Project Case Study
Project Case Study
Boxes Manufacture
Project Case Study
Table of Contents
1)
2)
Introduction ............................................................................................................................. 4
A)
ii)
iii)
iv)
v)
Boxes production:............................................................................................................ 4
vi)
B)
3)
ii)
B)
4)
i)
Quality ............................................................................................................................. 5
ii)
Resources ........................................................................................................................ 5
iii)
Scope ............................................................................................................................... 5
iv)
Time ................................................................................................................................. 5
Decomposition .................................................................................................................... 6
B)
WBS ..................................................................................................................................... 6
5)
B)
C)
6)
i)
ii)
iii)
B)
C)
D)
7)
i)
ii)
iii)
ii)
B)
8)
ii)
B)
C)
D)
E)
9)
Project Stakeholders.......................................................................................................... 18
B)
Communications groups.................................................................................................... 18
C)
10)
A)
B)
C)
11)
12)
References ......................................................................................................................... 20
Page 2 of 20
1) Table of figures
Figure 1(Scope Decomposing) ........................................................................................................ 6
Figure 2(Project WBS) .................................................................................................................... 7
Figure 3(Activity List)..................................................................................................................... 7
Figure 4(Activity Duration) ............................................................................................................. 8
Figure 5(Activity Sequence)............................................................................................................ 9
Figure 6(Bar Chart) ......................................................................................................................... 9
Figure 7(Revised Bar Chart) ......................................................................................................... 10
Figure 8(Type of Resources) ......................................................................................................... 11
Figure 9(Resources Quantities) ..................................................................................................... 11
Figure 10(Organization Chart) ...................................................................................................... 12
Figure 11(Primavera Resource Histogram) ................................................................................... 12
Figure 12(Excel Resource Histogram) .......................................................................................... 13
Figure 13(Excel Revised Resource Histogram) ............................................................................ 13
Figure 14(Project Budget) ............................................................................................................. 14
Figure 15(Revised Project Budget) ............................................................................................... 14
Figure 16(Project Cash Flow) ....................................................................................................... 15
Figure 17(Project Revised Cash Flow).......................................................................................... 15
Figure 18(Qualitative Risk Analysis) ............................................................................................ 16
Figure 19(Quantitative Risk Analysis) .......................................................................................... 17
Figure 20(Communications Information)...................................................................................... 18
Page 3 of 20
2) Introduction
A) Project background
Our company Flexible Models (FM) awarded a project for the Research and
Development unit of the Property Development Department of the Government
(PDDG). The project is part of Seismic Zone Residential Construction
Improvement Program, and it is to manufacture and deliver boxes, which used on
a foundation of buildings. In order to deliver the final product, the project will pass
through the following stages:
i) Requirements Analysis:
Interview the project stakeholders and Product detail analysis to define the
project scope of work.
ii) Design and concept:
Perform the project design and execution method statement in order to plan the
project.
iii) Plan the project:
Develop the project plan; scope statement, WBS, schedule, resources, cost,
risks, communication, and quality plans as per the following sections.
iv) Materials procurements:
As per the project management plan, and the design, the materials procurement
should start to provide the materials required to manufacture the boxes.
v) Boxes production:
As per the materials delivery schedule and the project plan, the manufacture
should start to deliver the boxes on time.
vi) Boxes assembly:
As per the production schedule, and the project management plan, the boxes
should be delivered and assembled at the client's site as required.
Page 4 of 20
3)
Note: the given effort of resources is total number of resources to complete the
task not the daily manpower,
The following is the Labor rates:
iii) Scope
The boxes should be delivered and assembled at the client's site
iv) Time
The project completion date was revised because of the risk management.
See section 8-D.
The calendar used on oracle Primavera scheduling tool is standard 5-day
work per week except for task number A1150 Shipment/Delivery the
calendar used is 7-day work per week.
Page 5 of 20
4)
B) WBS
After decomposing the project into work packages, the WBS is created by Oracle
Primavera as per the following figure-2.
Page 6 of 20
5)
Project schedule
A) Define project activities
After the creation of the WBS on Oracle Primavera, the activities were populated
under the related WBS as per the following figure-3
Page 7 of 20
C) Schedule activities
i) Sequence activities
The activities is sequenced in Oracle Primavera by assigning the predecessor and
successor relationships as per figure-5 below.
