1.
Project Definition
Creation of Project
Transaction code: CJ20N
Open the Project Builder either by typing the T code mentioned above or through
the drill down menu as shown below
Project Builder:
The project Builder is a user-friendly method of accessing Project System, which
enables you to edit your projects quickly and efficiently.
It consists of three parts: Structure tree, work list and templates and Work Area
PS Level-2 training
Project LAKSHYA
In the work List Area we can see Last Five projects Processed.
If you want to create a project click on Create and choose Project
PS Level-2 training
Project LAKSHYA
PS Level-2 training
Project LAKSHYA
PS Level-2 training
Project LAKSHYA
We have to give the required organization elements. Once we have selected the project
profile, default organization elements will come. Required changes can be made
according to your project requirements.
Basic data Tab
We have to give the project start date, finish date, factory calendar and Time unit.
PS Level-2 training
Project LAKSHYA
PS Level-2 training
Project LAKSHYA
d) Enter Level 1, with coding mask & description of the WBS element
PS Level-2 training
Project LAKSHYA
PS Level-2 training
10
Project LAKSHYA
PS Level-2 training
11
Project LAKSHYA
Repeat the same for all Level 2 & 3 WBS elements so as to create a project structure.
PS Level-2 training
12
Project LAKSHYA
Repeat the same for other WBS elements so as to create one activity each under each
WBS element
PS Level-2 training
13
Project LAKSHYA
PS Level-2 training
14
Project LAKSHYA
15
Project LAKSHYA
Select the WBS element in structure tree and double click on Costs in
work list area. Here we can mention general costs.
PS Level-2 training
16
Project LAKSHYA
7. Material Assignment
Select the activity and Double click on Material. Mention the material and its type also
give required quantity and date.
PS Level-2 training
17
Project LAKSHYA
8. PS Texts
If we want to attach PS texts and Documents, select the WBS Element and double
click on PS texts.
PS Text for the description and its type and
Documents for the attaching the required documents for the WBS Element.
PS Level-2 training
18
Project LAKSHYA
9. Estimation
T Code: KKE1 (Create base planning object)
Open the transaction either by typing the T code mentioned above or through the drill
down menu as shown below
PS Level-2 training
19
Project LAKSHYA
Estimation is done using unit costing method. Base Planning object shall be created for
defining material, equipment & labour norms. These BPO will then be assigned to WBS
elements to get the total cost of the project.
Use T code KKE1 for creating a base planning object
PS Level-2 training
20
Project LAKSHYA
For defining material norms, select Item category M, select material code from material
master & enter the norms & rate will be picked from the master which is editable.
PS Level-2 training
21
Project LAKSHYA
For service item, select Item category N & then select the appropriate service. Enter the
norms & rate for the service selected.
Repeat the steps for all services. The system calculates the unit cost of the item at the
bottom
Assign this BPO to the WBS element in CJ40.
Open the transaction either by typing the T code mentioned above or through the drill
down menu as shown below
PS Level-2 training
22
Project LAKSHYA
PS Level-2 training
23
Project LAKSHYA
Detailed Planning
Change / Display
Select B as Item category & select the BPO created & enter the quantity
PS Level-2 training
24
Project LAKSHYA
Save the record. This will give the total cost of WBS element. Repeat the steps for all
WBS elements & select Edit
Total Up which will sum up the costs of all WBS
elements.
PS Level-2 training
25
Project LAKSHYA
PS Level-2 training
26
Project LAKSHYA
Enter the superceding activity number, relationship & interval (in days) after which this
activity should start
Repeat the steps for all activity. Schedule the project which will give the bar chart for the
project
PS Level-2 training
27
Project LAKSHYA
PS Level-2 training
28
Project LAKSHYA
ii)
Network Costing
We have to use Cj40 for Manual cost planning with cost element
Enter the project for which cost planning needs to be done & enter the version as 1
Select the WBS element for which cost planning is to be done & click on the primary
costs
PS Level-2 training
29
Project LAKSHYA
PS Level-2 training
30
Project LAKSHYA
This will sum up costs of all the WBS elements & give the total cost of the project
PS Level-2 training
31
Project LAKSHYA
PS Level-2 training
32
Project LAKSHYA
Select the WBS element for which revenue is to be planned & click on the detailed
planning button
PS Level-2 training
33
Project LAKSHYA
Enter the revenue for the WBS element & the quantity
PS Level-2 training
34
Project LAKSHYA
This will sum up the revenues of all the WBS elements for the project
PS Level-2 training
35
Project LAKSHYA
PS Level-2 training
36
Project LAKSHYA
Original Budget
Convert cost plan to budget
Release of budget
Supplement or Return of budget
Once the cost planning is done the same is transferred as an original budget through
IMCCP3. User has to enter the cost planning version, project code & controlling area for
copying
PS Level-2 training
37
Project LAKSHYA
Executing this T code will copy the budget from cost plan version selected as shown
PS Level-2 training
38
Project LAKSHYA
Copy View
PS Level-2 training
39
Project LAKSHYA
PS Level-2 training
40
Project LAKSHYA
PS Level-2 training
Status
Release as shown
41
Project LAKSHYA
Save the project & the project will get released for execution
16. Confirmation
T Code: CJ20N
We have to confirm the internal activities for obtaining actual values. Confirmation
means mentioning the actual work done. In the Project Builder we have
to select the activity and go to Edit in the menu bar choose activity- confirmation and
mention the number of units of actual work done.
PS Level-2 training
42
Project LAKSHYA
Activity
Confirm. This
Enter Actual start & End date with the quantity executed for that period under
consideration
17. Closing.