BUILDING ECONOMICS
Introduction
The costs of buildings are influenced by a variety of factors, some
of which are interrelated, such as:
building shape and size,
storey heights and total height,
size, shape and constructional system;
the amount and type of materials used (the building's
specification) and how much they cost;
the costs of human resources involved in design and
construction; the cost of plant, machinery and tools;
the
efficiency
and
integration
of the
design,
procurement and construction;
the effectiveness of the design in allowing efficient, low-cost
use of the building when completed.
LECTURE 4
Site considerations
Each construction site has its own characteristics which have an
important influence on its suitability for development.
The size of the site required will generally be determined by
the type of project to be constructed.
The cost of the project will be affected by its location. A
congested city site have problems of access, materials
deliveries, close proximity of adjacent structures etc. It may be
located in the outskirts with its own problems of material and
labour availability and particularly transport costs.
JK Ho
Building Size
This is an important factor in terms of cost efficiency, because
costs are not in proportion to changes in size.
Larger buildings have lower unit costs than smaller sized
buildings with an equivalent quality of specifications.
For example, a dwelling house on its own individual plot of
land will cost more to construct than a similar house from a
large housing estate contract.
Smaller factories cost more per unit than their larger
counterparts. To some extent this is due to the economic
theory of economies of scale.
Planning efficiency
Plan Shape
The plan shape of any structure has an important effect on the
overall cost of the project. This effect is not restricted to the
external envelope costs, but also applies to the internal
division elements.
A square-plan-shaped structure will in the majority of cases
provide the most economic solution. This is largely due to the
wall-to-floor ratio. A square shape provides the lowest amount
of wall area to gross floor area.
The more complex the shape, the higher will be the overall
cost of the structure based on an agreed required floor area.
JK Ho
Height
The constructional costs of tall structures are greater than those of
low-rise buildings offering a similar amount of accommodation.
Tall structures are thus preferred only where the land is either
expensive or in scarce supply.
provision of vertical transportation such as hoists and cranes,
the problems with material storage, the delays in waiting for
the construction to 'set', the increased amounts payable to
operatives and safety requirements.
increasing costs of engineering services and their provision
within the building, such as lifts, refuse disposal installations,
pumping equipment for sewage disposal and protective
installations such as firefighting equipment and lightning
conductors.
10
11
12
13
14
Groupings of buildings
Savings in cost can usually be achieved by inter-linking
buildings or structures because of a saving in foundation and
external walling costs or other common items of construction.
15
16
17
JK Ho
Storey Height
The storey heights of buildings are largely determined by the
needs of the user of building.
A greater storey height than normal may be necessary to
accommodate larger machinery or equipment, or it may be
necessary to provide space within false ceilings for service
ducts for cables, pipes or air conditioning ducts.
Buildability
Buildability is defined as the extent to which the design of a
building facilitates ease of construction, subject to the overall
requirements for the completed building.
Buildability is largely concerned with the work on site and the
practicalities of producing a structure from a design.
Good buildability means that the design takes a very close
account of the way in which the building will be constructed,
and the conditions imposed on this process.
Constructional Details
The cost differences between alternatives may make a substantial
difference to the overall cost of the project. Other factors, such as
the length of time required for construction purposes, will also
need to be considered.
concrete may have an initial cost advantage, but the speed of
steel frame erection may show a reduced contract period with a
consequent saving in costs over the entire project.
use of prefabricated components or off-site techniques will
generally tend to shorten the contract period, but at a higher
costs.
18
Refurbishment
A further factor to consider at the inception stage of a new
project is the availability of an existing project that may be
capable of adaptation.
Generally, the refurbishment of an existing project will always
be less expensive than the construction of a new building.
Extensive refurbishment may be so necessary as to make
redevelopment a better alternative.
Sometimes, where the space available is insufficient, the
possibility of extending the premises may also be considered.
A further factor is that of continuity of use, which s not possible
if demolition and rebuilding are required and some form of
temporary accommodation will be required.
Design Economics
19
20
22
21
Clients Requirement
PERFORMANCE
Appearance
Quality
Function
Durability
Maintenance
CLIENTS
REQUIREMENTS
23
JK Ho
TIME
Design length
Start date
Hand-over
Completion
COST
Budget
Estimate
Tender
Final account
Costs-in-use
24
Design Factors
Design factors that influence the cost of the building are generally:
Shape
Size
Circulation space/Planning Efficiency
Storey height
Total height of building
Shape
The shape of a building influences the cost.
generally, the simpler the building shape the lower will be the
cost.
the perimeter/floor area ratio will increase, and a corresponding
higher unit cost with:
long and narrow building
complicated and irregular outline
25
26
10 m
10 m
2m
50 m
Area = 100 m2
Perimeter = 104m
Ratio = 1.04
Area = 100 m2
Perimeter = 40m
Ratio = 0.4
27
28
4m
5m
5m
2m
4m
6m
30 m
Dia = 11.3 m
30 m
Area = 100 m2
Perimeter = 86m
Ratio = 0.86
29
JK Ho
30
The geometry of the floor plan has significant impact upon the
interior space planning, exterior building envelope and
structural system.
