Final ToR 4 6 09 PDF
Final ToR 4 6 09 PDF
TABLE OF CONTENTS
1.0
2.0
INTRODUCTION
1.1
2.2
3.0
BACKGROUND
5
10
10
12
14
3.1
14
3.2
14
3.3
15
15
16
19
25
25
3.4
STAKEHOLDER CONSULTATION
25
3.5
EIA SCHEDULE
32
4.0
33
4.1
34
4.2
FIELD STUDIES
34
ERM
List of Tables
Table 1.
Table 3.
17
Table 4.
21
Table 5.
21
Table 6.
22
Table 7.
23
Table 8.
26
Table 9.
27
Table 2.
32
List of Figures
Figure 1. Project Infrastructure
13
15
Box 1.
11
ERM
ii
1.0
INTRODUCTION
Alcoa and the Greenland Home Rule Government (GHR) propose to build
a state-of-the-art aluminum smelter in Maniitsoq, West Greenland, with
supporting facilities including hydropower stations at Tasersiaq (referred
to as the North Hydropower Development) and Imarsuup Isua (referred
to as the South Hydropower Development) to provide electrical power to
the smelter, transmission lines to connect the smelter with the
hydroelectric facility, and a harbor for importing and exporting Projectrelated materials. For the purposes of this document, these four facilities
are collectively referred to as the Project (Figures 1 and 2).
An Environmental, Social, and Health Impact Assessment (EIA) is
currently underway to document the potential effects of the Project and
recommend measures to manage (maximize positive and minimize
negative) and monitor those effects.
The purpose of this final Terms of Reference (ToR) is to outline the process
for conducting the Project EIA. Specifically, the ToR sets objectives,
defines the scope, and establishes the strategy and schedule for the EIA
process. The draft ToR was initially open for public comment until March
1, 2009. The comment period was extended until March 31, 2009 to ensure
adequate opportunity for the public to comment on the draft ToR.
1.1
BACKGROUND
In 2006 Alcoa initiated formal discussions with the GHR regarding the
potential to construct an aluminum smelter and associated infrastructure,
including a hydroelectric development, transmission lines, and a harbor,
in western Greenland. Initial discussions between Alcoa and GHR
prompted the GHR to commission a working group to identify the
infrastructure and environmental issues related to the Project. The
working group delivered a preliminary report to parliament in March
2007, which recommended that the GHR conduct a Strategic
Environmental Assessment (SEA) to compare the advantages and
disadvantages of siting alternatives for the Project and to recommend
additional studies to be carried forward if the Project progressed to a
formal impact assessment.
The GHR issued a draft SEA in December 2007, which assessed several
potential locations for the smelter and port in Sisimiut, Maniitsoq, and
Nuuk based on existing information on the environment, human health,
ERM
ERM
ERM
ERM
2.0
2.1
ERM
Table 1.
Standard/Guideline
Description
European Union
Environmental Impact
Assessment (EIA) Directive
Arctic Environmental
Protection Strategy Finnish
Ministry of the Environment
ERM
Table 2.
Agreement/Convention
Vienna Convention for
the Protection of the
Ozone Layer, 1985
Montreal Protocol on
Substances that Deplete
the Ozone Layer, 1989
United Nations
Framework Convention
on Climate Change
(UNFCC), 1994
Kyoto Protocol, 1997
Rotterdam Convention,
1998
The Stockholm
Convention, 2001
Convention on the
International Maritime
Organization, 1948
Convention on the High
Seas, 1958
Convention of the
Prevention of Marine
Pollution by Dumping of
Wastes and Other Matter
(London Convention),
1972
ERM
Description
CLIMATE CHANGE/AIR QUALITY
Protection of the ozone layer, came
into force in 1988,
Protection of the ozone layer.
Status
Denmark ratified for
Denmark in 1985 and for
Greenland in 1991
Denmark acceded in 1987
and subsequently ratified
the amendments.
Ratified by Denmark in
1993.
Ratified by Denmark in
2002.
Ratified by Denmark in
1982.
Ratified by Denmark in
1994.
Ratified by Denmark in
2004.
Ratified by Denmark in
2003.
Denmark is a member
since 1959.
Denmark ratified in 1968.
Ratified by Denmark in
1997 and passed enacting
legislation in 2006.
