DBM Final Report
DBM Final Report
PROVIDING AND LAYING WET MIX MACADAM OF 75MM AND 100MM, DENSE
BITUMINOUS MACADAM 75MM AND ASPHALTIC CONCRETE 40MM
INCLUDING PRIME/TACK COAT, TRANSPORTATION AND ROLLING
COMPACTION TO WORK SITE AS PER MORT&H SPECIFICATIONS (4TH
EDITION) BETWEEN KM 151 TO 161.5 KM ON PHUETSHOLING THIMPU ROAD
UNDER 19 BRTF PROJECT DANTAK INSIDE BHUTAN
1. INTRODUCTION
In response to the request of M/s SUNSHINE OVERSEAS PVT. LIMITED vide letter
80293/60/E8 dated 16-August-2007, for carrying out Testing of Materials and Design of Job
Mix of Dense Bituminous Macadam for the work, Providing and laying Wet Mix Macadam
of 75mm and 100mm, Dense Bituminous Macadam 75mm and Asphaltic Concrete 40mm
including prime/tack coat, transportation and rolling compaction to work site as per
MORT&H specifications (4th Edition) between Km 151.0 To 161.5 Km on Phuetsholing
Thimpu road Under 19 BRTF project Dantak inside Bhutan, the job mix and design of the
mix have been undertaken by the Transportation Section of the Civil Engineering Department
of IIT Guwahati. Samples of the following materials were supplied by the client to the
laboratory of the section for carrying out the work.
Materials:
a) Crushed Stone Chips 26.5mm size
b) Crushed Stone Chips 13.2mm size
c) Crushed Stone Chips 6.0mm size
d) River Sand
e) Bitumen 80-100
f) Cement (OPC)
Sample no 1
Sample no 2
Sample no 3
Sample no 4
Sample no 5
Sample no 6
The following sections present a brief description of the work carried out.
2. JOB MIX
To determine the job mix, the aggregate analysis will be somewhat governed by the number
of aggregate stockpiles
2.1 Sieving
Sieving on the above samples (Samples 1, 2, 3, 4 and 6) were carried out to determine the
percentage passing of all the samples so that blending of the different samples can be arrived
at to conform within the specified limit for Dense Bituminous Macadam (DBM). The
following table (Table 1) gives the percentage passing of all of the supplied samples with the
required specified grading.
Table1: Sieve analysis of the supplied samples with specified grading
Percentage Passing of Individual Aggregate
Sieve
Size S126.5mm S213.2mm S3 - 6mm River Sand Cement
37.5
26.5
19
100.00
92.68
5.34
100.00
100.00
95.70
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Specified
Limit
100
90 - 100
71 - 95
13.2
4.75
2.36
0.3
0.075
0.00
0.00
0.00
0.00
0.00
52.95
0.00
0.00
0.00
0.00
100.00
48.49
2.51
0.30
0.20
100.00
100.00
99.60
40.16
3.61
100.00
100.00
100.00
100.00
57.61
56 - 80
38 - 54
28 - 42
7 - 21
2-8
Speion
100
90-100
71-95
56-80
38-54
28-42
7-21
2-8
Results
81.12
48
609.1 Cst.
4. MARSHAL METHOD
The Marshall Method consists of the following major steps:
1. Aggregates are blended in proportion to meet the specification (Table 2).
2. The mixing and compacting temperatures for the asphalt cement being used are obtained
from the temperature-viscosity graph. These temperatures are those required to produce
viscosity of 170 20 centistokes for mixing and 280 30centistokes for compacting.
For determining the mixing and compacting temperature of the mix, viscosity test on the
supplied bitumen (Sample 7) was carried out. The result is shown in the figure below
(Figure 1).
Viscosity (Cst)
10000
1000
100
10
85
105
125
145
165
185
205
Temperature(degree centigrade)
Figure 1: Determination of Mixing and Compacting Temperature
From the above figure the mixing temperature at 170 20 centistokes (150Cst 190 Cst)
is between 164.87C to 170.93C and for Compacting temperatures at 280
30centistokes is between 152.31C to 157.83C.
Note:
Mixing Temperature:
164.9C to 170.9C
Compacting Temperature:
152.3C to 157.8C
3. A number of briquettes, 101.6mm (4 in) in diameter and 60-65mm (2 1/2 in) high, are
mixed using 1200 gm of aggregates and asphalt cement content at various percentages
both above and below the expected optimum.
4. The required % passing and weight of individual samples for each sieve size for the
blended sample is determined and weighted. The briquette is prepared for a particular
percentage of bitumen to determine the following required steps.
5. Density of the briquettes is measured after coating the samples with paraffin wax to allow
calculation of the voids properties.
6. Briquettes are heated to 60C. Stability and Flow values are obtained in compression test
in the Marshall apparatus to measure strength and flexibility. The stability is the
maximum load the briquettes can carry. The flow is the compression (measured in units of
hundredths of an inch or in millimeters) that the sample undergoes between no load and
maximum load in the compression test.
14.2
14
13.8
13.6
13.4
13.2
13
12.8
3.75 4.25 4.75
1600
1500
Stability (kg)
2460
2450
2440
2430
2420
2410
2400
2390
3.75 4.25 4.75 5.25 5.75 6.25
Bitumen Content, Percent
1400
1300
1200
1100
1000
3.75 4.25 4.75 5.25 5.75 6.25
Bitumen Content, Percent
VFB, Percent
VMA, Percent
Density kg/cum
5. RESULTS
Results of the analysis that was carried out and plot between densities vs. % bitumen content,
stabilities vs. % bitumen content, voids in mineral aggregates vs. % bitumen content, voids
filled with bitumen vs. % bitumen content, air voids vs. % bitumen content and flows vs. %
bitumen content are given in the following figures.
100
95
90
85
80
75
70
65
60
3.75
4.5
Flow, mm
3
2
6.25
6.25
3.5
3
2.5
1
0
3.75
6.25
2
3.75
Figure 2: Test property curves for Dense Bituminous Macadam by the Marshall Method
9) IS: 2386 (Part 1) (1963) Methods of Test for Aggregate for Concrete. Particle Shape
and Size Bureau of Indian Standard, New Delhi.