Generally the simpler and more regular the floor shape, the
more easily it can be adapted to the users needs in terms of
space planning.
Square and rectangular floor plans work more efficiently than
curved and irregular shapes
31
32
509m
33
452m
421m
415m
391m
384m
374m
367m
346m
34
JK Ho
36
37
38
Circular buildings enclose the greatest floor area for the smallest
perimeter but are:
uneconomical to construct
major internal planning and layout problems.
39
40
Size
Increase in the size of the building will usually results in reduction
in the unit cost such as cost per square metre of the floor area.
Certain costs do not rise proportionately with increases in the
plan size of the building such as:
transportation,
temporary site buildings for material storage, offices and
workers accommodation,
temporary water and electricity supply,
temporary roads and drainage,
site personnel etc.
41
JK Ho
42
15.0
8.0
8.0
B
30.0
Area A
Perimeter A
P/Flr
= 120m2
= 46m
= 383mm
Area B
Perimeter B
P/Flr
= 240m2
= 76m
= 317mm
43
44
45
46
5.0
24.0
5.0
12.0
5.0
5.0
5.0
24.0
48.0
GFA
less circulation
Usable Area
= 576m2
= 96m2
= 480m2
47
JK Ho
GFA
less circulation
Usable Area
= 576m2
= 116m2
= 480m2
48
Storey Heights
Increases or decreases in storey heights cause variation in the cost
of the building without changing the floor area. The main
constructional items affected by a variation in storey height are
walls and partitions, and the associated finishing and decorations
including:
Increased volume to be heated/cooled necessitating larger
capacity of HVAC units and loner lengths of pipes, cables and
ducting;
Longer service, waste and soil pipes to supply sanitary/service
appliances;
Increased cost of constructing staircases and lifts;
Possible increased cost of roof construction due to hoisting;
Possible additional cost in installing finishing and decorations
to ceilings;
49
50
51
52
Wall/Floor Ratio
Calculating the wall area against the floor area takes storey
height into account as a cost factor.
Confirms that the wall perimeter length is an important cost
factor .
Window/Wall Ratio
The cost per square metre of windows is generally much more
expensive than a square metre of wall.
53
JK Ho
54
10.0
5.0
6.0
10.0
5.0
5.0
10.0
Partition/Floor Ratio
Useful when comparing buildings such as office blocks, eg.:
large open plan office space, and
cell like offices with plenty of corridors typical in academic
buildings.
6.0
20.0
55
56
5.0
= 40m x 3m
= 10m x 10m
= 120m2 / 100m2 = 1.2
Plan B:
wall area
floor area
= 50m x 3m
= 20m x 5m
= 150m2 / 100m2 = 1.5
wall area
floor area
= 52m x 3m
= 16m x 4m + 6m x 6m
= 156m2 / 100m2 = 1.56
Plan C:
10.0
A
5.0
20.0
57
58
Plan A:
Plan B:
partition area
floor area
= 20m x 3m = 60m2
= 10m x 10m
= 60m2 / 100m2 = 0.6
partition area
floor area
= 15m x 3m = 45m2
= 20m x 5m
= 45m2 / 100m2 = 0.45
59
JK Ho
5.0
wall area
floor area
5.0
Plan A:
10.0
60
10
Other design factors that can have an effect on overall cost include
the following:
Mechanisation
speed up production, especially through the use of
prefabricated building components which eliminate much
of the cutting on site.
Prefabrication
allows maximum efficiency and economy as a result of
mass production.
Standardisation
allows manufacturers to use the same machinery
configuration for longer periods and therefore obtain
economies of scale in production
also allows the use of interchangeable parts resulting in
more competitive pricing.
Buildability
an approach where design takes account of the
construction process.
61
62
Tutorial 4
1. List five (5) design factors that will influence the cost of the
building.
2. Briefly describe with illustrations, how the shape of a building
influences the cost of the building.
END
63
64
7. What are the factors that affect the cost of high rise buildings
compared to low rise?
8. Explain the following ratios used to compare cost of
buildings:
a) Wall/Floor
b) Window/Wall
c) Partition/Floor
15m
17m
30m
40m
40m
60m
15m
7m
25m
2m width circulation
65
JK Ho
66