Agreement/Convention
International Convention
on the Prevention of
Pollution from Ships
(MARPOL), 73/78
Description
Preservation the marine environment
through the elimination of pollution
by oil and other harmful substances
and the minimization of accidental
discharge of such substances. Annexes
cover oil, noxious liquid substances
carried in bulk, harmful substances
carried in packaged form, sewage,
garbage, and air pollution.
International Convention
Protection of safety of merchant ships
for the Safety of Life at
(regulations regarding emergency
Sea (SOLAS), 1974
equipment, safety procedures, etc.).
United Nations
All aspects of ocean space, e.g.
Convention on the Law of delimitation, environmental control,
the Sea (UNCLOS), 1982
marine scientific research, economic
and commercial activities, transfer of
technology and the settlement of
disputes relating to ocean matters.
International Convention
Establishes uniform principles
on Load Lines, 1966
governing the safe loading of ships on
international voyages. Includes
regulations for determining the
location of ships load lines.
BIODIVERSITY/PROTECTED AREAS
Convention on Wetlands
The conservation and sustainable
of International
utilization of wetlands, i.e. to stem
Importance especially as
progressive encroachment on and loss
Waterfowl Habitat
of wetlands now and in the future,
(Ramsar Convention),
recognizing the fundamental
1971
ecological functions of wetlands and
their economic, cultural, scientific, and
recreational value.
Convention on the
To ensure that international trade in
International Trade of
specimens of wild animals and plants
Endangered Species of
does not threaten their survival.
Wild Fauna and Flora
Accords varying degrees of protection
(CITES), 1973
to more than 33,000 species of animals
and plants.
United Nations
Promotes development of national
Convention on Biological
strategies for the conservation and
Diversity, 1992
sustainable use of biological diversity.
Often seen as the key document
regarding sustainable development.
United Nations
To combat desertification and mitigate
Convention to Combat
the effects of drought through national
Desertification, 1994
action programs that incorporate longterm strategies supported by
international cooperation and
partnership arrangements.
Ottawa Declaration, 1996
Established the Arctic Council as an
intergovernmental forum to promote
coordination among Arctic States,
with the involvement of the Arctic
Indigenous communities and other
inhabitants on common Arctic issues,
in particular issues of sustainable
development and environmental
protection in the Arctic.
ERM
Status
Denmark acceded in
1980.
Ratified by Denmark in
2004.
Ratified by Denmark,
unknown date.
Ratified by Denmark in
1977.
Entered in force in
Denmark in 1977.
Ratified by Denmark in
2002.
Ratified by Denmark in
1985.
Agreement/Convention
Strategic Plan for the
Conservation of Arctic
Biological Diversity, 1998
Description
Gives effect to the Conservation of
Arctic Flora and Fauna (CAFF)
program, through the development of
a long-term plan based on five priority
objectives.
Status
Denmark has been a
participant in CAFF since
its establishment in 1996.
Denmark is a
participating country
since 1952.
UNESCO Convention
Concerning the Protection
of the World Cultural and
Natural Heritage, 1972
(World Heritage
Convention)
Constitution of the
International Labor
Organization
ERM
CULTURAL HERITAGE
Promotes cooperation among nations
to protect heritage from around the
world that is of such outstanding
universal value that its conservation is
important for current and future
generations.
LABOR/HEALTH/SAFETY
Promotes opportunities for women
and men to obtain decent and
productive work, in conditions of
freedom, equity, security and human
dignity.
OTHER
Sets out the obligations to assess the
environmental impact of certain
activities at an early stage of planning.
Also lays down the general obligation
to notify and consult each other on all
major projects under consideration
that are likely to have a significant
adverse environmental impact across
boundaries.
Promotes active international
cooperation between the contracting
Parties, before, during and after an
industrial accident.
Ratified by Denmark in
1979. Ilulissat ice fjord in
Greenland is a World
Heritage Site.
Entered in force in
Denmark in 2000.
2.2
ERM
10
ERM
11
ERM
12
Figure 3.
Commitments carried
into contractual
obligations, Contractor
Management Plans
Where appropriate,
corrective action and
continuous
improvement
Commitments
implemented by Alcoa
and contractors
Inspection, monitoring,
and reporting
ERM
13
3.0
As per international standards and guidelines, the Project EIA will assess
all components and phases of the Project, including the smelter,
hydroelectric facilities, transmission lines, and port during the
construction, operation, and decommissioning phases of the Project.
