Testing Commissioning Process Light Rail Project
Testing Commissioning Process Light Rail Project
RAIL PROJECT
R. Sharma*
*Ove Arup & Partners Ltd, Infrastructure and Planning Midlands (Rail)
Blythe Valley Park, Solihull (West Midlands), B90 8AE, United Kingdom
Email: [email protected]
Abstract
This paper discusses a testing and commissioning model for a
typical light rail project. The paper does not propose a new
methodology or concept, but the idea is to consolidate
different testing and commissioning exercises into a generic
structure of stages, which can be applicable to any light rail
project. The various stages depend on the level of testing and
integration required as a project progresses from supply of
equipment and installation to integration and actual operation.
Systems integration is a vital aspect of the testing and
commissioning programme, and is discussed in brief in this
context. The documention and control necessary to complete
the testing and commissioning programme are also outlined.
1 Introduction
Testing and Commissioning (T&C) is a very important phase,
or series of activities, in the construction of a light rail system
before it can be safely opened for commercial operation. Like
in any other industry, T&C demonstrates that all technical and
project requirements, as developed during the concept and
design stages, are met. It ensures that interfaces between
different systems and with existing and third party systems
are systematically closed and integrated. T&C confirms that
the railway is ready to be taken over by the employer and/or
the operator.
a.
b.
c.
d.
e.
(i)
(ii)
(iii)
(iv)
4 Systems Integration
4.1 Definition and Context
Systems Integration (SI) is defined as the process of bringing
together of the component subsystems into one system and
ensuring that they function together as a system. Systems
integration activities correspond to the right hand side of the
famous V life-cycle, although they are generally planned
well in advance.
In T&C context, the SI process can be defined to occur once
each supplier has installed and tested his system in isolation
and is satisfied that it is ready to be integrated into the overall
system. In other words, SI begins during the SAT stage and
continues to the end of the commissioning stage until the
railway system becomes ready for commercial operation.
However, as indicated in Section 3, SI in reality does begin
off-site during the FAT stage itself and also progresses in the
SIT stage, albeit at a low level.
can take place independent of the T&C process for a new line.
This can happen, for example, when a new line is being
constructed or an exisitng line extended, thereby requiring
modification of exisiting equipment on an existing line.
4.2 Compliance
Third party systems can be integrated during the SATExternal stage. Replacement, upgradation and migration of
equipment can be carried out during the SATOV-Equipment
stage. Speaking of migration, some systems such as SCADA
can be tested independently using a test bench or a mimic and
then migrated to the actual central control room where the
original system gets upgraded. Finally, the train on-board
systems can be integrated during the SATOV-Line trail run
stage.
Conclusion
Limitations
Although this T&C process may be applicable to all rail
modes, due to limited research at this stage, it is felt that it
could only be applied to light rail systems. The paper
discusses a simple and broad T&C model and hence does not
identify the best practice or give actual results from real
projects.
Acknowledgements
This paper is based on the experiences gained during a two
month site-based placement. The author was seconded to
SomagueBowenSacyr Joint Venture (SBS-JV), the main
contractor responsible for the construction of a 7.5 km light
rail extension of the Dublin Luas Green Line in Ireland. This
extension project, called the Line B1 Infrastrcuture Works,
was awarded by the Railway Procurement Agency (RPA) of
Dublin, the Luas infrastructure owner. The line is scheduled
for opening in early 2011.