Note: activity number A1040 Details with operation designs has a start-to-start
+ 2 days lag relationship with activity number A1030 High level design as per
statement The task 'Details with operation designs' starts with a 50% overlap with
'High level design'
Page 8 of 20
Page 9 of 20
6)
Resource
Type
4 days
Design
6 days
Design &
Assembly
2 days
Design
2
Design and Concept
2.1 High level design
4 days
Design
6 days
Design
3
Production
3.1 Set up
4 days
Assembly
Requirements Analysis
Page 10 of 20
Task
Duration
Resource
Type
3 days
Cutting
3.3 Sub-assembly 1
6 days
Assembly
3.4 Sub-assembly 2
6 days
Assembly
3.5 Sub-assembly 3
4 days
Assembly
3 days
Assembly
4
Material
4.1 Cardboard sheet
sheets
sheets
4.1 Cubes
pieces
5
Delivery
5.1 Pre-delivery
2 days
7 days
Design &
Assembly
Page 11 of 20
Page 12 of 20
Page 13 of 20
7)
Cost estimates
A) Determining Project Budget
i) Original project budget
The author estimated the cost of each activity, and accordingly the project budget
using Microsoft Excel. The project budget is 36,960 $ as per figure-14
Page 14 of 20
Page 15 of 20
8)
Risk Id R1: The Cutting and parts development task id A1060 required a
very skilled resource to meet the quality requirements.
Risk ID R2: Project materials could be damaged during shipment.
Risk ID R3: change in client requirements after the cutting stage.
Risk R1 has a 0.7 probability and will delays the project by 6 days for every
day of delay in this task, which consider high impact assumed by 0.6.
Risk R2 has a 0.3 probability and 0.3 impact on the task cost.
Risk R3 has assumed probability of 0.5 and has impact on tasks (Set up,
and Cutting and parts development) by 1
Page 16 of 20
From the quantitative risk analysis, the project budget increased by 855$, and the
task duration for tasks (Set up, and Cutting and parts development) increased by
2, and 3 days respectively. These changes reflected on the project management
plan.
9)
Communications plan
A) Project Stakeholders
In addition to the project team identified on the organization chart in section 6-C,
other external stakeholders is identified. Joseph Bukhmann, the chief editor of
Construction Consortium Journal.
B) Communications groups
The project consist of three main groups:
FM Company group
Client Group
External stakeholders group.
Stakeholder Name
Roy Benjamin
Michael Gartner
Philip Cloony
Stakeholder
Group
Type of information
Sequence of
Communicat
ion
Information
Delivery
Method
Email
FM Company
group
FM Company
group
FM Company
group
product design
alternate day
detailed drawings
assembly drawings
Weekly
design drawings
Weekly
FM Company
group
vendor management,
market analysis,
contracting, and
procuring required
resources
Weekly
FM Company
group
information on the
progress
project management
processes
Daily
FM Company
group
budget
Weekly
External
stakeholders
group
Monthly
Client Group
progress of the
technical design
Progress presentation
Weekly
report
biweekly call
Email
Phone Call
Jim Stanford
5
John Morris
6
Caroline Smith
7
Joseph Bukhmann
8
Paul Lee
Page 18 of 20
Web-based
project tracking
system
Reports, and
Memo's
one-on-one
meetings, and
telephone calls
B) Quality Assurance
During the manufacture process, and before proceeding with the second stage of
the manufacture, the first stage should be checked via inspection request and
verified by the QA engineer. This procedure will reduce the probabilities of quality
defects and if any defects discovered during the manufacture will be fixed in early
stage, rather than waiting the assembly stage to find out that there is a problem in
the boxes.
C) Quality Control
During the manufacture process, the QA engineer should physically check the
quality of the product and sign inspection request for each stage of the
manufacture.
Page 19 of 20
12) References
BERMAN, J., 2007. Maximizing project value [electronic book] : defining, managing, and
measuring for optimal return / Jeff Berman. New York : Amacom, American Management
Association, c2007.
KERZNER, H., 2009. Project management [electronic book] : a systems approach to planning,
scheduling, and controlling / Harold Kerzner. Hoboken, NJ : John Wiley & Sons, 2009; 10th ed.
PROJECT MANAGEMENT INSTITUTE, 2008. A guide to the project management body of
knowledge (PMBOK guide). 4th edn. Newtown Square, Pa.: Project Management Institute.
PROJECT MANAGEMENT INSTITUTE., 2013. A guide to the project management body of
knowledge (PMBOK guide). Newtown Square, Pennsylvania: Project Management Institute, Inc.
SANGHERA, P., 2010. PMP in depth, second edition : project management professional study
guide for the PMP exam / Paul Sanghera. Australia ; Course Technology/Cengage Learning,
2010; 2nd ed.
WYSOCKI, R.K., 2012. Effective project management. 6th edn. Indianapolis, IN: Wiley.
Page 20 of 20