that prevent the customer from installing
one. This is an exception and will be handled on a
case-by-case basis
2. If PG&Es primary facilities are across the street, PG&E
will own and maintain substructures in the franchise area
and the customer will own and maintain substructures
on private property. PG&E will provide cable to the point
of service
Figure A3-2
Underground Primary Service from Underground Distribution
Nonpreferred Service Arrangement
Customers Termination Facility > 500 Feet From PG&E Splice Box
A3-4
May 1, 2003
Attachments
PG&E Distribution
Pole and Riser
Notes:
1. PG&E will install a protective device under a special facilities agreement if there
are extenuating circumstances that prevent the customer from installing one.
This is an exception and will be handled on a case-by-case basis
2. If PG&Es primary facilities are across the street, PG&E will own and maintain
substructures in the franchise area and the customer will own and maintain
substructures on private property. PG&E will still provide one continuous pull of
cable to customers termination facility, not to exceed 500 feet.
Figure A3-3
Underground Primary Service from Overhead Distribution
Preferred Service Arrangement
Customers Termination Facility 3 500 Feet From PG&E Pole
May 1, 2003
A3-5
Attachments
PG&E Distribution
Pole and Riser
Street
Point of Service
Primary splice box installed, owned, and
maintained by customer at a mutually
agreed location at the property line
Customer provides protective device
PG&E approves settings
Notes:
1. PG&E will install a protective device under a special facilities agreement if there
are extenuating circumstances that prevent the customer from installing one.
This is an exception and will be handled on a case-by-case basis
2. If PG&Es primary facilities are across the street, PG&E will own and maintain
substructures in the franchise area and the customer will own and maintain
substructures on private property. PG&E will provide cable to the point of
service.
Figure A3-4
Underground Primary Service from Overhead Distribution
Nonpreferred Service Arrangement
Customers Termination Facility > 500 Feet From PG&E Pole
A3-6
May 1, 2003
Attachments
Customers Conductor
Street
Customers
Riser
Meter
Enclosure
May 1, 2003
A3-7
Attachments
A3-8
Main Service
Entrance Panel
24 x Siemans SR-100
solar Equipment
24 x 100 watt
Panel Modules:
4 in series=50 blts
x 6 modules
UL-1741
Inverter Units
20ampere
2-pole breaker
Lockable Disconnect
Figure A3-6
Advanced Electric Systems GC-1000 (grid intertie inverter)
No batteries, no transfer or bypass switching
PG&E Meter
L1
3 - 10 ga. conductors
1 - 12 ga. ground
May 1, 2003
2-pole, 30ampere
Square D DU 221 RB
Ground Rod
12 - 8 ga. conductors
(2 per module)
1 - 8 ga. ground
Attachments
Attachment 4
Equipment
List of Eligible Inverters
May 1, 2003
A4-1
Attachments
A4-2
May 1, 2003
Attachments
Attachment 5
Rule 21 Process
Rule 21
Rule 21
May 1, 2003
A5-1
Attachments
A5-2
May 1, 2003
Attachments
Attachment 6
Telemetering and Transfer Trip
Telemetering and Transfer Trip
May 1, 2003
A6-1
Attachments
A6-2
May 1, 2003
Attachments
Attachment 7
Substation Grounding Requirements
Substation Grounding Requirements
May 1, 2003
A7-1
Attachments
A7-2
May 1, 2003
Attachments
Attachment 8
Generator Automatic Synchronizers
Generator Automatic Synchronizers for Generation Entities
May 1, 2003
A8-1
Attachments
A8-2
May 1, 2003
Attachments
Attachment 9
Generator Protective Relay Requirements
Generator Protective Relay Requirements for Generation Entities
May 1, 2003
A9-1
Attachments
A9-2
May 1, 2003
Attachments
Attachment 10
Rule 2
Rule 2, Description of Service
May 1, 2003
A10-1
Attachments
A10-2
May 1, 2003
Attachments
Attachment 11
Rule 21
Rule 21, Generating Facility Interconnections
May 1, 2003
A11-1
Attachments
A11-2
May 1, 2003
Attachments
Attachment 12
Forms and Agreements
Authorization To: Receive Customer Information or Act on a Customers Behalf
Generator Interconnection Agreement
Generation Operating Agreement
Generation Special Facilities Agreement
E-9 Checklist
Form 62-4527
Form 79-280
Form 79-285
Form 79-756
Form 79-843
Form 79-854
Form 79-973
Form 79-974
Form 79-978
Form 79-988
Form 79-992
May 1, 2003
A12-1
Attachments
Form 79-994
Form G2-2
Form G5-1
A12-2
May 1, 2003