3.1
3.2
ERM
14
SCOPING/ TERMS OF
REFERENCE
Stakeholder Consultation
3.3
STUDIES
IMPACT ASSESSMENT/
MANAGEMENT PLANS
DISCLOSURE
IMPLEMENTATION
Scoping Phase
Scoping is the initial phase of the EIA process. In the Scoping Phase, key
issues to be investigated and assessed during the subsequent phases of the
process are identified, and the range and extent of the studies to be
conducted is determined. The primary Project stakeholders are also
identified during the Scoping Phase. The Scoping Phase for the Project
was initiated in mid September 2008, and continued through March 2009
ERM
15
when the final Terms of Reference was completed. Public input was a
critical component of the Scoping Phase.
During the Scoping process desktop analyses, stakeholder interviews, and
public meetings were conducted to ascertain whether additional
information is needed to evaluate baseline conditions and potential
impacts within the Project area. The desktop evaluation included reviews
of pertinent environmental and social data collected from external sources
and previous studies of the Project area. The Project proponents met with
stakeholder groups (e.g., local governmental agencies, district agencies,
NGOs, and representatives of local population centers) to discuss the
scopes of the proposed studies including alternatives and the criteria for
the impact assessment and determine if additional baseline data will be
required for a comprehensive analysis. The key objectives for the Scoping
Phase were to:
Identify stakeholders and inform them of the Project and the EIA
process;
Study Phase
The Study Phase is the second step in the EIA process. In the Study Phase,
desktop and field studies are conducted to evaluate the key issues
identified during the Scoping Phase. The goals of the Study Phase are to
provide a detailed description of the affected area and establish the
environmental and social baseline that will be used in the Impact
Assessment Phase. The Study Phase for the Project was initiated in the
spring of 2008 and will continue through the end of 2009. ERM is
cooperating with several Government and non-government partners
including the Greenland Institute of Natural Resources, Greenland
National Museum, and the Danish National Environmental Research
Institute to conduct these studies.
Table 3 contains the preliminary list of studies that will be conducted as
part of the EIA. This list may change based on study results and
stakeholder consultations. Section 4 of the ToR contains detailed study
scopes for several of the key studies listed in Table 3. Studies with an
ERM
16
asterisk following their name have detailed study scopes in Section 4. The
remainder of the studies will be scoped prior to initiation.
Table 3.
Reference
Number
1
3
4
Approach
Schedule
May 2008
September 2010
Spring 2009
AugustSeptember 2008
(3 week field
survey period).
ERM
Marine resources*
Meteorological conditions
study*
17
May/June 2009
Winter survey
2009 possibly
required, based
on results of
2008 survey.
Site-specific
studies of
important char
areas in August
or September
2009.
Summer 2008,
prior to char
and freshwater
biodiversity
study
Summer 2008;
Summer 2009 if
necessary
Spring and
summer 2009
Mid-July 2009
(moulting)
Late July-mid
August 2009
(foraging)
2008-2009
Reference
Number
10
Study Title
Surface water,
groundwater, and
hydrographic analysis*
Approach
Schedule
2008-2009
Includes:
Daily average stream flows in the
Sarfartoq and Igassup Kua Rivers for
a minimum one year period (can
likely get this from historical data)
Water quality data in the Sarfartoq
and Igassup Kua Rivers and the
Project reservoirs (including
dissolved oxygen, temp, conuctivity,
and turbidity at a minimum)
Pre- and post-Project reservoir
boundaries (CADD or GIS format;
PB has these)
11
Sedimentation analysis*
12
Natural resources,
livelihoods, and cultural
change study*
13
Socioeconomic and
planning study*
Groundwater analysis:
Water table elevation
Transmissivity
Groundwater quality
Characterization of sediment transport
from reservoirs through hydropower
developments and into tailwaters, and
rate of sediment deposition in the
reservoirs.
Project-specific analysis of culture of
affected communities (may include oral
histories, ethnography, archival
research, semi-structured interviews).
