Abstract:: A Case Study - Installation of Cut-Off Wall in Seyrantepe Dam Project
Abstract:: A Case Study - Installation of Cut-Off Wall in Seyrantepe Dam Project
H.Turan Durgunoglu1, Selim Ikiz2, Sabahattin Eser3, Onder Akcakal4, Melis Sutman5
1
Prof. Dr. P.E., Chairman, Zeta Zemin Teknolojisi A.S., 34794 Istanbul Turkey;
[email protected]
2
CE, Msc., General Manager, Zeta Zemin Teknolojisi A.S., 34794 Istanbul Turkey;
[email protected]
3
GE, Bsc., Site Manager, Zeta Zemin Teknolojisi A.S., 34794 Istanbul Turkey;
[email protected]
4
CE, Msc., Project Engineer, Zeta Zemin Teknolojisi A.S., 34794 Istanbul Turkey;
[email protected]
5
CE, Bsc., Asst. Project Engineer, Zeta Zemin Teknolojisi A.S., 34794 Istanbul Turkey;
[email protected]
ABSTRACT: Due to high energy demand, recently dams are one of the most
encouraged projects by the state in Turkey. Dam locations are determined in order to
obtain maximum energy output and minimum cost to attract the private investors. On
streams alluvial and permeable areas possess special problems for controlling
groundwater seepage under the dam. For this purpose cut-off walls are well known
relatively impermeable groundwater barriers that have been used for decades in
various sizes and types. This paper examines a cut-off wall case study beneath
Seyrantepe Dam Project in Elazig, Turkey. Seyrantepe Dam is planned to be
constructed on alluvial deposits of Peri Stream which discharges into Munzur River.
Maximum 30 meters deep alluvial and slope debris layers exist under the Seyrantepe
Dam site. A slope failure has occured during the initial stage of the construction that
added great difficulty and complexity in construction of seepage barrier. To avoid the
groundwater seepage in the alluvial and slope debris layers, a cut-off wall with 800
mm thickness was planned to be constructed penetrating two meters into relatively
impermeable marl base rock. Mechanical grab and hydrofreze cutter diaphragm wall
machine was used to construct the cut-off wall considering very unfavorable subsoil
conditions given by slope debris containing irregular large size basalt boulders. In
addition systematic grouting of limestone formations was planned in order to control
permeability within of the dam settlement area. The plastic concrete which used in
the cut-off wall was determined based on the hydraulic conductivity tested in the
laboratory. Special permeability tests are also implemented after construction in
order to verify the impermeability of the cut-off. Construction method and
encountered difficulties with special emphasis are discussed in the scope of this case
study.
INTRODUCTION
The number of dam projects which serving for multiple purposes is now increasing
rapidly in Turkey. Dam locations are determined in order to obtain maximum energy
output and minimum cost to attract the private investors and engineers are compelled
Creep Zone
FIG. 3. Failure Mechanism on the Dam Shoulder, Vardar and Sans (2006)
CUT-OFF WALL
Because of the existence of pervious soil layers alluvial and limestone directly
under the dam site and failed pervious slope debris containing large boulders at the
left side of dam long cut-off wall is planned to be constructed both beneath the
alluvial, limestone and slope debris to eliminate the excessive groundwater seepage.
Cut-off curtain wall depth is determined based on 2.0 m minimum socketing into the
relatively impermeable underlying bedrock marl formation.
It is well determined that the limestone formation beneath the dam is
heterogeneous. Water pressure Lugeon values determined during soil
investigations often yield excess Lugeon values. Therefore systematic cement
grouting was planned to be implemented based on observed Lugeon values within
the limestone. Further, systematic cement grouting is also planned to be implemented
prior to cut-off wall construction up to 90.0 m under dam foundation including the
west side. Dam and cut-off wall section is illustrated in Figure 4.
CUT-OFF WALL
(Lmax=31m)
Slope Debris
Bottom Limit
SK-243
SK-242
SK-9
SK-239
SK-240
43
43
SK-2
SK-256
SK-238
SK-231
SK-10
SK-7
32
SK-4
~4
DB-9
CURTAIN INJECTION
BOTTOM LIMIT
Min 2m Socket To
Bedrock
Cut-off wall panels are contsructed as primary and secondary units as illustrated
in the Figure 7. Panels are constructed with providing minimum 200mm - 400 mm
overcutting between them.
hydro-freze cutter machine could be rescued after seven days of struggle without a
major breakdown (Figure 10).
As faced in this case study, the excavation of cut-offs in loose slope debris
containing large boulders under ground water is one of the most difficult and
unpredictable task to be performed in foundation construction.
DESIGN OF PLASTIC CONCRETE
In the scope of the design of plastic concrete, hydraulic conductivity tests are
conducted in the laboratory on the core samples taken from the plastic concrete
from initial cut-off wall as reported by Altun and Mihcakan (2007). Permeability
tests are conducted on the samples under various pressures. Pressure is increased
from 1 bar to 5 bar and it is noted that permeability decreased respectively with
the increasing pressure. Permeability values 10-4 and 10-6 cm/sec are obtained for
the design mixture of plastic concrete and found to be acceptable. Test results are
given in the Figure 11.
CONCLUSIONS
A cut-off wall using mechanical grab and cutter is constructed in order to
prevent seepage under the dam described in this case study. Since bedrock stratum
where the cut-off wall is socketed is heterogeneous, systematic cement grouting is
also implemented based on observed Lugeon values in excess of unity within the
bedrock. Cut-off wall is constructed within slope debris with the mechanical grab
and hydro-freze cutter where very large basalt and agglomerate boulders were
presented. Boulder sizes encountered during construction were larger than the
ones anticipated in the design stage. It is demostrated that loose slope debris
containing large size boulders under groundwater as in this case study is one of
the most difficult and detrimental condition to be faced in cut-off wall
construction using cutters. High groundwater conditions and very high strength of
boulders having basaltic and agglomarete lithology within the failed slope added
greatly to the complexity of the problems. During the operation, one of the
segment of trench collapsed while hydro-freze cutter machine was at a depth of
18.5 m from the working platform due to presence of large size boulders and loose
slope debris. Hydro-freze cutter machine have been rescued in seven days of
struggle without a major breakdown by implementing special rescue operation
employing construction of a special dewatered rectangular caisson shaft. The
construction of the cut-off wall has been completed with success, finally and
giving the possibility to learn great deal and never to forget to ask the critical
question of what could go wrong in such chalenging foundation engineering
problems.
AKNOWLEDGEMENTS
We would like to thank to Seyrantepe Dam Consortium - DARENHES Elektrik
Uretim A.S. for their cooperation throughout the construction. We would also like
to thank Dr. Vardar, Professor of Istanbul Technical University for his valuable
suggestions during the construction of cutoff wall within the slope debris.
REFERENCES
Tanaka H., Yahagi F., (1956). Some Considerations on the Cut-off Wall Length
in the Pervious Rock Foundation. 'Le Bulletin d'Information de l'Association
Internationale d'Hydrologie Scientifique', Hydrological Sciences Journal.
Vardar M., Sans G., (2006), (In Turkish) A Case Study for Seyrantepe Dam Left
Side Landslides Formation, Reasons, Effects and Remedition Studies for
Unstabilities, ROCKMEC-2006 VIII. Regional Rock Mechanics Symposium,
Istanbul, Turkey
Altun G., Mihcakan I.M., (2007), (In Turkish) Seyrantepe Baraj ve HES naat
ZETA Plastik Beton Karmlar Geirgenlik Deneyleri n Deney
almalar, Dahili Rapor