Exercise 2: Summary task, Early and Late Schedules, Critical Path, Floats
(Note: Continue the Road project in Exc. 1)
Create the following summary tasks and sub tasks as given below.
Site Clearance
Clearing and Grubbing
Dismantling Structures
Cutting of Trees
Excavation
In all types of soil
Ordinary Rock
Hard Rock
Construction of Embankment
Construction of Subgrade with approved material
Subbase and Base coarse
Construction of GSB
Construction of WMM
Construction of DLC
Construction of Bituminous coarse
Providing and laying Primer Coat
Providing and laying Tack Coat
Providing and laying DBM
Providing and laying Bituminous Concrete
Construction of Culvert
Earthwork
Backfilling
Providing Filter media
PCC M-25 for foundation and other works
Road Appurtenanences
Supplying and Fixing Traffic Sign Boards
Pavement Marking
Providing Mile stones
Drainage works
Finish
Link the tasks with the details given below.
ID
Task
1
2
3
4
5
Site Clearance
Clearing and Grubbing
Dismantling Structures
Cutting of Trees
Excavation
Duratio
n
Predeces
sor
5d
2d
2d
2
2
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1.
2.
3.
4.
10d
10d
15d
25d
15d
3
3
3
8,6,7
9
10d
10d
5d
10
12
13
5d
5d
5d
3d
12
16
17
18
2d
1d
1d
4d
3
21
22
22
1d
2d
1d
3d
0d
19
26
27
24
28,29,4,2
3,14
Summarise the project and note the project duration and project finish date
Forma the Gantt Chart to view critical tasks and critical path
View Schedule table and note the early schedule, late schedule and floats.
View Network Diagram. Study the critical path.
Milestone Schedule
To view Milestone Schedule: Project Filter forMilestones
Working with Resources
To create Resource Sheet: ViewResource Sheet
Max. Unit is the availability of work type of resources per day. It can be entered in decimal or
percentage.
To change the Assignment unit for Max. Unit type: ToolsOptionsScheduleShow
Assignment unit as, select the Assignment unit (decimal or percentage)
4
Type
Work
Work
Work
Material Label
Max. Unit
25
15
5
Std. Rate
Rs.15.00/hr
Rs.12.00/hr
Rs.25.00/hr
Ovt. Rate
Rs.30.00/hr
Rs.25.00/hr
Rs.50.00/hr
Supervisor
Work
4
Site Engineer
Work
1
Painter
Work
0
Cement
Material Bags
Sand
Material Brass
Aggregate
Material Brass
Steel
Material Kg
Water
Material 1000 Lit
Boulders
Material
JCB
Work
3
Dumpers
Work
6
Roller
Work
1
Paver
Work
2
Concrete Mixer
Work
1
Vibrator
Work
1
Water Pumps
Work
1
Assign the Project calendar to work type of resources.
Rs.30.00/hr
Rs.50.00/hr
Rs.0.00/hr
Rs.250.00
Rs.2,400.00
Rs.2,200.00
Rs.35.00
Rs.400.00
Rs.1,500.00
Rs.1,000.00/hr
Rs.300.00/hr
Rs.1,500.00/hr
Rs.2,000.00/hr
Rs.100.00/hr
Rs.30.00/hr
Rs.10.00/hr
Resources
Labour[3],Helper,Supervisior,Site Engineer,JCB,Dumpers[3]
Labour[3],Helper[2],Supervisior,JCB,Dumpers[3]
Labour[2],Helper[3],Supervisior,JCB
Labour[3],Helper[5],Supervisior,JCB,Dumpers[3]
Labour[3],Helper[5],Supervisior,JCB,Dumpers[3]
Labour,Helper[3],Supervisior,JCB,Dumpers[2]
Labour[3],Helper[5],Supervisior,Dumpers[5],Roller
Labour[3],Helper[5],Supervisior,Site Engineer,Water[1 1000
Lit],Roller
Labour[2],Mason,Helper[4],Supervisior,Site
Engineer,Dumpers[4],Roller,Water[1 1000 Lit]
Labour[2],Mason,Helper[4],Supervisior,Site
Engineer,Dumpers[4],Roller,Water[1 1000 Lit]
Labour[2],Helper[4],Mason,Supervisior,Water[1 1000
Lit],Paver,Concrete Mixer
Labour[2],Helper[4],Supervisior
Labour[2],Helper[4],Supervisior
Labour[3],Helper[6],Supervisior,Site Engineer,Paver
Labour[3],Helper[6],Supervisior,Site Engineer,Paver
Rs.60.00/hr
Rs.100.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Rs.0.00/hr
Bituminous Concrete
Earthwork
Backfilling
Providing Filter media
PCC M-25 for foundation
and other works
Supplying and Fixing
Traffic Sign Boards
Pavement Marking
Providing Mile stones
Drainage works
Do the Following.
1.
2.
3.
4.
Labour,Helper[2],Supervisior,JCB
Labour,Supervisior
Labour,Supervisior
Helper[4],Labour[2],Mason,Supervisior,Site Engineer,Concrete
Mixer
Supervisior,Helper[4]
Supervisior,Helper[4]
Supervisior,Helper[4]
Labour[2],Helper[4],Mason,Supervisior,Site Engineer,Concrete
Mixer,Vibrator
2.
3.
4.
5.
6.
Create a custom table named Bill of Quantity with the columns, Item, UOM, Quantity, Rate, and
Amount. Define the formula for as Amount = Quantity x Rate
Project Monitoring and Control
To save Baseline project: ToolsTrackingSave Baseline, Entire Project, Click on Ok.
To display the baseline bar in the Gantt chart: FormatGantt Chart
WizardNextBaselineFinishFormat itExit
Updating the Actual Progress
Auto Update is carried out when the work gets completed as per the baseline:
ToolsTrackingUpdate ProjectUpdate
To View the Progress Line: ToolsTrackingProgress Line, select the Always display current
progress line on status date
To Plot the S-curve: ViewTool barAnalysis. Select Analyze Time scaled data in Excel
Assignment Evaluation
1. Assignment 1: 26th November
2. Content: WBS, Task, duration, links (Complete time schedule) 20 Marks
Assignment 2:
Project Organisation, Milestone schedule, Resource load, Leveling resources