Livelihood group-focused research
subsistence and commercial resource
use. Field methods TBD (may include
focus groups, semi-structured
interviews, data collection from
government or associations)
complementary to data collection in
demographics/socioeconomics above
National and regional data on general
socioeconomic conditions
2008-2009
2008-2009
(synchronized
with above)
2008-2009
(fieldwork
expected 2009)
ERM
14
15
18
Summer 2008
and 2009
Spring/summer
2009
Reference
Number
16
17
Study Title
Ecological and human
health risk assessment*
Topographic analysis
Archaeology studies
Geotech permafrost borings
Sub-glacial survey
Transmission line study
Freshwater birds
Approach
Schedule
2009 data
gaps follow-up;
ecological and
health risk
assessments
Summer 2009
2008-2009
2009
2008-2009
2008
2008
2009
Summer 2009
ERM
19
Likelihood
Enhancement
Low
Medium
High
High level of
enhancement
Moderate
Major
Major
Medium level of
enhancement
Minor
Moderate
Major
Minor
Moderate
Minor
Minor
Moderate
Medium severity
Minor
Moderate
Major
High severity
Moderate
Major
Major
ERM
20
ERM
21
Table 4.
Low
Medium
High
Affects environmental conditions, species and habitats for the long term (i.e., over
the life of the Project) may substantially alter the local and regional ecosystem and
natural resources, and may affect sustainability. Regeneration to its former state
would not occur without intervention.
Affects environmental conditions or media over the long term, has local and
regional affects and/or is irreversible.
Table 5.
Extent
Low
Benefits will be
short term.
Benefits to a few
species, habitat,
and resources in
the local
environment
only.
Minor benefits to
species, habitat,
and natural
resources that
provide minor
opportunities for
sustainability.
Medium
Benefits will be
measurable in
the short term
and possibly
longer.
Benefits to many
species, habitats
and natural
resources in the
local
environment and
beyond.
Moderate
benefits to
species, habitat,
and natural
resources that
may provide
opportunities for
sustainability.
High
Benefits will be
sustained over
the long term.
Benefits will
extend beyond
local
environment (i.e.,
linkage of
fragmented
habitat, e.g.,
regional corridor)
Direct benefits to
species or
resources will
provide
significant
opportunities for
sustainability.
ERM
22
Table 6.
Duration
Extent
Ability to Adapt
Socio-cultural
Outcome
Health Outcome
Low
Short-term
Inconvenience
but with no
consequence on
long-term
livelihoods,
culture, quality
of life, resources,
infrastructure
and services.
Event resulting
in annoyance,
minor injury or
illness that does
not require
hospitalization
Medium
Medium-term
Small
Those affected will
number of be able to adapt to
households change, with some
difficulty, and
maintain preimpact livelihoods,
culture, quality of
life and health but
only with support
Primary and
secondary
impacts on
livelihoods,
culture, quality
of life, resources,
infrastructure
and services
Event resulting
in moderate
injuries or
illness, which
many require
hospitalization
Large part
of/ full
settlement
Widespread and
diverse primary
and secondary
impacts likely to
be impossible to
reverse or
compensate for.
Catastrophic
event resulting
in loss of life,
severe injuries or
chronic illness
requiring
hospitalization.
Project
operation
period,
intermittent
frequency
High
Long-term/
Irreversible
Permanent,
constant
frequency
ERM
23
Table 7.
Extent
Degree of Change
Focus/ Sensitivity
Benefits will be
short-term (up
to a year)
Benefits to few
individuals/
households
either in the
local area
and/or further
afield.
Some benefits to
individuals and
communities,
potentially improving
opportunities for
furthering themselves
and improving
livelihoods
Medium level
Benefits will be
of enhancement felt for a
medium period
of time (1 to 7
years) or be
intermittent
over the longer
term
Benefits to
many
individuals
and
households in
the local
community
and beyond
Moderate benefits to
individuals and
communities which
will provide some
opportunities for
furthering themselves
and improving
livelihoods
Benefits will
possibly pertain to
vulnerable groups
and those that might
have been losers
from the Project
High level of
enhancement
Benefits
throughout the
local
community
and beyond to
State/
National level.
Direct benefits to
individuals and
communities will
provide significant
opportunities for
leveraging secondary
benefits and
significantly improving
livelihoods for
themselves and others
Low level of
enhancement
Benefits will be
lasting and
sustained over
the long term
i.e.: more than 7
years
ERM
24
Monitoring Plan - this plan will comprise the follow up and other
monitoring measures recommended by the EIA team to be
implemented during the construction and operation phases of the
Project.
Disclosure Phase
During the Disclosure Phase, the results of the EIA will be submitted to
the GHR Ministry of Environment and presented to the public, who will
be given the opportunity for review and comment. Public access to the
document will be provided through several venues. The public will be
able to review the full-text of the report and full details of the analysis will
be provided to the local media. Public meetings will be held during this
time and will be attended by representatives of ERM and the Project
proponents.
Implementation Phase
If the Project is approved after the Disclosure Phase, the Implementation
Phase commences with the implementation of recommended ESMPs
during the design, construction and operation phases of the Project.
Monitoring activities of any potential impacts identified during scoping
are initiated to verify that the EIA findings are correct and that
appropriate mitigation and prevention measures are properly
implemented.
3.4
STAKEHOLDER CONSULTATION
Stakeholder consultation is an important component for any new project
Alcoa undertakes anywhere in the world and it is a key aspect of the EIA
process. The consultation process gives stakeholders an opportunity to
learn about the Project, raise concerns, understand the potential effects,
and comment on the Project as well as on the reports that are produced
during each phase of the EIA.
Table 8 summarizes the key stakeholder consultation activities planned
for each phase of the EIA. This plan is adaptive and subject to change
based on stakeholder responses and Project requirements. A combination
of various types of consultation techniques will be used including face to
face meetings, focus group discussions (discussions with sub groups
within communities like women, youth, and indigenous people), public
meetings, and sample household socioeconomic surveys. The concerns
and issues that are expressed by the stakeholders during the consultations
will be recorded and disclosed in the EIA. Table 9 contains a summary of
ERM
25
EIA Phase
Consultation Plan
Scoping Phase
Impact Assessment
Phase
ERM
Estimated
Timeframe
September 2008
September 2008
Discussions with:
NERI
National Museum
Sisimiut
Nuuk
Maniitsoq
Distribution of draft ToR to key stakeholders including
government ministries and community leaders.
January 2009
January 2009
26
January 2009
January 2009
January 2009
January
December 2009
May 2009
EIA Phase
Disclosure Phase
Consultation Plan
Qualitative discussions/ Focus Group
Discussions with communities in:
Sisimiut
Nuuk
Maniitsoq
Kangaamiut
Napasoq
Study update meeting to be held in Maniitsoq and
possibly Sisimiut, Nuuk, and Kangaamiut
After the first draft of the EIA has been prepared
another round of consultations will be held to
share initial findings and solicit stakeholder
feedback on the EIA.
Table 9.
Estimated
Timeframe
May 2009
October 2009
March 2010
April 2010
End of May 2010
June 2010
Issue
Sub-Issue
Company
Performance
Previous
Experience
Employment
Availability of
Jobs
Nationality of
Employees
Workforce
Development
ERM
27
Issue
Sub-Issue
Cumulative
Impacts
Other Industrial
Developments
Energy
Transmission
Capacity
Health
Health Impact
Health Services
Information/
Communication
Contact Point
Studies/Access
to Information
Safety
Infrastructure &
Planning
ERM
Capacity of
Existing
Infrastructure
28
Issue
Sub-Issue
Access Around
Planned
Infrastructure
Livelihoods of
Hunters and
Fishers
Consultation
Potential
Environmental
Damage
Fear that hunting areas around Paradise Valley and the lake
in Nuuk will be damaged as a result of construction of the
Project.
History of
Hunting
Practices/
Folklore
ERM
29
Issue
Sub-Issue
Resource
Availability
Safeguarding
Fishing/
Hunting Cabins
Natural
Resources
Biodiversity
ERM
30
Issue
Sub-Issue
Land Change
Pollution
Water Quality
CO2 Emissions
Waste Discharge
Production
Capacity
Smelter
Capacity
Project Siting
Selection
Social Impacts
Concern About
Potential
Conflict
Social Impact
Assessment
ERM
31
Issue
Sub-Issue
Stakeholder
Engagement
Future
Consultations
3.5
EIA SCHEDULE
Table 10 summarizes the schedule for implementing the EIA for the
Project. This schedule is based on the Project proponents proposal to
initiate construction in late 2010 so that the Project can be operational by
2014. The EIA schedule is subject to change based on Project needs and
development schedule.
Table 10.
Schedule
EIA Task/Activity
May through
September 2008
September 2008
September through
January 2009
February 2009
March-April 2009
October 2009
March 2010
Prepare Draft EIA and hold Draft EIA public disclosure meeting
April 2010
June 2010
ERM
32
4.0
Visual/aesthetics
Natural hazards
Social:
Health:
ERM
33
4.1
whether the current existing baseline data is still valid and sufficient
or should be updated and extended through primary research; and
One of the primary sources for desktop research will be the SEA report
(GHR, 2007). For some resources, desktop studies will be sufficient for the
impact analysis. For most resources, field studies will be necessary, as
detailed in the following section.
4.2
FIELD STUDIES
The following section provides brief summaries of the objectives, scopes,
and schedules for the field studies to be conducted by ERM and their
partners as part of the EIA process. Note that some 2009 field studies will
not be scoped until spring 2009 so the study plans are not included in this
ToR.
ERM
34
4) Habitat modeling using snow distribution in the fall, winter, and spring;
vegetation mapping; and a digital terrain model.
Work Products
Reports and maps that combine the data from satellite collars, vegetation maps,
and terrain models to document the spatial and seasonal distribution of caribou
and migration routes in the study area. The data will identify preferred
locations of Project-related infrastructure to minimize impacts on caribou.
Schedule and Study Partners
Schedule: Field work for this study began in May 2008 and will continue
through September 2010
Study Partners: GINR and NERI
ERM
35
Objective
To determine the location of important foraging and calving habitats for
caribou.
Approach
The caribou calving grounds study program
consists of three parts:
1) An aerial transect survey to locate caribou
calving grounds between Sukkertoppen
Iskappe and Godhbsfjorden.
2) Analysis and preparation of maps
documenting the calving grounds,
including maps of calving grounds overlaid on
vegetation maps. The maps will be used to
identify preferred siting of proposed Projectrelated infrastructure to minimize impacts on caribou.
Caribou calf
Work Products
The caribou calving grounds study will produce a report indentifying the
most important caribou calving areas in the study area. The report will
include maps of the caribous calving areas overlaid on vegetation maps.
Schedule and Study Partners
Schedule: June 2009
Study Partners: GINR and NERI
ERM
36
The noise study will produce a noise model that predicts the magnitude and
extent of noise produced at the proposed smelter and quantifies the increase
in noise energy that would occur over existing conditions.
Schedule and Study Partners
Schedule: December 2008 January 2009
Study Partners: None
ERM
37
38
Approach
Conduct semi-structured qualitative interviews with fishermen in Maniitsoq
on the following topics:
1) Identifying key recreational, subsistence, and commercially fished species;
2) Locating and delineating important areas for fishing;
3) Identifying the most productive fishing seasons; and
4) Understanding historical fluctuations in the abundance of preferred
species.
Work Products
The consultation with fishers study will produce a report that describes local
knowledge of habitat requirements and seasonal movements of locally
significant aquatic biological resources.
Schedule and Study Partners
Schedule: Field work for this study began in August 2008 and will continue
in 2009.
Study Partners: NERI
ERM
39
ERM
40
Approach
Research will include a desktop component and may include a field
component, depending on the availability and quality fo existing marine
resources data. Desktop research will consist of the following tasks:
1) Reviews of existing scientific literature on the species composition,
distribution, and habitat requirements of the marine resources in the
vicinity of the proposed port.
2) Determination of the worldwide conservation status and sensitivity to
disturbance of marine resources that occur in the vicinity of the proposed
port.
Work Products
The marine resources study will produce a report that describes the species
composition, distribution, and conservation status of marine resources in the
vicinity of the proposed port.
Schedule and Study Partners
Schedule: Desktop study will occur from March through May 2009. If field
research is required, the scope and schedule for field study will be determined
in May 2009.
Study Partners: To be determined.
ERM
41
Approach
The aerial survey of goose moulting areas consists of two parts:
1) Review of existing scientific literature on the species composition,
distribution, and habitat requirements of White-fronted and Canada
geese in the areas potentially affected by the proposed hydro projects.
2) An aerial transect survey using a twin-engined Partenavia Observer
aircraft will identify the location of geese moulting areas in the vicinity
of the proposed hydro projects.
Work Products
The aerial survey of goose moulting areas will produce a report that describes
the moulting and foraging areas for Greenland White-fronted and Canada
geese in the vicinity of the proposed hydro projects.
Schedule and Study Partners
Schedule: Mid-July 2009
Study Partners: NERI
ERM
42
Work Products
The meteorological conditions study will produce a report that describes the
local climate and weather patterns in the vicinity of the smelter site.
Schedule and Study Partners
Schedule: January 2009 December 2009
Study Partners: Masanti
ERM
43
Approach
Field study will include the following tasks:
1) Measurement of river stage data over several months from the following
rivers:
a) Igassup Kua River;
b) Sarfartoq River; and
c) Arnagarnup Kua River.
2) Measurement of lake levels at the following locations:
a) Tasersiaq;
b) Tuvssp tasia; and
c) Additional unnamed lakes in the southern development.
Work Products
The surface water, groundwater, and hydrographic analysis will describe the
seasonal fluctuations in water level and flow in the rivers and lakes in the
areas potentially affected by the proposed hydro projects.
Schedule and Study Partners
Schedule: Field work for this study began in 2008 and will continue in 2009.
Study Leader: PB Power
ERM
44
Approach
Research will consist primarily of field study including the following tasks:
1) Characterization of dominant sediment type(s), rate of deposition, and
transport characteristics in the following rivers:
a) Igassup Kua River;
b) Sarfartoq River; and
c) Arnagarnup Kua River.
2) Characterization of dominant sediment type(s) and rate of deposition in
the following lakes:
a) Tasersiaq;
b) Tuvssp tasia; and
c) Additional unnamed lakes in the southern development.
Work Products
The sedimentation analysis will produce a report that describes the sediment
transport and deposition in the areas potentially affected by the proposed
hydro projects.
Schedule and Study Partners
Schedule: Field work for this study began in 2008 and will continue in 2009.
Study Leader: PB Power
ERM
45
Approach
Research will include desktop and field investigations and examine the
following topics:
1) Use of the natural resource base, including spatial and temporal variations
and the factors that explain such variations (climatic, technological,
cultural, etc. and the interplay with hunting, fishing, herding and
tourism), specific user groups, belief systems concerning the environment;
2) Livelihoods, including income, adaptability/substitution, and other
dimensions like food insecurity, social inferiority, exclusion, lack of
physical assets, and vulnerability;
3) Socio-cultural institutions, including formal and informal social
institutions:
a) Ways of coping with life through economy, social systems and cultural
values;
b) Social cohesion-the ways communities are organized and held together
by their social and cultural institutions and beliefs;
c) Identity- ways of life that communities value as expressions of their
identity;
4) Prevalent religions, including origin, practices and diversity;
5) Aesthetics, recreation and cultural relationship to the natural
environment, including the aesthetic and cultural character of a
community or neighborhood its ambience;
ERM
46
ERM
47
48
1)
2)
3)
4)
The study team will also liaise with Alcoas Human Resources and
Procurement personnel to fully understand the proposed Projects
employment, procurement, and infrastructure requirements.
Field research will consist of semi-structured qualitative interviews with the
following key leaders in Maniitsoq, Nuuk, and Sisimiut:
1) Elected leaders
2) Planning department staff and other labor and economic development
officials;
3) Other local decision makers/community leaders;
4) Owners and managers of businesses and educational or training
institutions.
Work Products
The socio-economic and planning study will produce a report that describes
sociology and land use in the areas of Project influence.
Schedule and Study Partners
Schedule: May - October 2009
Study Partners: NIRAS and/or other local experts
ERM
49
Approach
Field work for the landscape and scenic resources assessment will consist of a
photographic survey of the following sites:
1) smelter and port sites;
2) the proposed sites for selected above-ground components of the
proposed hydropower developments; and
3) road and transmission line alignments.
Work Products
The landscape and scenic resources assessment will produce a report that
describes and depicts the landscape and scenic resources in the areas of
Project influence.
Schedule and Study Partners
Schedule: August 2008-August 2009
Study Partners: None
ERM
50
Approach
Review existing data on rare plant locations and vegetation community
mapping and overlay data on maps of proposed Project infrastructure. Local
rare plant experts and international experts on fluoride-sensitive fauna will
conduct site-specific surveys during appropriate season (timing is speciesdependent).
Work Products
The rare and fluoride-sensitive flora study will produce a report that
describes the rare and fluoride-sensitive flora in the areas of Project influence.
Schedule and Study Partners
Schedule: Spring/Summer 2009
Study Partners: NERI (rare plants), Leonard Weinstein and Alan Davison
(fluoride-sensitive flora).
ERM
51
ERM
52
ERM
53
Work Products
The health study will produce a report that describes health conditions in the
areas of influence of the proposed Project, the potential health effects of the
proposed Project, and a management plan for addressing those effects.
Schedule and Study Partners
Schedule: May October 2009
Study Partners: Ministry of Health and other Greenlandic and Danish health
experts to be determined.
ERM
54